Title: Service Plan April 2005 March 2006
1Service Plan April 2005 March 2006
- Division Building Design Unit
- BRIAN J ANDERSON
2 Section Summary
- The BDU comprises Architects, Architectural
Technicians, Quantity Surveyors, Structural,
Mechanical and Electrical Engineers, Building
Surveyors, Clerks of Works - The BDU provides full, multi-disciplinary
building design and project management/constructio
n services to the Council - This unit is responsible for all the major
capital building projects funded by the Council
and a variety of external funding streams,
including, inter alia, European (Objective One,
Pathways, SRB6), DfES, Neighbourhood Renewal
Fund, Heritage and Sports Lottery Boards etc.
3 Section Summary
- The range of projects completed over recent years
is varied and includes, major housing estate
refurbishment, schools, conservation work,
leisure/sports, health, arts/culture, One Stop
Shops, University and Industrial
research/training buildings, Community Facilities - The unit continues to drive Egan and partnering
for the Authority and to date has implemented 15
project partnering contracts with a total value
of 30M using the PPC 2000 contract - The BDU works closely with local community groups
and is currently on site with the Lauries and St
James Centres in Birkenhead, both 2M Community
Facility schemes
4Family Tree of Divisional Structure
5SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Capital Programme, Property Asset Management
- Capital Strategy submission scored Good by GONW
in Nov 2003 - Rationalising office accommodation for Fit for
Purpose - Strengthening links between capital investment
and AMP - Improved delivery of 2003/04 Capital Programme
against KPI targets - Improved local labour figures of 57.5 (47.4 in
2001/02) - BDU delivered 7.7M capital works on site in
2003/04
6SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Capital Programme, Procurement, Service Quality,
Local Labour - Average BDU fee 9.38 in 2003/04 (reduced from
11.8 in 98/99) - Client feedback average score 87.5 (increased
from 65 in 99/00) - Average tenant feedback score of 86.6 (increased
from 80 in 01/02) - Contractors on major schemes now selected on
quality and price - 4.08 av days lost through staff sickness (reduced
from 10.8 in 01/02) - 10.7 local FTEs created per 1M construction
spend (3.72 in 02/03) - We have worked even closer with our customers,
contractors, suppliers and - Consultants over the last year to achieve
continuous and measureable service - improvements
7LOOKING FORWARD 2005/06 AND BEYOND
- BDU DIVISIONAL CHALLENGES
- Develop multi disciplinary teams within the BDU
and PMU - Develop Term Contracts with Consultants
- Establish Service Level Agreements with Client
Departments - Increase further efficiencies and reduced fees
- Reduce car mileage
- Re-Engineer Services to maximise opportunities as
one Department - Develop and implement Green Building
Specifications - Further development and implementation of Egan
and Partnering -
8LOOKING FORWARD 2005/06 AND BEYOND
- DEPARTMENTAL CHALLENGES
- Establish New Department and co-locate at
Cheshire Lines - Maintain Services during Re-organisation
- Re-Engineer Services to maximise opportunities as
one Department - Adapt and support new Core IT systems
- Build teams improve performance
- Streamline operations, Clear Focus on whats
important!
9Risks
- W.P.H. Housing Transfer
- Loss of key professional staff
- Loss of workload on housing schemes
- Demands on key areas, procurement advice, PMU
surveys etc - Staffing
- Staffing EVRs staff shortage (loss of
expertise knowledge) - Temps long term (difficulty in retaining
staff) - Cross Departmental Working reduction in
establishment posts - Education Cultural Services
- Changes in working practices potential
lower workload - PFI and Schools for Future potential lower
workload - Systems
- QA and B.S.I. Accreditation
- Joint working and cross-cutting processes (QA,
HS, CDM) -
-
-
10KPI Achievement Summary
- Average fee scale on Capital projects
- past 11.8 current 9.38 future 9
- Tenant feedback average scores
- past 80 current 87 future ?
- Construction Cost Predictability
- past 55 current 61 future 65
- Client feedback surveys average score
- past 65 current 87.5 future 90
- Construction Programme Predictability
- past 55 current 75 future 80
- Tender Sum Contract Sum
- past 68 current 88 future 90
11Family Tree of Proposed Divisional Structure
12Divisional Key Issues
- Implement multi-disciplinary design teams
- Structure of Division to be confirmed as soon as
possible with all acting ups confirmed to
implement interim management structure - Potential SLAs to be agreed with client
departments - Term contracts to be developed with Consultants
- Further implementation of Egan and partnering
across Department
13Service Plan April 2005 March 2006
- Section
- Waste Strategy Recycling
14Service Plan
- Section Head
- Allen Barker
15Waste Strategy Recycling(setting the scene)
- Structure Strategy Manager Recycling
Officer Assistant Recycling
Officer Assistant Recycling Officer
Assistant Recycling Officer Clerical
Support
16Waste Strategy Recycling
- Core Services Provide Recycling
Facilities Educate and Inform the
public Develop a Local Waste Reduction
Strategy Help Develop a Regional Waste
Strategy Represent the Council on the Bidston
Project board
17SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Waste Strategy Recycling
- Introduced interim recycling services
- Relaunched the doorstep paper recycling scheme
- Installed an additional 45 on street glass banks
- Extended the kerbside collection of garden waste
- Developed a community sector scheme for the
recycling of bulky household wastes - Developed a multi media education and recycling
awareness campaign - Worked with MWDA to develop a successful bid for
the redevelopment of Bidston (5M)
18LOOKING FORWARD 2005/06 AND BEYOND
- Waste Strategy Recycling will comprise
following core services - Recycling Services
- Provide bring facilities for the recycling of
paper, glass, cans, textiles, books, foil,
shoes. Etc. Provide door to door collections of
garden waste, mixed dry recyclables and other
organic wastes - Strategy Development
- Waste and recycling strategy development for
Wirral - Waste Strategy development for the Merseyside
region - Facilities Development
- With MWDA and others, develop the waste
management facilities for Wirral at Bidston - EducationProvide education resources and deliver
the recycling and waste reduction message to
schools and the general public - Research Provide research and development
services
19LOOKING FORWARD 2005/06 AND BEYOND
- CHALLENGES
- Reduce household waste arisings
- Provide multi-material collections of recyclables
for all households - Provide garden waste collections for all
appropriate households - Procure recycling collection contractor(s)
- Recover WEEE, bulky and hazardous wastes from the
waste stream - Develop further the Education and PR initiatives
- Work to develop a waste disposal strategy for
Merseyside for the next 25 years
20BIG ISSUES and POTENTIALS
- Encourage smart shopping (low packaging, avoid
disposables), promote home composting, promote
reuse, (nappies,batteries, bags), - Procurement and installation of 140,000 second
wheeled bins, manage the PR associated with this
and trouble shoot the problems - Examine all the options for service delivery
partners and advise on the best options for
Wirral - Procure and install garden waste recycling
facilities for a further 60,000 households - Work with partners for the refurbishment and
recovery of waste electrical equipment, bulky
waste and hazardous waste - Make all householders and schoolchildren aware of
the reasons why waste reduction and recycling are
important for them. - Work to ensure Bidston meets all Wirrals waste
recovery needs.
21Risks
- Failure to persuade householders to change their
buying habits in favour of less packaging,
reusable products, etc. - Delays in construction of MRF and composting
facility at Bidston - Increased government targets
- Additional legislation
- Failure to secure budgetary provision
22KPI Achievement Summary(appendix)
- BVPI 82a Percentage of household waste
recycled2003/4 6.8 actual2004/5 10
expected2005/6 18 statutory target - BVPI 82b Percentage of household waste
composted2003/4 0.2 actual (trial scheme
only)2004/5 2 expected2005/6 3 marginal
improvement expected - ISO 14001 Accreditation in November 2004 expected
23Family Tree of Divisional structure(appendix)
- Showing clear lines of reporting for Key Issue
Exchange/etc., down to clustered job roles
24Divisional Key Issues
- Reduce Household Waste Arisings
- Introduce Borough-wide multi-material kerbside
recycling - Procure a kerbside recycling collection
contractor - Expand Kerbside garden waste collections
- Recover WEEE, bulky hazardous materials from
the household waste stream - Develop promotion, PR and education initiatives
- Work in partnership on the development of
regional and sub regional waste treatment and
disposal strategies.
25Service Plan April 2005 March 2006
Traffic Management
26Service Plan
Technical Services - Traffic Management
Divisional Head
- Geoffrey Bell
- Assistant Director
27Divisional Summary Core Services
Technical Services - Traffic Management
In line with both Government and Wirral Borough
Council strategy and policy, the Traffic
Management Division carries out a wide range of
traffic-related responsibilities. In particular,
the main areas of activity are-
Safety
Safety
Safety
- Design
- Design and provision of all new traffic signs and
road markings - Accident analysis and Safety audit
- Design, installation and maintenance of traffic
signals including pedestrian facilities - Urban traffic control
- The provision and maintenance of cctv
- Implementation and review of traffic regulation
orders - The design and implementation of local safety
schemes, measures to assist buses, traffic
calming, pedestrian refuges - Provision of parking bays to assist disabled
people and lowered kerb crossing points
- Training
- Providing road safety education
- Cycle Training
- Kerbcraft pedestrian training
- Road Safety publicity events / campaigns
28Divisional Summary Core Services
Technical Services - Traffic Management
- Information
- Road safety and traffic management advice in the
planning application process and to external
agencies - Road accident information provided for internal
and external customers - Road traffic data provided for internal and
external customers
- Other
- Administration and management of the school
crossing patrol service - Administration and management of on-street car
parking - The engagement, supervision and monitoring of
consultants and contractors to assist in the
overall service delivery - Traffic co-ordination role
- Inter-authority liaison in the local transport
plan process - Management of the highway for temporary events
29Technical Services - Traffic Management
30Technical Services - Traffic Management
- CLUSTERED JOB ROLES
- UTC - Urban Traffic Control
- Maintenance and design of new traffic signals
- CCTV
- Variable Message Signing Telematics
- Roadworks / events co-ordination
- Traffic survey investigations
- Accident Investigation
- Examination / analysis of accident database
- Design of Local Safety Schemes
- Safer Routes to Schools
- Road Safety
- Education, Training Publicity
- Kerbcraft Initiative
- School Crossing Patrols
- Managing 120 sites
- Risk assessment
- Traffic Management
31Key Partners / Service Links
Technical Services - Traffic Management
Merseytravel Police Community Groups Solicitor WIR
ED Government Office NW Consultants Cheshire /
Babtie / Atkins / MIS / Highway Agency Birkenhead
Town Centre Management Tourism
Hackney / Private Hire Nth West Development
Agency NWDA Other Merseyside District
Authorities Events organisers Forums Wirral
Waterfront All Council Departments NHS Hospital
Trust Healthcare Primary Trusts Driver Vehicle
Licensing Agency (DVLA) Vehicle Operators
Standards Agency (VOSA)
32PAST SERVICE PLAN TO MARCH 2005SERVICE AREA
OBJECTIVES AND PROGRESS TO DATE
Technical Services - Traffic Management
33SOME OF OUR ACHIEVEMENTS DURING 2003/04
Technical Services - Traffic Management
- Centre of Excellence
- - School Crossing Patrol Service
- - UTC
- - Identifying LSS
- - Involvement with external parties
- - Funding opportunities
- Quality jobs / professional approach
- Consistent delivery of service to meet a wide
range of performance indicators both at local and
national levels.
- Delivery of Capital / Revenue programmes 2.2m
and 2.0m respectively - Delivery of increased Capital and Revenue
programmes some of which directly assist persons
with disabilities and generally have necessitated
partnership working with external consultants to
help with the peaks in workload. - Management and monitoring of the budget within
guiding principles. - Delivery of P.Is
- Considerable advancement in CCTV/VMS and
telematics technology. - Considerable involvement and advice on major new
initiatives throughout the Borough.
. . . . .
34SOME OF OUR ACHIEVEMENTS DURING 2003/04
Technical Services - Traffic Management
- 3rd Child Pedestrian Co-ordinator appointed and
Kerbcraft programmes successfully completed. - Safer Routes to School and Walking Buses.
- Second Speed Alert Trailer and development of
deployment strategy - On-going improvements in Best Value Review in
Road Safety (continuous service review)
- Success in quality bus partnership initiatives
with Merseytravel. - Supportive in a wide range of PR and media issues
both of an internal and external nature eg RNLI
Hoylake, The Egg Run, Queens Golden Jubilee and
charitable events. - Key role in supporting the LTP process and
membership of MTEG. - Close corporate working on tourism sign-posting.
35Division Challenges(What we look forward to
managing - What we are not so good at)
Technical Services - Traffic Management
- CHESHIRE LINES MOVE
- lack of parking facilities
- accommodation
- lack of detail on move
- not properly thought out
- service delivery before during and after
- open plan office
- opportunity in flexi working from home etc
- security on site
- PRIORITISING
- Statutory functions - Road Traffic Act 1991
- Non statutory functions
- KEEPING ON TOP OF CORPORATE INITIATIVES
- BEING PROACTIVE Constrained by reactive work
- MANAGING WORKLOADS
- ACQUIRING THE NECESSARY I.T. TO DO THE JOB
- INTERACTING WITH PUBLIC ON FEEDBACK ON WHAT THEY
WANT - KEEPING A GOOD RECORD SYSTEM
- as-built drawings
- TRO procedure
- TEAM BUILDING
ATTRACTING AND KEEPING STAFF PERSONAL
DEVELOPMENT PLANS REVIEWS OF JDs AND JOB SPECS
36BIG ISSUES
Technical Services - Traffic Management
- FANTASTIC FEEDBACK
- On what we have to do now, in the future and
suggestions for economies and efficiencies
- NOW
- Deliver KPIs / P.Is Enhanced
- Deliver services and programmes
- Move to Cheshire Lines
- Address recruitment and retention
- Better manage consultants
- PR with public and Councillors (expectations v
resources v timescale) - Open Golf Tournament
- Merseytravel
- Neighbourhood Renewal Fund (NRF)
- Staffing
- FUTURE
- Identify Revenue savings
- Longevity of funding arrangements
- Project management
- Traffic management Bill / Act
- Improve staff morale
- More flexible working arrangements
- Management of sickness
- Open Golf Tournament
- TRO Decrim review
- Backlog of Committee reports
- Netting off
- LPSA target delivery
- Statement of Intent / P.Is
- Keeping up with Corporate initiatives
- Gain better level of public and Councillor
support - Develop time to monitor what we do so as to be
able to improve - Leaflets / displays / IT website
37BIG ISSUES
Technical Services - Traffic Management
- COHESION
- Closer working with planning function
- Streetlink review
- Contact Centre toolbox type talks
- Work / Life balance
- Member training
- Charge for pre-planning advice
- Improved / updated IT (GIS/TROs/UTC)
- Charge all service users disabled?
- Current income generators
- Capital schemes
- Survey information
- Signal information
- Accident information
- Temp TROs
- Lost parking permits
- Automatic traffic counts
- APMs
Target 260,000
38KEY PERFORMANCE INDICATORS AND P.IS
Technical Services - Traffic Management
39KEY PERFORMANCE INDICATORS AND P.IS (continued)
Technical Services - Traffic Management
40RISKS TO THE BUSINESS
Technical Services - Traffic Management
- POOR DELIVERY OF SERVICE
- POOR P.R.
- STAFF RETENTION / RECRUITMENT
- STAFF MORALE AND MOTIVATION
- EFFECTS OF THE OFFICE MOVE
- ABILITY TO MANAGE CONSULTANTS
- FAILURE TO MEET BOTTOM LINE BUDGET
- FAILURE TO DELIVER
- LPSA Targets
- P.Is
- Statement of Intent
- POOR QA PROCEEDURES
- SERVICE RE-ENGINEERING
-
41Service Plan April 2005 March 2006
- DivisionProperty Maintenance Unit
- Jeff Sherlock
42Section Summary
- Property Maintenance Section provides various
professional services to all client departments
and also works with the in-house Building Design
Unit to cover peaks in workload. - The Section comprises of Building Surveyors,
Quantity Surveyors, Structural Engineers, Lift
Engineers, Demolition Surveyor, Asbestos
Surveyors, Assistant Building Surveyors and
Technical Clerical Staff.
43The Section is responsible for the following
- The Councils Planned Preventative Maintenance
Programme (PPM)1m per year. - Adaptations for disabled design and supervision
approximate value 900,000 per year. - Maintenance and new installations of all lifts,
stairlifts, and lifting appliances approximate
value 700,000 per year. - New Deal for Schools (N.D.S.) and condition
funding spends in partnership with Education
Cultural Services, Facilities Management Section
approximate value 1.5 m. - Demolition projects annual value of 1.3 m.
- Asbestos identification, removal, encapsulation
works, annual value of 300K.
44- Day-day reactive maintenance works to municipal
buildings and managed properties covering over
300 properties with an annual budget of
approximately 500k. - Day-day reactive heating maintenance for 12
communal housing properties and 40 Social
Services sites. - Annual boiler maintenance on municipal buildings
and 135 schools. - Structural surveys and reports for Department of
Housing Environmental Protection including the
Market Renewal funded schemes. - Council House Right to Buy surveys.
- Day-day reactive works and major refurbishment
schemes for Merseyside Magistrates Courts.
45SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Capital Programme, Property Asset Management
- Significantly improved disabled access to
Councils public buildings - Rationalising office accommodation for Fit for
Purpose - Strengthening links between capital investment
and AMP - Improved delivery of 2003/04 Capital Programme
against KPI targets - Improved local labour figures of 79 (71 in
2002/03) - P R Programme restored to summer working
46SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Average PPM fee 11 in 2003/04 (reduced from
12.5 in 2002/03) - Client feedback average score 87.5 and average
tenant score of 92 - Contractors on major schemes now selected on
quality and price - Major scheme incorporating new court rooms at
Birkenhead Court House delivered on time for
Merseyside Magistrates Courts.
47LOOKING FORWARD 2005/06 AND BEYOND
- DIVISIONAL CHALLENGES
- Develop multi disciplinary teams within the new
Property Maintenance Unit and Building
Maintenance Unit - Develop Facilities Management services
- Establish Service Level Agreements with Client
Departments - Increase efficiency and reduce fees
- Reduce car mileage
- Re-Engineer Services to maximise opportunities as
one Department - Re-tender all S.O.R. Contracts
-
48LOOKING FORWARD 2005/06 AND BEYOND
- DEPARTMENTAL CHALLENGES
- Establish New Department and co-locate at
Cheshire Lines - Maintain Services during Re-organisation
- Re-Engineer Services to maximise opportunities as
one Department - Adapt and support new Core IT systems
- Build teams improve performance
- Streamline operations, Clear Focus on whats
important!
49Risks
- W.P.H. Housing Transfer potential reduction in
workload - Adaptations Home Adaptation Role (HAT)
- Right to Buy Surveys, Structural Surveys, Lifts
- Staffing
- Staffing EVRs staff shortage (loss of
expertise knowledge) - Temps long term (difficulty in retaining
staff) - Cross Departmental Working reduction in
establishment posts - Education Cultural Services
- Changes in working practices potential
lower workload - Schools autonomy potential lower workload
- Changes in Legislation eg Asbestos Regulations
places increase on workload - S.O.R. Contracts extended year on year not
market tested (D.A.) - Systems
- QA and B.S.I. Accreditation
- Joint working and cross-cutting processor (H S,
CDM) -
-
-
50KPI Achievement Summary(appendix)
- Average fee scale on PPM projects
- past 12.5 current 11 future 10
- Adaptation Service Delivery Targets
- past 75 current 95 future 100
- Improve Service Delivery Stairlifts
- past 75 current 50 future 80
- Client feedback surveys average score
- past 80 current 87.5 future 90
- Housing Repair Painting Programme Summer
Working - past 56 current 95 future n/a
- Development of Asbestos Register completed
surveys - current 55 future 75
51(No Transcript)
52Divisional Key Issues
- Structure of Division to be confirmed as soon as
possible with all acting ups confirmed - Potential SLA to be agreed with client
departments with priority given to those affected
under Wirral Partnership Homes Transfer - Diagnostic Surveys (structural)
- R.T.B. Surveys/Valuations
- H.R.A. Adaptations for the Disabled
- Lift Maintenance Installations
- Asbestos Removal/Treatments
- C.D.M. Regulations
53Divisional Key Issues
- Develop FM commencing with Education
Cultural Services - S.O.R. contracts to be re-tendered
- AMP/condition surveys to be completed as per
Government guidance - Implement Asbestos Management Procedures
54Service Plan April 2005 March 2006
- Division
- Drainage Coastal Parking Services
55Service Plan
- Assistant Director
- Malcolm Alexander
56DIVISIONAL SUMMARY(CORE SERVICES)
- Drainage
- Coastal
- Parking Services (Since April 2003)
- Highway Development (Full since April 2004)
- Street Lighting (Since April 2004)
- Bridges and Special Projects (Since January 2003)
57STAFF STRUCTURE
58SOME OF OUR ACHIEVEMENTS DURING 2004/05
- Divisional
- Six partially completed sub-key issues from
2003/2004 Departmental Plan now fully
completed. - Integrated Street Lighting Section into the
Division. - Took responsibility for all highway
development and street naming and numbering
functions. - Developed special projects section to meet
Departmental
needs.
59SOME OF OUR ACHIEVEMENTS DURING 2004/05
- Sectional
- Introduction of new paperless naming numbering
system electronic notification to improve
efficiency of service - Reviewed improved the authorities highway
adoption agreements incorporating more efficient
inspection regimes and commuted sums for future
maintenance of new highway assets - 11m Mersey River Wall scheme audit and final
grant payment - DEFRA approval of Shoreline Management Plan
monitoring and Scoping Study for Cell 11 Tidal
and Sediment Study with Wirral as Lead Authority - DPE operation on budget (first full year of
operation)
60SOME OF OUR ACHIEVEMENTS DURING 2004/05
- Sectional (continued)
- PD ticket machine replacement programme
completed - Unified permit system
- Transition to paperless system for ordering
lighting works - using Hilight Horizon
- Traffic signs on the highway report and asset
survey - Procurement of maintenance painting contractor
61LOOKING FORWARD 2005/06 AND BEYOND
- DRAINAGE
- Operational control and asset management of
highway drainage network - Design of highway drainage and flood defence
works - Operation and management of gully cleansing
contract - Advice service for general drainage issues
- Act as Land Drainage Authority in respect of
ordinary watercourses and liaison with
Environment Agency in respect of main river
issues
62LOOKING FORWARD 2005/06 AND BEYOND
- COASTAL
- Implementation of Councils Policy Statement on
Flood and Coastal Defence - Act as Coast Protection Authority
- Operational control and asset management of
Wirrals coastal defences - Implementation of Shoreline Management Plan
recommendations - Operation of tidal flood warning procedure
consistent with Environment Agencys Local Flood
Warning Plan
63LOOKING FORWARD 2005/06 AND BEYOND
- PARKING SERVICES
- Operation and management of on-street and
off-street parking enforcement - Operational control and asset management of pay
and display and non pay and display car parks - Management of operational maintenance for
on-street parking and waiting restriction signs
and lines
64LOOKING FORWARD 2005/06 AND BEYOND
- HIGHWAY DEVELOPMENT LIGHTING
- Operational control and asset management of
Wirrals street lighting - Development of revised residential roads
specification. - Management of highway-related development and
adoption of new highways - Management and operation of street naming and
numbering system
65LOOKING FORWARD 2005/06 AND BEYOND
- BRIDGES SPECIAL PROJECTS
- Operational control and asset management of
bridges and other highway structures - Procurement of consultancy services
- Service reviews
66LOOKING FORWARD 2005/06 AND BEYOND
67LOOKING FORWARD 2005/06 AND BEYOND
- BUDGETS AND RESOURCES (continued)
- Capital Budget Expenditure
- Coastal - DEFRA grant aid and SCE for coast
protection schemes. Annual allocation varies
(0.15m 04/05) - Bridges - Dft grant aid through LTP highways
capital budget. Annual allocation varies
(3.4m 04/05) - Street Lighting - LTP and Wirral Capital funding
(0.14m 04/05)
68CHALLENGES
- Provision of services and maintenance of income
during reorganization - Meeting income budgets with diminishing parking
assets - Secure funding for Bidston Moss Viaduct
- Roll out the revised Residential Road
Specification to internal and external users - Undertake a survey of street lighting stock
- Secure DEFRA funding for coast protection capital
works programme
69BIG ISSUES AND POTENTIALS
- Development of highway related database and asset
management plan - Crime reduction initiatives in partnership
- Effective use of consultants
- Introduction of new government strategy for flood
and coastal erosion risk management in England - Implications arising from the Water Framework
Directive - Replacement of life-expired street lighting stock
70RISKS
- Reduced car park income due to falling footfall
in Birkenhead town centre and redevelopment of
car park land - Bidston Moss Viaduct costs and/or programme
overruns - Seeking energy supplier for street lighting stock
by tender - Impact of global warming on land drainage and
flood defences - Failure to capture knowledge and data relating to
drainage, highway and coastal assets
71KPI ACHIEVEMENT SUMMARY
72KEY ISSUES
- Raise the total penalty charge notices recovery
percentage to 70 by March 2006 - Increase the percentage of Wirral pay and display
car parks achieving Secured Car Park status from
0 to 10 via the Safer Parking Scheme, by the
end of March 2006 - Replace night scouting paper report system with
electronic data capture system by March 2006 - Reduce the number of repeat highway drainage
flooding incidents caused by blockages in the
network by 10 before March 2006 - Revise the tidal flooding section of the
Departmental Emergency Plan for Major Disasters,
and include a section for fluvial flooding, by
March 2006 - Issue an invoice for the highway supervision fees
and secure a cash deposit/bond for completion of
the new highway works within six weeks of
approving development proposals.
73KIE STRUCTURE
74Service Plan April 2005 March 2006
- Division
- HIGHWAY MAINTENANCE/ ENVIRONMENTAL SERVICES
75Service Plan
- Divisional Head
- Mike Wilkinson
76Divisional Summary(setting the scene)
- MANAGEMENT OF THE WASTE CONTROL FUNCTION,
INCLUDING - Management of the refuse collection contract
- Management of the street cleansing contract
- Operation of enforcement issues
- Flytipping
- Graffti
- Abandoned Cars
- Joint operation of the
- ERIC Service
- Hit Squads
77Divisional Summary(setting the scene)
- MANAGEMENT OF THE HIGHWAY NETWORK, INCLUDING
- Highway Maintenance
- Management of the New Roads and Street Works Act
- Ground Maintenance contract
- Arboriculture contract
- Public Rights of Way management
- Highway Enforcement
- Winter Maintenance Service
78Current Structure(setting the scene)
79Proposed Structure(setting the scene)
80SOME OF OUR ACHIEVEMENTS DURING 2004/05
- Transfer of manual operations (Eric, Hit Squads
etc) to Operational Services. - Amalgamation of Environmental and Highway
Maintenance Services in Streetscene operation. - Ground maintenance contract now developed into
partnership. - Arboricultural contract now influencing condition
of highway trees. - Highway Inspection regime revised in accordance
with Code of Practice. - Public liability claims, repudiation rate
continuing to rise. - High levels of defects issued against Statutory
Undertakers. - S.74 NRSWA operation proving effective.
81LOOKING FORWARD 2005/06 AND BEYOND
- CHALLENGES
- reduce litter production, flytipping, illegal
dumping - meet the requirements of the LPSA bid associated
with BVPI 199 - improve condition of highways, demonstrable
through Performance Indicators - improve public perception and satisfaction with
- cleanliness
- household waste collection
- footway condition
- carriageway condition
- design and condition of street furniture
- verge and tree maintenance
- develop an effective strategy for enforcement
-
-
82LOOKING FORWARD 2005/06 AND BEYOND
- BUDGET AND PERSONNEL
- Number of staff 52
- Revenue Budget - Works Expenditure
- Environmental Services 6,280.400
- Highway Maintenance 3,895.300
- Total 10,175.700
- Capital Funding 1,180.000
- Overall Total 11,355.700
-
-
83BIG ISSUES and POTENTIALS
- Future of the refuse and cleansing contracts.
- Impact of M.R.F. on services.
- Acquisition of Maintenance Management System.
- Improved methods of working through acquisition
of Maintenance Management System.
84RISKS
- Budget levels for service provision affected by
overall Council budget levels. - Service over re-engineering (leading to too few
staff). - Statutory Undertakers resolve quality issues with
their contractors and level of defects reduces.
Adverse affect on budget provision. - Refuse and cleansing services, contractor
performance in final year of contracts. - Establishment of Council liability, following
Court judgements on requirements to pre- treat
footways to ensure public safety. - Industrial Action in connection with the refuse
service.
85KPI Achievement Summary(appendix)
86KPI Achievement Summary(appendix)
87Divisional Key Priorities
- Develop and implement short and long term
strategies for the management of NRSWA. - Review enforcement policies, programme and
operational structure to meet requirements of the
Streetscene approach to environmental and highway
management. - Develop and implement with partner contractor, a
short term service improvement plan for refuse
and cleansing contracts. - Review operational administrative roles, develop
training procedures and implement training
programme to allow staffing flexibility within
operational roles. - Review operational requirements of Public Rights
of Way service area. - Investigate, trial and evaluate methods of
footway and carriageway reconstruction that
assist the sustainability agenda.
88Family Tree of Divisional Structure(appendix)
Proposed Structure
89 Wirral
Service Plan April 2005 - March
2006 Division OPERATIONAL SERVICES
90 Wirral
Service Plan Divisional Head NIGEL JENKINS
91Metropolitan Borough of Wirral
Technical
Services Department
OPERATIONAL SERVICES DIVISION
92- Core Services
- Highway repair and maintenance
- Drainage
- Street Lighting
- General Engineering
- Road Lining and signs
- Transport
- Environmental Services
93Metropolitan Borough of Wirral
Technical
Services Department
PROPOSED STRUCTURE OPERATIONAL SERVICES DIVISION
94- Operational Services Division
- Some of our achievements during 2003/04
- 1. Successful integration of Environment
Services operational unit into OSD. - 2. Improved communications and working
relationships with other - divisions in Technical Services.
- 3. A developing multi-task workforce.
- 4. Improved succession planning-
- Stand-in Team Leaders
- Stand-in Highway Inspectors
- 5. Training and development successes.
- 6. Further improvement of working relationships
with trade unions.
95- 7. Expansion of recycling of waste materials-
- 100 highway waste now recycled
- recycling of plastics
- co-ordination of Corporate fluorescent tube
recycling scheme - 8. Further development and better understanding
of IT systems. - 9. Continuation of Craft Apprenticeship
programme. - 10. Expansion of partnership working with
external contractors. - 11. Review of procedures within Transport
Section. - 12. Improving morale within division.
- 13. Achieved or showing improving trend on all
performance targets set by - Clients.
96Looking forward 2005/06 and beyond. Operational
Services will comprise of the following core
services- Construction, maintenance and repair
of road and footpaths Street Lighting Drainage Roa
d Signs Road Lining General Engineering
(Metalcraft) Fleet Vehicle Management Vehicle
Maintenance and Repair Out of hours emergency
call-out service Winter Maintenance ERIC
Service Recycling collection - schools Green
Waste collection Environmental Hit Squads Street
Litter Bins Dog fouling signs Graffiti Squad Skip
Wagon Maintenance of bottle bank sites Kerbside
recycling scheme collection
97- LOOKING FORWARD 2005/06 AND BEYOND
- Operational Services will have
- Total number of staff _at_ 170
- Environment Services budget of 1.8m
- Highway operations turnover of 7.7m
- Transport operations turnover of 4.8m
98- CHALLENGES
- Further review of management structure following
integration of Environment Services operations. - Maintain services, workload and morale during
time of change. - Re-engineer operations to ensure maximum
efficiency. - Improve performance.
- Improve quality of work.
- Management of depot facilities due to
establishment of Wirral Partnership Homes. - Further develop working relationships between
divisions. - Maintain/improve financial performance.
99- Big Issues and Potentials
- Further develop existing partnering arrangements.
- Future development of facilities/resources at
Dock Road and Cleveland Street sites. - Multi-task working.
- Joined-up working. (Best use of expertise and
avoid duplication). - Safe working methods.
- HSE regulations
- Fleet Management.
- Fit for Purpose
- Wirral Partnership Homes
- Performance and Quality
- Learn from each other.
100OSD KEY RISKS 1. Loss of use of buildings
(fire/explosion) 2. Long term loss of IT /
telecommunications. 3. Failure to operate
profitably. 4. Loss / withdrawal of O
licence. 5. Failure to effectively manage
Health, Safety and Welfare - staff
absences, sickness, injury rates, HSE
regulations. 6. Industrial action by own
workforce and/or external partners. 7. Long
term fuel delivery strike.
101OSD PI Achievement Summary
102Operational Services DivisionKey Issue Exchange
Reporting Lines
103Service Plan April 2005 March 2006
- Division
- Highway Improvements
104Service Plan
- Division Head
- Paul McBride
105Highway Improvements Divisional Summary
- Current structure and core services
- Fit for Purpose proposed structure (include
family tree as appendix) and core services - No change
106HID Core Services
- To provide a range of services for highway
improvement and footway reconstruction schemes
(gt50k) including - topographical surveys
- civil engineering advice
- highway/civil engineering design
- preparation of tender documents
- site supervision
- Transport forward planning and policy (LTP APR)
- develop monitor the transport policy
- develop new transport schemes initiatives
- bid for central government funding thro LTP/APR
- comment upon relevant development proposals
planning applications - Sustainable transport co-ordination
- Review update travel plan
- Assist in achieving the award of ISO 14001
107Highway Improvements DivisionStaffing Structure
108SOME OF OUR ACHIEVEMENTS DURING 2003/04Highway
Improvements Division
- Capital expenditure of 6.44M (not all H.Imps)
- Local Transport Plan (LTP) / Annual Progress
Report (APR) - 80 - above average
- Award of 9.871M for 2004/05
- English Regions Cycling Development Team (ERCDT)
- 16 bells - Reconstruction of 7.8km of footway
- Reconstruction of 22km of carriageway
- Improved condition of highways cway
satisfaction 33.2 (28.4) - fway satisfaction 36.8 (30.7)
- Establishment of new/upgraded cycle parking
facilities at 46 locations - 100 of bridges subject to Principal Inspection
- 100 of Celsys enquiries completed within target
time - 61 increase in cycle usage compared to 2002/03
- St James Rd junction improvement
109SOME OF OUR AIMS/ACHIEVEMENTSDURING
2004/05Highway Improvements Division
- Forward Planning
- LTP updated and APR submitted to central
government (HID 7) - Maintain high level of LTP capital funding. Bid
of 7.946M (HID 7) - Achieve minimum Above average APR score
- ERCDT - target 20 bells, probable 24 bells
minimum (HID 6) - Appointment of Sustainable Transport Co-ordinator
- Design
- Working with consulting engineers on the Heron
Road improvement - Working with consulting engineers on the Arrowe
Park Roundabout improvement - Telegraph Road/Station Road/Thurstaston Road
roundabout - Birkenhead Strategic Movement Improvements
(Wirral Waterfront)
110SOME OF OUR AIMS/ACHIEVEMENTS DURING
2004/05Highway Improvements Division
Construction (approx. 4m)
- Saughall Massie Bypass
- Woodchurch Road/Prenton Hall Road junction
improvement - Leasowe Road/Gardenside roundabout
- Leasowe Road/Reeds Lane junction improvement
- Hoylake Park and Ride car park
- Hoylake to West Kirby pedestrian/cycle-track
- Seacombe Spaceport car park bus facility (in
partnership with Merseytravel) - Wirral Way pedestrian/cycle-track - (West Kirby
to Thurstaston) - Clatterbridge Road/Thornton Common Road junction
improvement - Other cycling schemes
- Caldbeck Road extension
111SOME OF OUR AIMS/ACHIEVEMENTS DURING
2004/05Highway Improvements Division
Construction continued
- 26 (25 target) increase in the quantity of
recycled material used in highway schemes
(HID 2) - Operation of Constructionline/CHAS tenderer
selection procedure - Working with consulting engineers to deliver the
Dundonald Street Methuen Street Home Zone
112LOOKING FORWARD 2005/06 AND BEYONDHighway
Improvements Division
- Forward Planning
- LTP2 APR
- Review Wirrals Travel Plan develop action
plans for key Council sites - Cycling schemes (ERCDT - 30 bells)
- Highway Improvements
- Birkenhead Strategic Movement Improvements
- Cross Lane Access
- Hoylake West Kirby Regeneration Improvements
- Heron Road Improvement
- Saughall Massie Road Improvement Ph5
- Arrowe Park Roundabout Improvement
- Woodchurch Road/Storeton Road junction
improvement - Telegraph Road/Station Road/Thurstaston Road
junction improvement - Green Lane/Mollington Link
- Hind Street Regeneration Zone
- Wirral International Business Park infrastructure
113LOOKING FORWARD - 2005/06 AND BEYOND
- HIGHWAY IMPROVEMENTS will have
- Total nr. of staff 20 FTEs (21 posts)
- Net Revenue Budget (staff) 335.5k
- LTP/Capital Budget 4m/annum Delivery - Staff
-
Consultants - Income Nil - only recharges
- Income Generators None
-
114LOOKING FORWARD - 2005/06 AND BEYOND
- CHALLENGES
- Co-locate at Cheshire Lines and integrate within
New Department - Maintain services during re-organisation
- Re-engineer services to maximise opportunities as
a reunited - Division and one Department
- Adapt and support new Core IT systems
- Contribute to intradepartmental teams to improve
performance - Review necessity for QA procedures to determine
benefits/disbenefits - Production of successful LTP2 maintain high
transport capital settlements - Finding sufficient parking spaces!!
115BIG ISSUES and POTENTIALS
- Further develop Egan and Partnering principles,
expand across all areas, embrace modern
procurement techniques (CPU) but if it aint
broke, dont fix it! - Develop multi-disciplinary working, particularly
in specific Service Improvement areas, e.g. HS,
Forward Planning - Local Transport Plan 2 / Annual Progress Report
- Local Transport Capital Expenditure Settlement
- Comprehensive Performance Assessment
(Environment) - Wirral Waterfront (Birkenhead T C, Wirral Interal
Business Park). - Hoylake/West Kirby (Open Golf Championship -
2006).
116BIG ISSUES and POTENTIALS
- Expand best practice across all areas of
operation - project management, contract performance and
monitoring, user feedback, suitability etc - Contribute to Environmental Issues
- ISO14001 - Sustainable Transport
- Development of Supplementary Planning Guidance to
support LTP/ Sustainable Transport - Recycling
- Develop long-term framework/Partnership
Agreements - Consultants and Contractors
- Customer Care - Members, public (complaints and
feedback).
117Risks
- Failure to submit good LTP2/APR and achieve
acceptable annual - transport capital settlements
- Failure to deliver 5 year programmes to achieve
LTP1 2 targets - Failure to maintain a robust internal budgetary
system - Failure to spend transport capital budget
- Failure to recruit and retain the right calibre
staff - Failure to ensure safe working procedures
(HS/CDM) - Failure to supervise consultants and monitor
performance - Failure to supervise contractors and maintain
construction standards
118KPI Achievement Summary(appendix)
- KPI performance (past/current) and future targets
relating to the Highway Improvements Division. - LTP PIs 03/04 04/05 05/06
- actual target target
- PI 18. Length (km) of cycleways 3 6
3 - PI 19. Nr. of cycle trips 273 290 305
- (Ave daily flow over 5 nr cordons)
- PI 27. Park ride spaces 0 137 50
- PI 34. Bus priority corridors centres
- (corridors S,T V and centre 8) 0 1(V)
1(S) - PI 64. No increase in HGV journey times a
a a - PI 75. Nr. of workplace Travel Plans 4
3 2 - PI 76. Nr. of School/FE Travel Plans 7 5
2
119Family Tree of Divisional structure(appendix)
- Showing clear lines of reporting for Key Issue
Exchange/etc., down to clustered job roles
120Divisional Key Issues
- To develop LTP2 and APR in partnership with other
Merseyside authorities for submission to central
government. - To develop a sustainable transport action plan
for staff working at Cheshire Lines Building. - To inspect all cycle facilities and develop a
maintenance schedule. - To progress the annual capital programme of
highway schemes. - To review the implementation of the revised
procurement strategy for civil engineering
projects. -
- Specific
- Measurable
- Agreed
- Realistic
- Time bound
121Service Plan April 2005 March 2006
- Division
- Building Control
122Service Plan
- Divisional Head
- Paul Grey
123Divisional Summary - pre FFP
124Core Services
- Building Regulations - Administering national
legislation across a broad range of construction
projects and processing applications for approval - Safety at Sports Grounds - Co ordination of the
safety team, monitoring the safety of the public
attending events at Prenton Park and the
performance of stadium management with regard to
compliance with the safety certificate - Dangerous Structures - Maintaining a round the
clock emergency response to co ordinate the
removal of any danger - Event Safety/Entertainment Liquor Licensing -
Advice to Members and Licensing Justices on the
suitability of venues/premises with regard to
public safety requirements - Demolitions - Ensuring the safety of the public
and protection of adjacent buildings during
demolition operations, processing of applications
and issue of counter notices - Hoarding and Scaffolding - Processing permit
applications, inspection of sites and issue of
schedule of conditions, where on the highway
125SOME OF OUR ACHIEVEMENTS DURING 2003/04
- Currently Rated by Best Value Inspectorate - Good
2 Star, Likely to improve - Significant progress towards service improvement
plan milestones reported to Members - Full Cost Recovery on the self financing building
regulation charge earning budget - fourth
successive year - whilst maintaining a quality
service - Successfully delivered annual safety project plan
for the Boroughs designated sports ground
(Prenton Park) - service re engineered - Co ordination of the Councils response to the
Fire Precautions (Workplace) Regulations, leading
to the satisfactory risk assessment of 95 of
premises - Responded to 247 (100) of emergency call outs
within 60 minutes - All submitted building regulation applications
determined within statutory time limits (2525 -
5weeks/2months) - Top half of Merseyside authoritys in respect of
agreed, key local benchmarks - National Quality and Performance Matrix (QPM)
figure equalled target 60
126LOOKING FORWARD 2005/06 AND BEYOND
- Business Projection Fit For Purpose
- Opportunity to build on market leading business
performance - Building Control Fee Earning - Total
Expenditure 466,500 -
Total Income 669,200 -
Net Expenditure 202,700 (surplus) - Building Control Non Fee Earning - Total
Expenditure 295,100 -
Total Income 4,400 -
Net Expenditure 290,700 - Net Cost of entire Building Control operation
88,000 - OUTSTANDING VALUE
-
127LOOKING FORWARD 2005/06 AND BEYOND
- CHALLENGES
- Establish Empty Property Strategy, as key
Streetscene driver - Enable proactive use of available
legislation (sect.79)/LOPA 1925 - Identify pump priming finance as a kick
start - role for new legal - Example of benefits from a North West Core City
- Properties brought back into use/all debts paid
- 235 - Properties sold to new owners
- 49 - Outstanding debt owed to Council, repaid prior to
sale - 258,330 - Outstanding debt recovered through the sale of
property - 244,788
128LOOKING FORWARD 2005/06 AND BEYOND
- CHALLENGES
- Implementation of the ODPM priority outcome - R8,
Online receipt and processing of Building
Regulation applications by the end of 2005 - Impact of Government proposals for Modernisation
of Licensing Laws - Continuing obligation under the Charges
Regulations to achieve break even over a three
year rolling period for building regulation work - Significantly extended responsibilities under the
Building Regulations due to the implementation of
major revisions to Parts A, C E - Additional responsibility/liability under Part M
and the requirement for access audits with the
continued introduction into UK legislation of DDA
- New responsibilities for electrical installations
Part P - New responsibilities to administer a self
certification scheme for electrical installations - Introduction of proactive measures to combat
cowboy builders
129BIG ISSUES and POTENTIALS
- Re engineering of application processing and
information provision to enable transfer of
resources to the call centre by February 2005 - Continuing support and development of the B C
Management Information System (BCMIS) requires
update completion
130Risks
- Inability to recruit and retain appropriate
levels of quality staff - Loss of network and management IT systems and
systems development capability - No formal data capture plan to facilitate
electronic land charges/searches system. Key
staff are being allowed to leave without adequate
replacement - Unique knowledge of key personnel Building
Regulation Charge setting -
Safety at Sports Grounds - Damage/Loss of reputation if not providing
minimum Government standards. Potential loss of
business to better performing competitors.
Danger of exploitation of perceived weaknesses - Disruption of licensing panel or Court hearing
due to lack of divisional representative
131KPI Achievement Summary
132KPI Achievement Summary - QPM
133KPI Achievement Summary - AGMA
134KPI Achievement - summary
135Family Tree of Divisional structure
136Divisional Key Issue