Title: Project Planning: Managing the Triple Constraints
1Project Planning Managing the Triple Constraints
2Session Focus
- Summary of Scope, Time Cost
- Review of project management terms techniques
for controlling Scope, Time Cost - Tools you can use to manage Scope, Time Cost
- Hands on introduction to the tools
3The Project Management Knowledge Areas
- 1. Project Integration
- 2. Scope Management
- 3. Time Management
- 4. Cost Management
- 5. Quality Management
- 6. Human Resource Management
- 7. Communications Management
- 8. Risk Management
- 9. Procurement Management
4Why do you need to be concerned?
- What impact do the triple constraints have on all
technology projects? - Why must Scope, Time and Cost be controlled?
5 Failure rates of Information Technology
Projects Standish Group findings-1994
6Triple constraints
7Scope
- Defined What is included in the project, as well
as what is to be excluded. - Management techniques
- Conduct a thorough needs analysis
- Define whats in and whats out
- Clearly identify the projects goal, objectives
and main drivers - Manage scope creep
8Project Scope Management Tools Techniques
- Scope Overview Project Overview Statement
summarizing the Project, Goal, Objectives,
Success criteria, Assumptions, Risks and
Obstacles - Scope Planning-Create a project scope management
plan documenting how the project scope will be
defined, verified, controlled, and how the work
breakdown structure will be created and defined. - Scope Definition-Develop a detailed project scope
statement as the basis for project decisions - Creation of a Work Breakdown Structure
(WBS)-Subdivide the major project deliverables
and project work into smaller, more manageable
components - Scope Verification-formalizing acceptance of the
completed project deliverables - Scope Control-controlling changes to the project
scope
9Why develop a Project Overview Statement?
- Answer To clearly define/articulate the purpose
of a project, the pros, cons and assumptions - Opportunity Why the project is being undertaken
- Goal-clearly defined
- Objectives-that drive project towards the goal
- Success Criteria-specific and measurable
- Assumptions that were made
- Risks-most probable
- Obstacles-and how to avoid
10Project Overview Statement-example
11Tool 1 Project Overview Statement.Your turn
12Presentation of results
- Tool 1 Project Overview Statement
- Questions/Comments
13Time
14Time management
- Defined A mechanism to ensure the project is
completed on time, within the resources
available, and avoids delays and associated cost
overruns - Management techniques
- Define project activities
- Estimate the activity duration using references,
professional contacts, actual task completion
personnel - Track progress using PM tools Gantt Chart, Work
Breakdown Structure, Network Diagram.
15Project Time Management Techniques
- Activity Definition
- Activity Sequencing
- Activity Resource Estimating
- Activity Duration Estimating
- Schedule Development
- Schedule Control
16Tool 2 Work Breakdown Structure (WBS)
- Work Breakdown Structure organizes and defines
all the project work - Work Breakdown Structure subdivides the project
into smaller, more manageable pieces of work - The lowest level, most detailed level of the Work
Breakdown Structure (work package) can be
scheduled and cost estimated
17WBS Elements and Example
- Elements
- Summary Description of Work
- Duration (time to complete)
- Deliverable (Unique Result of Above Work)
- Dictionary (adequately detailed description of
work) - Example
- 1. Concept
- 1.1 Business Plan
- 1.2 Resources and Budget
- 2. Content Development
- 2.1 Content Collection
- 2.2 Abbreviated outline
- 3. Media Distribution
- 3.1 Media Design
- 3.2 Production
18Work Breakdown Structure
19WBS.Your turn
20Presentation of results
- Tool 2 Work Breakdown Structure
- Questions/Comments
21Other tools
- Gantt chart
- Network Diagram
- Both based on the Work Breakdown Structure
22Gantt Chart
23Network Diagram
24Activity Definition
- The Activity Definition process identifies
deliverables at the lowest level (work package)
in the work breakdown structure. - Work packages are further broken down to provide
a basis for estimating, scheduling, executing,
and monitoring and controlling the project work.
25Activity Sequencing
- Activity sequencing involves identifying
documenting the relationships among schedule
activities - Network Diagram Schematic displays of the
projects schedule and the logical relationship
among them.
26Activity Resource Estimating
- Determining what resources (people, equipment or
material) will be needed, when and how much. - Tools Techniques
- Professional judgment
- Alternatives analysis
- Published estimating data
- Project Management software
- Bottom-up Estimating
27Activity Resource Estimating
- This process uses information from the scope of
work, required resources and quantities and
resource calendar. - The inputs for the estimates of schedule duration
originate from the person or group who is most
familiar with the required work.
28Activity Duration Estimating
- Tools Techniques
- Expert judgment
- Analogous estimating
- Parametric estimating
- Three-point estimates
- Reserve analysis
29Schedule Development
- Determines the planned start and finish dates for
the project activities. - Schedule estimates can require that time and
resource estimates are reviewed to create a
project schedule that can serve as a baseline
tracking tool. - Tools Techniques
- Schedule network analysis
- Critical path method calculates the possible
start and end dates for project activities and
the project overall.
30Schedule control
- Tools Techniques
- Progress reporting
- Schedule change control system
- Performance measurement to produce the schedule
variance - PM software
- Variance analysis
- Schedule comparison bar charts-comparison of
planned vs. actual schedules
31Cost
32Cost
- Defined The cost of all resources required to
perform and complete incremental tasks and the
overall project - Management techniques
- Gather internal and external costs.
- Look to vendor references
- Estimate recurring costs
- Usually 15 of initial hardware/software cost
33Project Cost Management Techniques
- Cost Estimating
- Cost Budgeting
- Cost Control
34Tool 3 Cost Breakdown Structure
35Tool 3 Cost Breakdown Structure..Your turn
36Presentation of results
- Tool 3 Cost Breakdown Structure
- Questions/Comments
37Cost Estimating
- Developing an approximate cost of the resources
needed to complete the project - Tools Techniques
- Analogous Estimating Based on similar projects
- Bottom-up Estimating Costs at lowest level are
rolled up for reporting and tracking - Parametric Estimating Base on statistical
information - PM software
- Vendor Bid Analysis
38Cost Budgeting
- Defined Total the estimated costs of different
work packages to establish a baseline for
measuring project performance. - Tools Techniques
- Cost Aggregation Scheduled activity cost
estimates are totaled in accordance with the WBS. - Parametric estimating Using mathematic models to
predict costs. - Reserve Analysis Establishes contingency
reserves - Funding Limit Reconciliation Work scheduled to
limit expenditures
39Cost control
- Cost change control system
- Performance measurement analysis
- Forecasting
- Project performance reviews
- Project Management software
- Variance management
40The news is getting better
- The 2003 Chronicles report shows some major
improvements. The report was based on analysis of
13,522 Information Technology (IT) projects - Projects meeting Scope, Time and Cost estimates
have increased from 16 to 34. - Project failures (cancellations) have decreased
from 31 to 15 - Cost overruns for approximately half of projects
decreased from over 180 to 43. - Time overruns have increased to 82 of projects.
- Large organizations currently net 52 of the
original functions and features in the end
product. This is a 10 increase.
41Session Focus Recap
- Scope, Time Cost
- Review of project management terms techniques
for controlling Scope, Time Cost - Tools you can use to manage Scope, Time Cost
- Hands on work with the tools
42Want to know more?
- Resources
- Law Enforcement Tech Guide (LETG)
- Project Management Book of Knowledge (PMBOK)
- Project Management Institute (www.pmi.org)
- The SEARCH technical assistance program
- PM courses and certificate programs
43Questions/Discussion