Title: Control of
1Control of
FINES DUST
and
2Introduction
Dust is a general term fine particles that are
suspended in the atmosphere.
Dust is formed when fine particles become
entrained in the atmosphere by the turbulent
action of wind, by the mechanical disturbance of
fine materials, or through the release of
particulate-rich gaseous emissions.
The concentration of particles in the atmosphere
can range from a few micrograms to hundreds of
micrograms per cubic meter (? g/ m3 ).
3Introduction contd.
There are several sources of mine dust production
and dispersal, which occur during rock breakage,
loading and transport.
Dust emissions by blasting are of concern to both
mine operators and surrounding communities.
Blasting, is one of the operations that is
carried out in most mines, and may produce very
large quantities of dust. The dust cloud can be
raised to substantial heights depending on the
blasting parameters.
4Introduction contd.
The quantity of dust produced, and the effects of
its dispersal depend substantially on geological,
blasting and meteorological conditions.
Most of the dust settles in and around mining
area, although some may be dispersed to long
distances before settling down. Some of the
settled dust is raised again by mining activities
such as moving vehicles.
5Introduction contd.
A limited number of studies only have been
carried out to study the amount of dust produced
during blasting, its dispersal, and the
quantification of the amount of dust reaching a
particular area.
Efforts are needed to understand the process of
dust generation and dispersion, and the steps
that need to be taken to reduce its generation
and the dispersal of fines and dust.
6FINES
- Poorer fragmentation results in boulders and
also generation of fines thus affecting the
economy of blasting and - Excessive fragmentation leads to the generation
of a significant proportion of fine material.
7- Fines are the finest fraction generated in
quarries/mines, a material for which there may
not be much use. - This fraction often becomes both on environmental
issue and an economical loss for the producers - Fine coal is
- Difficult to handle,
- Suffers low yield,
- Carries excessive moisture and
- Often attracts a lower sales price
8DETERIMENTAL EFFECTS OF FINES
- Poor Excess Poor Increased
Reduced - blast fines digging
downtime of production - shovel-dumper
- operation
- Water spray for dust suppression
- Mix-up with Dust Wet ore
- lumps
- To crushing
- plant
- Reduction in
- price of production Reduction in feed Bridging
of - due to poor quality rate to crushing ore at
grizzly - plant ore pass
- Tarnish company Reduced overall
- image recovery
9DUST
Dust due to blasting is a major problem
DUST REMAINS SUSPENDED FOR LONGER PERIOD THEN
VISIBLE
10- Dust is a general term-fine particles that are
suspended in the atmosphere. - Dust is formed when fine particles become
entrained in the atmosphere by the turbulent
action of wind, by the mechanical disturbance of
fine materials, or through the release of
particulate-rich gaseous emissions. - The concentration of particles in the atmosphere
can range from a few micrograms to hundreds of
micrograms per cubic meter (? g/ m3 ).
- Dust formation usually occurs with mining
activity initiated by the disturbance of
particles e.g. blasting. - Depending on factors such as climate, geology and
the method of mining, the potential exists for
greatly increased dust levels in the environment
surrounding a mine. - If blasting is appropriately designed much of
dust formation and dispersion can be controlled.
11Dust generation and dispersal can be controlled
12- A sound knowledge of blast mechanism and
related science is required - a) to understand the breakage mechanism in the
immediate vicinity of the charged section of the
blast hole (the origin of fine particles
generation) - b) The influence of explosive properties, priming
methods, rock properties, blast geometry and
delay timing on the occurrence and extent of the
fracture process. - c) To achieve the goal of reduced fines
generation, use proper explosive type, blast
parameters, initiation sequence, charge
distribution need to be tailored in such a way to
produce optimum size distribution of fragments
13Correlation Between the Hole Diameter, Charge
Length and the Amount of Fines
- Four blasts were carried out in anorthosite with
diameters of 76, 89, 102 and 114mm. The specific
charge was, for all blasts, 0.623 kg/m3 and the
number of holes varied accordingly. The result
was an increase of the amount of fines (0-4mm),
in production scale, by 18 for every half-inch
increase in borehole diameter. The total increase
was as high as 53 when the 76mm borehole was
compared with 114mm one - (Kristiansen,1995)
14BURDEN
- The quasistatic type of crushing, produced by
high gas pressures on the walls of adjacent
redial cracks increases as burden increases
beyond the optimum burden (for which total
operating costs are a minimum) - Close to hole crushing is much higher for very
small burden
15SPACING
- If the optimum burden is exceeded, then the
amount of fines is increase - If the hole spacing is increased and the burden
kept the same, the fines generation decreases - increase in burden and decrease in spacing lead
to more fines
16SUBDRILLING
- If subdrilling is increased beyond the required,
then the explosive energy is given more time to
fragment the rock, more fines are produced
17STEMMING
- Stemming influences the fines generation in two
ways - Increased stemming length means explosive energy
has increased time to work and thus produce more
fragmentation, whereas it also reduces length of
explosive column thus fines are reduced. However,
increased stemming length means more boulders
18Shape and Size of Blast
- The length to width ratio should be at least 3.0
if possible, because the blast has to be given
the space to move forward without sealing the
back rows. If a row is not allowed to move
forward, the explosion gases are trapped for a
longer time and unnecessary fines are generated. - The bench should be wide and shallow, not short
and deep
19SPECIFIC CHARGE
- Generally an increase in specific charge would
yield an increase in fines. - By decreasing the charge factor to an optimum
value, fines could be reduced to 36.5 whereas a
higher charge factor increased fines production
to 64.45
20DECOUPLING
- The amount of fines can be reduced by decoupling
(by providing an annulus of air between the
charge and blasthole wall) because the borehole
pressure becomes lower - Decoupling can be achieved either by using
cartridged explosives or by placing the bulk
explosives inserted in the hole
21DECKING AND STEM PLUGS
- Charges are decked by separating portions of the
explosive columns with drill cuttings or air
pocket deck charges. - When air decked, considerable reduction can be
observed in the amount of fines generated - Stem plug makes considerable
- difference
22DELAY TIME
- If fines are to be minimized, the rock in front
of a row must be loosened before the next row
behind it starts to move. - The amount of fines rises with shorter delay
times and a greater number of boreholes
23INITIATION SEQUENCE
- In a V-type initiation effective burden is
considerably less than drilled burden distance. - The reduction allows displacement of rock with
ease. Because of lower inertia of the smaller
burden, less crushing. - The effective burden also effectively changes
delay interval thus causing easy movement of rock
between holes thus does not allow increase in
fines
24(No Transcript)
25(No Transcript)
26(No Transcript)
27Dust generation and dispersion Controlled by
Blast design and execution Stemming
material Down the hole initiation
28(No Transcript)
29FRAGMENTATION PHOTO ANALYSIS
- Input Image
- Automatic Edge Detection
- Net Creation
- Block Unfolding Sizing and Counting
- Histogram
- Cumulative Size Distribution Curve
30- Fragmentation Analysis Information
- Data from Fragmentation Analysis Software
- Field Photographs
- Fragmentation Analysis Photographs
- Digging Condition at Face
Blast No. 3
Blast No. 3
31India Blasting video
32Introduction contd.
Depending on factors such as climate, geology and
the method of mining, the potential exists for
greatly increased dust levels in the environment
surrounding a mine.
33Design
If blasting is appropriately designed much of
dust formation and dispersion can be controlled.
This requires a sound knowledge of blast
mechanism and related science
- The breakage mechanism in the immediate vicinity
of the charged section of the blast hole (the
origin of fine particles generation). - (b) The influence of explosive properties,
priming methods, rock properties, blast geometry
and delay timing on the occurrence and extent of
the fracture process.
34Sampling Results
What points need to be mentioned regarding
these? These are aditya data.
35Experiments at Jaisalmer
Diameter 120 mm
Depth 4.0 5.0 m
Spacing 3.0 m
Burden 2.5 m
Charging ANFO a column charge and aluminized
slurry explosive as bottom charge.
36Jaisalmer video
37Details of Experimental Blast
Explosive Used RAJBLAST RAJBLAST RAJBLAST ANFO RAJBLAST ANFO RAJBLAST ANFO WATER BAG SAW DUST
Average Burden (m) 2.27 1.93 2.44 2.42 2.62
Average Spacing (m) 2.83 2.10 2.19 2.85 2.08
Max. Charge Per delay 103.80 66.48 53.56 298.32 44.30
Average Throw (m) 5.80 7.43 6.00 9.00 5.95
Average Back break(m) 1.37 1.66 1.64 1.85 1.01
Average over On side break (m) 0.65 0.85 1.77 1.80 1.66
Average Fragments size (mm) 727 755 275 317 106
Powder factor 6.42 5.00 6.81 8.23 6.48
Fragmentation Not Good Not Good Good Good Good
38Blast observations
Blast No. 1 2 3 4 5
Average burden (m) 2.27 1.93 2.44 2.42 2.62
Average spacing (m) 2.83 2.10 2.19 2.85 2.08
Max. charge per delay 103.8 66.48 53.56 298.32 44.20
Explosive charge Rajblast Rajblast Rajblast ANFO Rajblast ANFO Rajblast ANFO with sawdust water bag
Average fragment size (mm) 727 755 275 317 106
Powder Factor 6.42 5.00 6.81 8.23 6.48
Fragmentation Large boulders and finely crushed Large boulders and finely crushed Uniform fragmen-tation Uniform fragmen- tation Uniform fragmen- tation
Rajblast is cap sensitive aluminised slurry
39Fragmentation Analysis
Blast No. 1 Cartridged slurry Rajblast charge
40Fragmentation Analysis
Blast No. 2 Cartridged slurry Rajblast charge
41Fragmentation Analysis
Blast No. 4 Cartridged slurry Rajblast bottom
charge and ANFO as column
42Fragmentation Analysis
Blast No. 5 Cartridged slurry Rajblast bottom
charge and ANFO mixedwith saw dust as column and
with water bags in stemming
43Sampling Results
44Sampling Results
45Sampling Results
46Ball filled with water
High tensile, non-brittle plastic balls were used
in the stemming column.
Ball filled with water
The ball works as a lock or obstruction to the
blow out of stemming material for a little while
longer.
47Water ball in stemming
The balls have been filled with water when the
ball breaks it sprays water, which moistens dust
and thus reduces dust dispersion.
Placing ball filled with water in a blasthole
48Placing the water filled ball
49Water filled ampoule in stemming
The blasthole liner is filled with water and
formed into cartridge shape.
Diameter 89 mm Length 0.8 m
Effective in providing confinement as water is
incompressible and also in reducing dust.
50Water filled ampoule in stemming
These are placed as the last ½ m of stemming.
This is done to avoid damage to ANFO in case of
incidental breakage of ampoule and damage in the
column.
51Water filled ampoule in stemming
In this blast five blastholes were without water
ampoules and five blastholes were with water
ampoules.
The ejection of detonation gases was reduced when
water ampoules were used, which resulted in
better and uniform fragmentation.
52Water sprinkling of area surrounding the blast
If soil, fines and dust is moist then it may not
get airborne easily.
The area surrounding the blast were thoroughly
sprinkled with water before charging the
blastholes.
This dust prevents dust settled out during
previous operations from becoming airborne.
53Conclusions
Measurement of dust falling from moving plume is
difficult task, which is affected by wind
direction, velocity and other parameters.
The atmospheric carries dust much longer then the
visible dust plume.
Several steps can be taken to reduce generation
of fines and dust by optimizing blasting
parameters.
Dust dispersal can be controlled to some extent
by use of water filled ampoules and water filled
plastic balls in the stemming.
54Dust Dispersal After Surface Mine Blasting
- Dust released after blasting and its dispersal
needs to be studied - Modelling of Near Source Dispersal of SPM in
Planetary Boundary Layer - Respirable dust sampling and meteorological
conditions
55Software Details
Blast data, atmospheric data and ground contour
data
56Software Details
Temperature, Pressure, Humidity parameters and
coefficient of ground profile
57Software - One
58Software - Two
59Software - Three
60Software - Four
61Software - Five
62Experiment Site Details
Sites Birla, Aditya and Jaisalmer.
Mineral Unit of Quantity No. of Mines Quantity Labour
Limestone 000 t 557 145552 19621
63Layout of Instruments for measurement
64Birla Cement Works
Diameter 165 mm
Depth 8.0 m
Spacing 6.0 m
Burden 5.0 m
Charging 25 cap sensitive explosive and 75.
Bottom initiation using Excel or Raydet systems
are adopted and air decking techniques practiced.
65Birla video
Mining operations are very close to the
residential areas.
66Sampling Results
Answer awaited What points need to be mentioned
regarding these? What do these measurement show?
67Difficulties with field measurement
Incorrect identification of central line of plume.
Uneven surface levels of instruments 1,2,3,4 and
5.
Incorrect assumption of uniform dust distribution
in the vertical column.
Incorrect rate of suction leading to erroneous
dust weight.
Distance of power supply to the instruments (gt
100 m) then the voltage reaching is quite weak.
68Difficulties with field measurement
Wind direction, may sometimes, suddenly change at
the last moment, after the entire set of
instrument have been laid.
This may result in either partial dust capture or
no dust, at all, may reach to any of the five
instruments.
69Aditya Cement Works
Diameter 114 mm
Depth 9.0 m
Spacing 7.0 m
Burden 4.5 m
Charging ANFO a column charge and slurry
explosive as bottom charge.
Bottom initiation using signal tube method and
air decking techniques practiced.
70Aditya Cement Works
Variable Strata
71Aditya video