Title: 9. FIRE
19. FIRE
2Introduction
- Many fires are associated with the use of
high-risk materials and, through ongoing
legislation should result in continuing
improvements - it often takes several years before older,
high-risk materials are replaced. - In large or tall buildings, the much higher
potential risk resulting from reduced access of
emergency services has long been recognized
through again, fires still occur, sometimes due
to failure of one or two parts of the structure
to prevent fire spread. - Increasing attention is now being given to fire
stops in cavities, ducts and roof spaces.
3Combustion
- Three prequisites for a fire are
- Fuel
- Oxygen
- Heat
- 1. Fuel
- Almost all organic materials behave as fuels.
- Carbon and Hydrogen are the main constituents so
that the materials rich in these will be a
greater hazard and especially those rich in
hydrogen, such as oil products and gas, since
hydrogen generates more heat than carbon.
4- 2. Oxygen
- This is present in the form of air, diluted with
nitrogen which is inert. - Pure oxygen, sometimes stored in cylinders is
highly dangerous. - 3. Heat
- Heat causes
- Chemical decomposition of most organic materials
releasing volatile vapor. This effect is called
PYROLYSIS. - Reaction between both the solid and vapour
fraction and oxygen - C O2 ? CO2 heat (solid fuel)
- CH4 2 O2 ? CO 2H2O Heat (hydrocarbon fuel)
-
- These are combustion processes though it is the
reaction of vapor with oxygen together with
accompanying light emission that is described as
a FLAME
5Flame
- They are not necessary for fire but their
pressure usually increases the severity of a
fire. - Because
- Gases have much greater mobility than solids so
that flames help spread the fire. - The temperature in a flame is very high- usually
? 1200oC.
6Ignition
- The application of sufficient heat will initiate
the combustion process, which then generates more
heat and ultimately, when the temperature is high
enough, ignition or flaming will occur.
7Fire and Density
- The ideal for habitable buildings might be
considered to be avoidance of all combustible
materials. - Normally totally impracticable
- because organic materials are inseparably linked
to human comfort furniture, furnishings,
clothing- and to human activity-books paper and
implements. - In many cases for reasons of economy and/ or
convenience the enclosure itself will involve
combustible materials (wooden floors, doors,
window frames and partitions).
8Fire Load
- The risk presented by the combustible contents of
an enclosure is defined as FIRE LOAD. - Fire Load total mass of combustible contents
in the enclosure - expressed as wood equivalent per unit floor area.
- Fire Load Comb.mass/(m2 (floor))
- Higher fire loads produce longer duration fires.
9- Fire Severity
- Depends on
- Type and decomposition of combustible material,
- Ventilation characteristics
- good ventilation may reduce the durability of
fires by venting heat.
10Development of Fires
- Damage of fire depends on
- situation which give rise to it,
- the way in which it develops and spreads.
- In the early stages of most fires, spreading is
largely the result of flaming and localized heat
generation, - hence it requires materials which are not only
combustible but in a flammable form.
11 Flashover
- It is the most important stage in any fire (See
Figure 9.1). - Occurs when the air temperature in the enclosure
reaches about 6000C. - At that point, pyrolysis (vaporisation) of all
combustable materials takes place so that they
all become involved in the fire and flaming
reaches dramatic proportions, limited only by the
total fuel available and/or by the supply of air.
12Figure 9.1 BS476 tests relating to initiation,
growth, and spread of an uncontrolled fire in the
compartment of origin.
13- In many such fires, flaming occurs mainly outside
windows using to lack of air internally and this
helps spread the fire upwards to adjacent floors
of the building. - A priority in design for fire resistance is to
prevent or delay flashover since there is little
change of survival in an enclosure once this has
occurred.
14- The thermal inertia of the surfaces of an
enclosure is an important factor - highly conductive, heat absorbent materials such
as brick, help to delay the temperature rise as
well as being non-combustible. - Flashover may be prevented in poorly ventilated
closures due to lack of air for combustion, or
delayed in very large ones where there are large
volumes of air in relation to available fuel-they
have a cooling effect. - It is estimated at present that the fire services
arrive before flash-over in about 90 of fires.
15Fire Tests
- Fire tests attempt to classify materials and
components in relation to fire performance and
form the basis of Building Regulations. They
cover 2 chief areas - 1. The development and spread of fire.
- These tests include combustability, ignitibility,
fire propogation, spread of flame and heat
emission of combustible materials. - 2. Effects of fire on the structure, adjacent
structures and means of escape, the first
priority in any fire being the safety of the
occupants. - These tests are concerned with the structural
performance of buildings, their ability to
contain the fire and problems associated with
smoke.
16- Many of the above aspects are covered by BS476,
Figure 9.2. A brief resume of the contents of
parts relating to fire spread in current Building
Regulations is given in Table 9.1. - Examples on fires
- Collapse of World Trade Centers (New York)
17Figure 9.2 Five ways in which fire can be
initiated.
18Table 9.1 BS476 tests relating to fire
development and spread referred to in current
Building regulations.
19BURNING OF CONCRETE
20After Fire
- the amount of debris,
- blackening of the structure,
- Peeling,
- loss of finishes,
- can give the impression that the concrete
elements are severely damaged.
21Assessing fire-damage
- An inspection of the site including limited
non-destructive testing, sampling and laboratory
investigation to produce a repair classification
for each element. - Experienced practitioner can obtain a significant
amount of information during a site inspection. - Laboratory investigation is often critical to
establish the temperature achieved at different
depths in the concrete and thus the condition of
that element. - An indispensable technique is the investigation
in petrographic examination.
22General considerations
- Loss of strength and modulus of elasticity
- Concrete looses strength on heating.
- Residual strength of a concrete element after a
fire depends on several factors, for temperatures
up to 3000C the residual strength of
structural-quality concrete is not severely
reduced. - Concrete is unlikely to possess any useful
structural strength if it has been subjected to
temperatures above 5000C, the strength then being
reduced by about 80.
23-
- Typically, concrete made with lightweight
aggregate does not lose significant strength
until 500oC. - The effects of a fire on modulus of elasticity
are similar to the effects on strength. - Up to 300oC, the modulus of elasticity is not
severely reduced but by 800oC it may be as little
as 15 of its original value (85 loss).
24Effects of fire on reinforcement
- Steel looses strength on heating but
reinforcement is often protected from the effects
of fire by the surrounding concrete, which is a
poor thermal conductor. - Steel reinforcement suffers a reduction in yield
strength at temperatures above 450oC for
cold-worked steel and 600oC for hot-worked steel.
- Prestressed steel looses tensile strength at
temperatures as low as 200oC and by 400oC may be
at 50 of normal strength. - Buckling of reinforcement can occur at high
temperatures if there is restraint, for example
by adjacent elements, against thermal expansion.
25Spalling of concrete after fire
- In a fire, most concrete structures spall to some
extend, although lightweight aggregate concretes
are usually more resistant. - The surface can scale in the early stages of a
fire as the near-surface aggregate splits as a
result of physical or chemical changes at high
temperatures. - Explosive spalling also occurs in the early
stages of a fire but involves larger pieces of
concrete violently breaking away from the surface
and may continue from areas already spalled. Such
spalling usually results from high moisture
content in the concrete. - The thermal shock of a cold water on to hot
concrete during fire-fighting can also induce
spalling.
26Depth of damage
- Concrete is a poor thermal conductor and so high
temperatures will initially be confined to the
surface layer with the interior concrete
remaining cooler. - At corners where two surfaces are exposed to the
fire, the effect will penetrate further because
of the transmission of heat from the two
surfaces. - If concrete spalls early in a fire, the depth of
effect from the original surface will be greater
than if the concrete does not spall or if
spalling occurs later in the fire.
27Damage assessmentSite inspection
- Various features of the concrete and associated
materials in the fire-affected locations must be
noted and from these a visual classification of
the damage produced. - The Concrete Society report (CSTR 33) includes a
useful numerical classification and this is shown
in a simplified format in Table 9.2
28Table 9.2. CSTR 33 classification of fire damage.
29Damage assessmentSite inspection
- Firstly, the condition of any plaster or other
surface finishes is noted. - Surfaces may be sooty but otherwise unaffected by
the fire. - As the effects become more severe, the finishes
start to peel until they are completely lost or
destroyed. - Likewise, during the fire the concrete surface
will progressively craze until it is lost. - The concrete color may also be affected during
the fire, generally changing with increasing
temperature from normal through pink to red, then
whitish grey and finally buff.
30- The pink and red colours relate to the presence
of small amounts of iron in some aggregates,
which oxidise and can be indicative of particular
temperatures. - It is important to note that many concreting
aggregates do not change colour at temperatures
normally encountered in an ordinary fire. - Although colour change clearly indicates a
particular temperature, the absence of colour
change does not mean that the temperature was not
reached.
31Other site investigation requirements
- Cores - or, if these are not possible, lump
samples - should be taken for laboratory
investigation from a number of locations
representing the range of damage classifications
observed and should include comparable unaffected
concrete as a control. - Laboratory petrographic examination is necessary
to support and enhance the site findings.
32- The depth of cover to any reinforcement must be
measured during site investigation so that, once
the laboratory investigation has been completed,
it will be possible to determine whether the
steel is likely to have been affected by the
fire. - It is also possible to take steel samples for
laboratory analysis, but this is usually
necessary only if the visual inspection reveals a
cause for concern.
33Laboratory investigation petrographic examination
- Petrographic examination should be conducted by
someone experienced in the technique and in
examining fire-damaged concrete, and is best
performed in accordance with ASTM C856. - An initial low- to medium-power microscopic
examination of all cores allows the selection of
those for thin-section preparation and more
detailed examination with a high- power
microscope.
34- As well as identifying physical distress such as
cracking, this examination can identify features
that allow temperature contours' to be plotted
on the concrete. - Binocular examination allows contours to be
plotted that equate to around 300C provided the
aggregate has become pink, the colour deepening
to brick-red between 500C and 600C.
35- Any flint in the concrete calcines (loses its
water component, about 4 ) between 250C-450C,
while at similar temperatures the normally
featureless cement paste begins to show patchy
anisotropy with yellow-beige colours. - Thus, careful and informed petrographic
examination can usually reveal an
approximate 500C contour. - Cracking of the surface of the concrete occurs at
relatively low temperatures, but deep cracking
indicates around 550C was reached.
36- Quartz alters structurally at 575C resulting in
a volume increase that typically causes extensive
fine microcracking. - As most concrete contains quartz, an approximate
600C contour can usually be plotted. - The change in colour from brick-red to grey also
begins at 600oC. - Limestone aggregate calcines at 800C and
concrete becomes a buff colour by 900C.
37Laboratory investigation
- Another laboratory technique sometimes used to
assess the temperature reached is
thermo-luminescence. - Based on the fact that quartz emits visible light
when heated to 300-500C, unless it has already
been heated to that temperature. - It is be possible to establish the depth to which
the concrete has been affected. - The usefulness of this method is somewhat reduced
by its limited availability and cost. - However in special circumstances,
thermo-luminescence is invaluable, despite the
expense.
38Overall assessment
- The visual damage classification prepared on site
provides the basis for a repair strategy. - However the laboratory investigation -
particularly the petrographic temperature
contouring - provides critical information about
the depth of any fire damage, and any
classification of damage should be reviewed after
the laboratory investigation. - Critical temperatures (T) are as follows
- T gt300oC considerable loss in strength of the
concrete. - T 200-400C considerable loss of strength of
prestressed steel. - T gt450oC loss of residual strength of
cold-worked steel. - T gt600C loss of residual strength of hot-rolled
steel.
39Options for repair requirements for demolition
- Detailed information about repair is given in
CSTR 33. - A brief guide to the level of repair required can
be based on the final classification of damage. - On the basis of practical experience, Figure 9.3
has been devised to illustrate the types of
repair that might be appropriate for different
classes of damage.
40World Trade Centre - New York - Some Engineering
Aspects
- General Information
- Height 417 meters and 415 meters
- Owners Port Authority of New York and New
Jersey.(99 year leased signed in April 2001 to
groups including Westfield America and
Silverstein Properties) - Architect Minoru Yamasaki, Emery Roth and Sons
consulting - Engineer John Skilling and Leslie Robertson of
Worthington, Skilling, Helle and Jackson - Ground Breaking August 5, 1966
- Opened 1970-73 April 4, 1973 ribbon cutting
- Destroyed Terrorist attack, September 11, 2001
41(No Transcript)
42(No Transcript)
43(No Transcript)
44(No Transcript)
45(No Transcript)
46(No Transcript)
47(No Transcript)
48(No Transcript)
49Figure 9.3. Simplified illustration of
Classification and Repair.
Some peeling of finishes, slight crazing minor
spalling. Class 1 rapair slight damage.
Total loss of finish, Whitish grey
colour, Extensive crazing, Considerable spalling
up to 50 reinforcement exposed, minor cracking,
class 3 principal repair involving strengthening.
Much loss of finish, pink colour, crazing, up to
25 reinforcement exposed, class 2 restoring
cover to reinforcement with general repairs
reinforced with light fabric
Plaster paint intact, Class 0 clean
redecorate if required.
Finishes destroyed, buff colour, surface lost,
almost all surface spalled, over 50
reinforcement exposed, major cracking. Class 4
major repair involving strengthening or
demolition replacement.
50 51TRNC Ministry of Culture Education, Turkish
Cypriot State Theatre Hall
Theatre Hall- after fire, 2006
52State Theatre Hall /Lefkosa-After fire in 1999
duration 20 minutes only
53State Theatre Hall /Lefkosa-After fire in 1999
54State Theatre Hall /Lefkosa-After fire in 1999
55State Theatre Hall /Lefkosa-After fire in 1999
56State Theatre Hall /Lefkosa-After fire in 1999
57State Theatre Hall /Lefkosa-After fire in 1999
58State Theatre Hall /Lefkosa-After fire in 1999
59Theatre Hall after fire, 2006
60Theatre Hall after fire, 2006
61 62Caracas Fire
63Taiwan
64Interstate bank
65Madrid
66Madrid
67Meridian Plaza
68The Windsor Building Fire, Madrid, SpainHuge
Fire in Steel-Reinforced Concrete Building Causes
Partial Collapse
Time Collapse Situation 129 East face of the
21st floor collapsed 137 South middle section of
several floors above the 21st floor gradually
collapsed 150 Parts of floor slab with curtain
walls collapsed 202 Parts of floor slab with
curtain walls collapsed 211 Parts of floor slab
with curtain walls collapsed 213 Floors above
about 25th floor collapsed Large collapse of
middle section at about 20th floor 217 Parts of
floor slab with curtain walls collapsed 247 South
west corner of 1 2 floors below about 20th
floor collapsed 251 Southeast corner of about
18th 20th floors collapsed 335 South middle
section of about 17th 20th floors collapsed
Fire broke through the Upper Technical
Floor 348 Fire flame spurted out below the Upper
Technical Floor 417 Debris on the Upper
Technical Floor fell down
69Sunday, Jan. 10, 2016 photo, the burned hulk of
The Address Downtown is seen in Dubai, United
Arab Emirates. Skyscraper fires like the blaze
that struck the 63-story luxury hotel in Dubai on
New Year?s Eve, 2016, swiftly turning it into a
towering inferno, are not that rare. The fire in
Dubai has raised new issues about the safety of
exterior sidings put on high-rise buildings in
the United Arab Emirates and around the world.
(AP Photo/Jon Gambrell)
70Assessment of fire damaged structuresBRE
Information Paper IP 24/81
- Buildings, or portions of buildings, look a
sorry sight after a fire - some may have collapsed and be only twisted
ruins, others may have mainly suffered damage
from smoke. - Between these extremes there is a wide range of
degree of damage. - Where there is no visible damage such as
charring of timber, spalling of concrete or
distortion of steelwork, there is generally
little likelihood of permanent loss of
strength of the material although this cannot
always be assumed. - It is essential to do a thorough inspection of
the complete premises in order to ensure that
damage, - eg through thermal expansion or water leakage,
has not occurred in those parts not directly
involved in the fire.
71TEMPERATURES REACHED IN FIRES AND ESTIMATION OF
FIRE SEVERITY
- Standard fire resistance tests determine the
period of time for which elements of building
construction should fulfill their design function
of load bearing and / or fire separation while
exposed to heat in accordance with a
predetermined time / temperature relationship is
an idealisation of an uncontrolled growing fire
in a room. - It assumes an unlimited supply of fuel and its
burning rate, being controlled mainly by
ventilation condition, follows a predictable
pattern.
72- In real incidents, fire may have remained
localised for a long time, the rate of
temperature rise may have been faster, or slower,
than in the standard test, or extensive spread
may occur. - Different rooms and different parts of a building
may have suffered different fire intensities. - It is important to determine as accurately as
possible the condition of each element of the
structure following the fire. - Particular attention also needs to be given to
those features which are an indirect consequence
of the fire, - eg forces not considered in the orginal design
may have been generated by expansion or damage to
other members.
73- Table 1 gives an approximate guide to the
estimation of temperatures attained by various
components in building fires, from an examination
of debris.
74(No Transcript)
75- The colouration of concrete at various depths is
a clue to both the maximum surface temperature
attained (Figure 1) and the time / temperature
experience (Figure 2). - Care and experince are required when considering
spalled surfaces. - The interpretation will depend on judgement as to
whether spalling occured during the period of
maximum heat exposure or subsequently, and as to
the allowance to be made for this factor. - The extent of the change of colour varies with
the type of fine and coarse aggregate but changes
will occur to some degree for all types of
concrete. - Wetting the affected concrete surface will
enhance the colours. Some types of stone shows
similar changes.
76(No Transcript)
77(No Transcript)
78- The depth of charring from the orginal surface
gives a rough guide to the duration of fire
attack on a timber member. - Timber will char at a steady rate on each face
exposed to heating. - The rates which are given in Table 2 relate BS
476Part 8 conditions and allow an assessment to
be made in terms of an equivalent fire resistance
time. - Increased values are appropriate for the rate of
depletion of columns and beams when exposed on
all faces. - Due allowance must be made for areas which have
been allowed to smoulder after the fire has been
controlled.
79- With palsterboard of 9.5 mm thickness, the
unexposed paper face will be charred if there
has been a fire equivalent in severity to about
ten minutes under BS 476 Part 8 conditions.
80MAIN EFFECTS OF HIGH TEMPERATURE ON MATERIALS
- any material heated above 200oC is likely to show
significant loss of strength which may, or may
not, be recovered after cooling.
81Brickwork
- Clay bricks withstand temperature in the region
of 1000oC or more without damage but under very
severe and prolonged heating the surface of a
brick may fuse. - Spalling can occur with some types of brick
particularly of the performed type. - A load bearing wall exposed to fire will suffer a
progressive reduction in strength due to
deterioration of the mortar in the same manner as
concrete. - Severe damage is more likely to be caused by the
expansion or collapse of other members. - Small expansion cracks in the structure may
collapse up after the building has cooled.
82Cast Iron
- Because of their heavy mass and low design
stresses, cast iron members generally show good
performance in fires. - The member should be carefully examined for signs
of cracking. A permanent loss of strength can
occur when the temperature of a cast-iron member
exceeds 600oC but because of their large thermal
mass this requires a fire of such severity that
rebuilding is probably necessary anyway.
83Concrete
- The behaviour of concrete structures in fire is
discussed elsewhere5.6. The pink colour change at
around - 300oC which occurs with most natural aggregates
used in the UK is very important as it coincides
with the temperature below which the compressive
strength is not significantly reduced. Higher
temperatures up to approximately 500oC or above
may be endured by lightweight concrete before
significant loss of strength occurs. In a
concrete member, only the temperature of the
outside layers increases initially and the
temperatures of the internal concrete will be
comparatively low, unless the fire exposure is
prolonged, as concrete is a poor conductor of
heat (Figure 2). Temperature rise at a greater
depth than indicated in that figure will occur if
extensive spalling occurs during fire exposure.
Natural aggregate concretes heated to - 300oC or above, and lightweight aggregate
concretes heated to 500oC or above, may need to
be replaced in - critical areas during reinstatement.
84Steel Reinforcement
- Looses strength at high temperatures as discussed
below. Loss in effective concrete section in
prestressed members may significantly alter the
intended design stress profile in addition to
permitting a higher temperature in any adjacent
steel tendons with consequent increased loss.
85- Hollow clay tiles and woodwool cement slabs (used
in floors) - may be damaged but when these are used as formers
for the structural concrete section they have no
structural significance and the damage can be
ignored. - Plaster
- Plaster tends to be loosened in a fire and may
require replacement for this reason. - If it is severely stained by smoke which is
resistant to washing, it will probably be more
satisfactory to replace the plaster than to
overpaint the smoke stains.
86Steel
- When a building has been exposed to fire the
structural steelwork may suffer from any or all
of the following effects - a) expansion of heated members relative to
others which restrain this movement, leading to
distortion of the heated member or its neighbours
particularly at connection, - b) increased ductility, reduced strength and
plastic flow while metal is at a high
temperature, - c) change, persisting after cooling, in the
mechanical properties of the metal. - The coefficient of linear thermal expansion of
steel is nominally 14 X 10-6/0C. In a fire this
may be sufficiently small for it to be taken up
by elastic deformation, expansion joints etc, or
may permanent distortion of the framework or
extensive cracking of bearing walls.
87- The temperature at which the flow stress of mild
steel falls to the design stress is generally
taken to be about 550oC - - for a design factor of safety of about 2. At
stress levels less than the maximum permitted in
design, this critical temperature will rise.
The effects of constraints and continuity can
also raise the critical temperature. - Unless temperatures of 650oC are exceeded, there
will be no deterioration in the mechanical
properties of mild and micro-alloyed steels on
cooling. - After heating cold-drawn and heat-treated steels
lose their strength more rapidly than mild and
micro-alloyed steels and, on cooling from
temperatures in excess of about 300oC and 400oC
respectively, part of this loss of strength will
be permanent.
88- In general, any steel members which have
not distorted can be considered to be
substantially unaffected by the heat to which
they have been subjected. However, it must be
realized that in certain cases some degradation
in strength will have occurred. - Members should be examined for cracks around
rivet or bolt holes if expansion movements have
taken place. - It will usually however, be the cleast, rivets
and especially bolts which will have suffered and
not the main members. - Decision on reinstatement may need to be taken in
the light of expert engineering and metallurgical
advice.
89- Tiles and slates
- Clay tiles that have survived a fire unbroken may
be reused, as can slates that appear sound. - Timber
- Behaviour of timber in fire is predictable with
regard to the rate of charring and loss of
strength. - It is free from rapid changes of state and has
very low coefficient of thermal expansion and
thermal conductivity. - For practical purposes, it can be assumed that
full strength is maintained below the charred
layer. - For assessment of fire resistance of structural
timber, BS 52683 provides calculation methods for
flexural, compressive and tensile members.
90(No Transcript)
91Woodwool cement
- The material below the crumbly fire damaged layer
will be sound. - If a sufficient depth of sound material is
present the slabs may be retained.
92ASSESMENT OF EXTENT OF DAMAGE AND POSSIBLE
REINSTATEMENT
- A design procedure for the reinstatement of fire
damaged buildings is given elswhere also a case
study on building reinstatement. - The problems caused by fire will of course
include damage from water used in fire fighting
as well as from heat and smoke.
93- The initial consideration of fire damaged
premises should classify the damage to building
components in terms of superficial, repairable or
requiring replacement. - In any investigation, it is essential to
determine the exact form of construction of each
element. - Specialist advice may be needed in cases where
there is much borderline repairable damage or
where the construction is sophisticated. - The final decision on the extent of repair or
demolition may include consideration of costs,
time and possible improvements.
94REFERENCES
- 1. British Standars Instution. Fire tests on
building materials and structures. Test methods
and criteria for the fire resistance of elements
of building construction. BS 476 Part 81972
London. BSI 1972 - 2. Bessey GE. Investigation on building fires.
Part 2. The visible changes in concrete or mortar
exposed to high temperatures. National Building
Studies Technical Paper No 4 . London, HMSO,
1950. - 3. British Standards Instution. The structural
use of timber. Fire resistance of timber
structures. Method of calculating fire
resisitance of timber members. BS 5268 Part 4.
11978. London, BSI, - 1978.
- Â 4. Lie T T. Fire and Buildings. Applied Science
Publisher Ltd. London, 1978. - Â 5. Asseement of fire damaged concrete structures
and repair by gunite. Concrete Society Technical - Â Report No 15. The Concrete Society. London,
1978. - Â 6. Green J K. Some aids to the assessment of
fire damage. Concrete. January, 1976. - Â 7. Smith C I et al. The reinstatement of fire
damage steel framed structures. British Steel
Corporation - Â Research Organization. Teeside Laboratories.
1980. - Â 8. Malhotra H L and Morris W A. An investigation
into the fire problems associated with woodwool
permanent shuttering for concrete floors.
Building Research Establishment Current Paper
CP68/78. Borehamwood, 1978. - 9. Marchant E W ( Editor). A complete guide to
fire and buildings. Medical and Technical
Publishing - Â Co Ltd. Lancaster, 1972.