Title: Run II Upgrades Status February 2006
1Run II Upgrades Status February 2006
2Outline
- Technical Progress Mike Martens
- AP2, DB Studies
- Daves talk (Congrats on the stacking record!)
- Recycler Record Stash of 436E20 (2/14/06)
- Run II Upgrade Status
- Run II Upgrade Shutdown Work
- Technical Progress
- Project De-scoping
- Status for January 06 Jeff Sims
3Run II Upgrade Project Status
- Shift in emphasis for Run II Upgrade Project
- Started almost 3 years ago!
- Project is 85 complete
- Jeff Sims is now the Run II Project Manager
- Most projects completed or nearing completion
- Some remaining projects maybe not needed will be
de-scoped - Stacktail Cooling Upgrades
- Debuncher Vertical Band 4 Aperture improvements
- Pbar Target Sweeping
- Hope to close the project books by end of FY 06
- but work on Run II continues
- Some of the work naturally continues within
machine depts - De-scoped projects can return if needed
4Run II Upgrade Shutdown Work
- Tevatron Separators
- Replace 3 separators at A49 ? Allow for higher
voltage - Install two new separators ? Allow for larger
helix - Install TEL-2 at A0
- Tevatron Alignment
- Re-shim the remaining dipoles
- Unroll quad (with 10 mrad roll) at D17
- Tev Chromatic Compensation
- Rewire Sextupole circuits
- Corrects the chromatic beta function error
- Necessary to run near ½ integer
- Rapid Transfers
- Install Hall probes
- Repair some beamline BPMS with noisy channels
- Install New Pbar Target
- Main Injector BPMs
- MI and Tev BLM installation
5Technical Progress
- Li Lens
- One each of PT-1 and PT-2 lenses will be filled
and the PT-2 will be tested on the test stand.
PT-2 should be ready for beam in June. - Rapid Transfers
- Many elements of the upgrade are in place
(ramping power supplies, BPMs) providing benefits
to operations in various modes - Transfers without reverse proton tune-up tried
many times last week with good results
6Technical Progress (Contd.)
- MI BPM upgrade
- Most of the hardware designed, ordered or
delivered - First house installed in MI40 now commissioning
- Full upgrade during and immediately after
shutdown - BLM upgrades
- Prototype system running at MI60 for 3 months,
with PC instead of local control card. Control
card software under test - Production to be completed by 4/15, a month of
testing followed by installation
7Technical Progress (Contd.)
- OTR detectors
- Installed in December
- See first images
Transverse beam profile measurement from the
OTR One pass of beam at injection Is tilt from
optics? OTR alignment? Some noise introduced by
poor termination in tunnel
8Technical Progress (Contd.)
- IPM detectors
- Some problem with vacuum at full B and E-field
- See (very preliminary) first images
Transverse beam profile from the
IPM Turn-by-Turn profiles
9Project De-scoping
- Stacktail Cooling
- Design work has been completed
- Not needed unless significant gain in stack rate
- Will Mothball project
- Will decide in Summer 06 if needed.
- Debuncher Vertical Band 4 Aperture
- Design is completed
- Not a significant gain in aperture
- Eliminates lots of cryo, vacuum, and mechanical
work during an already packed shutdown - Pbar Target Sweeping
- Design and Hardware completed
- Will focus on target improvements
- If needed, the remaining work is mostly
commissioning
10Status
11Initial PM Efforts
- Working with Mike and Subproject Managers to
understand the remaining Run II scope. - Deactivating 220 /- cost accounts
- 60/- cost account remain active. We have
obtained estimates on all remaining work. - Descoping Stacktail and Band 4 Cooling Tank
Upgrade - Planning for Run II Closeout
- All but three subprojects will be 100 complete
by the end of FY06. The remainder are studies
and commissioning related tasks and do not
benefit from formal project management approach. - Any remaining Run II FY07 effort (MS or SWF)
will be included in the appropriate AD department
budgets for FY07 - Compiling Responses to 2005 DOE review
Recommendations.
12Remaining Run II Work (1 of 3)
- PBar and Target Sweeping - 1.1.2
- Upgrades to Pbar Target 1.1.2.3
- MI Upgrades 1.1.3
- MI BPM System 1.1.3.2
- MI-8 BPM Upgrades - 1.1.3.4
- Rapid Response Team 1.1.6
- Lithium Lens 1 and 2 1.2.1
- AP2 and Debuncher Acceptance 1.2.2
- AP2 Debuncher Survey and Alignment-1.2.2.2
- Develop New Instrumentation 1.2.2.3 (goes into
FY07) - Redesign/modify/rebuild/relocate elements
-1.2.2.5 (may extend into FY07 if there are
aperture restrictions) - Orbit Control 1.2.2.6
- Develop model of AP2 Debuncher lattice-1.2.2.8
- AP2 Debuncher Acceptance Beam Studies-1.2.2.9
13Run II Remaining Work (2 of 3)
- Rapid transfers 1.3.6
- RT Software 1.3.6.3
- Rapid Transfer Oscillation Feedback Control -
1.3.6.4 - Diagnostics 1.3.6.5
- Additional Recycler Upgrades-1.3.7
- Upgrade Transverse Dampers for Broadband-1.3.7.2
- Additional E-Cool Upgrades -1.3.8
- TEV Beam Studies Simulation -1.4.1
- TEV Studies and Simulation Work-1.4.1.1 (extends
into FY07) - TEV Active Beam-Beam Compensation-1.4.2
- Tevatron Electron Lens- 1.4.2.1 (Tel2 extends
into FY07) - Increased Helix Separation -1.4.3
- New Helical Orbits 1.4.3.1
- Separator Conditioning Testing-1.4.3.3
- Install Spare Separators To Smooth Helix -1.4.3.4
14Remaining Run II Work (3 of 3)
- Chromatic Compensation- 1.4.4 New Scope
- Tevatron Alignment 1.4.7
- Tevatron On-line Level System 1.4.7.3
- Smart Bolts 1.4.7.5 TD Only
- Orbump Magnets 2.1.2 TD Only
- Infrastructure Vulnerability 2.1.11 Recent
220k req for spare 345kv Switchgear - BLM System Upgrade 2.2.4
15Remaining Milestones
Scheduled for 2/21/06
Actually 2/27/06
Will have to bump out to early June
16MS Spending through Jan. 06
17Effort for Jan. 2006
18Whats Next?
- Schedule Review
- Compare recent estimates to RLS
- Prepare necessary CRs for descoping (Stacktail,
Band 4 Cooling Tank Upgrade and FY07 transition
to AD Departments)
19Contingency
- Contingency Needs
- We understand there is 1.5 Mill remaining in the
Directorate held contingency fund for Run II. - We do not plan to add new scope at this time.
- Contingency may be needed for any subproject
overruns in the next 6 months or so. - One Remaining Vulnerability is the 40 MW 345kv to
13.8kv transformers at KRS/MSS. RLS has 0.
Rough estimate is 1.1 million.