Title: Introduction To Critical Chain Project Management
1Introduction To Critical Chain Project Management
- Hilbert Robinson, Afinitus Group, LLC
- Robert Richards Ph.D,, Stottler Henke Associates,
Inc.
2Are You A Responsible Person?
- Scenario
- You live in New England and Its late Winter
- Time to airport varies from 45 minutes to 3 hours
depending - Most times it takes a little over 65 minutes
- You are Joining the President at 900 AM
- Question
- How early should you leave? __________
- Why?_____________________________
3Presentation Outline
- Background
- Triple Constraints
- Murphys Law
- Complexity
- Problem What to Change
- Localized Risk Management
- Task Level Insurance Policy
- Student Syndrome
- Parkinsons Law
- Multi-tasking
- Solution What to Change to
- Governing Principle - Global Risk Management
- Project Level Protection
- Systems Perspective
- Execution Control
4Background
- Triple Constraints Binding Commitments
- Time Minimize
- Capacity Minimize
- Content Maximize
5Background
- Murphys Law Disruption Event
- Number of unknowns
- Range of possibilities
- Frequency of repetition
- Complexity Amplification factor
- Degree of integration required
- Number of dimensions to be integrated
6Presentation Outline
- Background
- Governing Principle or Paradigm Shift
- Triple Constraints
- Complexity
- Murphys Law
- Problem What to Change
- Localized Risk Management
- Task Level Insurance Policy
- Student Syndrome
- Parkinsons Law
- Multi-tasking
- Solution What to Change to
- Governing Principle - Global Risk Management
- Project Level Protection
- Systems Perspective
- Execution Control
7The Problem Localized Risk Management Strategy
- Task level insurance policy
- See opening scenario answers?
- And if it was a task in a project??
- How safe is safe enough?
- Student Syndrome
- The dog ate my homework
- Parkinson's Law
- Self-fulfilling prophecy good estimating?
- Multi-tasking absence of priorities
- Hero or villain?
8Problem Localized Risk Management
One Resource, Four Task, from Four Different
Projects
Multi-tasking causes delays to spread across all
projects, adding as much as 20 to all projects
9
9Presentation Outline
- Background
- Governing Principle or Paradigm Shift
- Triple Constraints
- Complexity
- Murphys Law
- Problem What to Change
- Localized Risk Management
- Task Level Insurance Policy
- Student Syndrome
- Parkinsons Law
- Solution What to Change to
- Global Risk Management
- Project Level Protection
- Systems Perspective
- Execution Control
10Solution
- Governing Principle Behind CCPM is
- Aggregation of risk
- Benefits
- Lower overall protection needed
- Higher degree of coverage achieved
- Leading to lower incidence of failure
11SolutionGlobal Approach to Risk Management
- Planning
- Project Level vs. Task Level Protection
- Systems Perspective for Multiple Projects
- Should load for multiple projects be considered?
- Why?
- How?
- Execution Control
- Promote and encourage team culture
- Controlled work queues
- No multi-tasking work rules
- No batch processing work rules
- Task assignment prioritization
- Management by Exception
12Critical Chain Planning Process
From Task to Project Protection
1. Traditional Plan
2. Safety Excluded
3. Resource Leveled
4. Critical Chain Marked
13Aggregation Principle
The Concept of Risk Pooling Can someone explain
why this works? Health Care Example larger
pool lower cost
14Aggregation Principle
- Insurance is designed to work by spreading
costs across a large number of people. Premiums
are based on the average costs for the people in
an insured group. This risk-spreading function
helps make insurance reasonably affordable for
most people. - http//www.insurance.wa.gov/legislative/factsheets
/PoolingRiskReducingCost.asp
15Critical Chain Planning
Compared to 60 days traditional
PB Project Buffer FB Feeding Buffer
- Aggregation Principle where did some of the
safety go? - Pooled protection provides more coverage
- Location is just as important as amount
- Sizing Rule of Thumb ? 2/3rds to 1/3rd
- Buffer is half of preceding chain
16Critical Chain in Execution
Schedule Before Execution Starts
AS OF DATE
- T8 experienced a 5 day increase in scope or delay
- Results in a 2.5 day impact to the project buffer
- The rest was absorbed by the Critical Chain gap
4. 35-32.52.5 ?7 Complete and 14 Buffer
Consumed
17Perspective on Buffers
- Not rear view mirror watching
- Predictive/Preventative/Leading Indicator
- Mechanism to Promote and encourage Team Work
- Collaboration / Communication Incentive Mechanism
- Measuring device Neutral, Normalized Metrics
- Real-time Risk Meter
- Encourages an holistic/goal oriented perspective
18Critical Chain Priority Metric
- Project Status Trend Chart or Fever Chart
19Multi-Project System
- Systems Perspective for Multiple Projects
- Should load for multiple projects be considered
jointly? - Obviously
- Why?
- Prevent System Overload/Multi-tasking
- How?
- By taking a Systems Perspective
20Creating a Multi-Project Schedule
Finite Capacity Pipeline
Due Dates Are Derived
Ingredients
- CC Plans shorter
- Strategic Pacing Mechanism
- Strict Priority Scheme
- Rate Limit Policy/Guidelines
21Multi-Project Execution ControlPipeline Status
Snap Shot
In Execution, Buffer Status Drives Priority
Decisions, not Project Importance
1010
By Portfolio of Projects
22The Upshot
- Benefits
- Operational Coherence Stability
- 20 Shorter Cycle-Times Speed
- On-time Performance Reliability
- More throughput Growth
- Challenges
- 1. Simple but not easy to grasp too simple?
- Requires a change in mindset
- Takes 120 days for typical 100 person team
- We dont need that much improvement
23Questions???
- Hilbert Robinson, Afinitus Group, LLC
- www.afinitus.com
- Robert Richards Ph.D,, Stottler Henke Associates,
Inc. - AACE2009.R.RichardsPhD_at_Neverbox.com
- www.StottlerHenke.com