Title: Electron cooling at the Recycler Status report
1Electron cooling at the RecyclerStatus report
- Lionel Prost
- DOE Tevatron Operations Review
- March 21, 2006
2Electron cooling status - Summary
- The electron cooling system installation was
finished on February 25th, 2005, at which date
commissioning began. - Cooling of 8 GeV antiprotons with the electron
beam was first demonstrated on July 15th, 2005
and was reported at the COOL05 workshop held in
Galena, IL. - Electron cooling was used for almost all collider
shots since - On October 5th, 2005, Recycler-only shots were
implemented. - Availability and reliability of the electron
cooling system is important for this mode of
operation to be profitable - It effectively passed the burden of cooling from
the Accumulator onto the Recycler - Fermilab now has a world-record operational
electron cooling system - 4.3 MeV, up to 1.5 A DC (U-Bend mode)
- Beam power 6.5 MW (New world record)
3Electron cooling system setup at MI-30/31
Added section
(includes additional pumping)
Beam line accommodates both U-bend and vertical
bend magnets
Fast acting valves
Magnetically shielded to protect e beam from
fields imposed by the MI bus
4Electron cooling system setup at MI-30/31
Pelletron (MI-31 building)
Cooling section solenoids (MI-30 straight section)
5Electron beam design parameters
- Electron kinetic energy 4.34 MeV
- Uncertainty in electron beam energy ? 0.3
- Energy ripple 500 V rms
- Beam current 0.5 A DC
- Duty factor (averaged over 8 h) 95
- Electron angles in the cooling section
- (averaged over time, beam cross section, and
cooling section length), rms ?0.2 mrad
All design parameters have been met
6Recirculation Stability High duty factor has
been met (gt95)
- Running at high current (gt 0.2 A) induces full
discharges (1-2 per week) until the Pelletron
needs to be reconditioned.
2 nTorr 2 nTorr 0.4 MV 0.2 A
Beam current
Pelletron voltage
No full discharges 5 recirculation interruptions
Decel. side pressure
Accel. side pressure
24 hours
7Electron angles in the cooling section
Angles are added in quadrature
Part of shutdown activities
8Electron beam status
- The electron beam stability and duty factor are
adequate for providing cooling when needed - Days of operation without trips for beam current
lt200 mA - Natural interruptions are taken care of
automatically (Java application) - Duty factor gt95 for beam current up to 500 mA
- Conditioning of the Pelletron takes a shift (8 h)
and can be done when the Recycler has a low stack - Less than once per month at low current (i.e. lt
200 mA) - Once per 2-4 weeks at high current (i.e. gt 200
mA) - Actually depends on number of full discharges
- Beam angles are low enough
- Confirmed by the fact that we successfully cool
antiprotons !
9First e-cooling demonstration 07/15/05
10Run II project milestones
- Plan Actual
- Commissioning begins 02/01/05 03/01/05
- U-bend commissioned 03/14/05 04/15/05
- Full beam line commissioned 04/04/05 05/04/05
- A 0.5-A DC beam 07/08/05 07/26/05
- Cooling of antiprotons 09/08/05 07/15/05
- Electron cooling operational 01/02/06 10/03/05
- (contribute to HEP)
11Electron cooling in operation
- In the present scheme, electron cooling is
typically not used for stacks lt 200e10 - Over 200e10 stored
- Electron cooling along with stochastic cooling is
used to maintain a certain longitudinal emittance
(i.e. low cooling from electron beam) between
transfers or shot to the TeV - 1 hour before setup for incoming transfer or
shot to the TeV, electron beam adjusted to
provide strong cooling (progressively) - The electron beam current is set to 100 mA
- Adequate for present number of stored antiprotons
- Longitudinal emittance of the bunch before mining
and extraction is typically lt 70 eVs - Some indirect interaction may exist between
electron cooling and stochastic cooling
This procedure is intended to maximize lifetime
12Adjusting the cooling rate
- Two knobs
- Electron beam current
- Beam stays on axis
- Dynamics of the gun varies between low and high
currents - Hence, changing the beam current also changes the
beam size and envelope in the cooling section - Electron beam position
- Adjustments are obtained by bringing the
antiprotons bunch in an area of the beam where
the angles are low
Area of good cooling
Schematic transverse profiles Pink pbars Blue
e-beam
5 mm offset
2 mm offset
13Electron cooling between transfers/extraction
Electron beam out (5 mm offset)
Electron beam current0.1 A/div Transverse
emittance1.5 p mm mrad/div Electron beam
position1 mm/div Longitudinal emittance
(circle)25 eVs/div Pbar intensity(circle)16e10/
div
Electron beam is moved in
Stochastic cooling after injection
100 mA
60 eVs
1 hour
195e10
14Electron cooling drag rate - Theory
- For an antiproton beam with zero transverse
velocity, electron beam 500 mA, 3.5-mm radius,
300 eV rms energy spread and 200 µrad rms angular
spread
Non-magnetized cooling force model
Linear approx.
15Cooling force Experimental measurements
- Two experimental techniques, both requiring small
amount of antiprotons, coasting (i.e. no RF) with
narrow momentum distribution and small transverse
emittances - Diffusion measurements
- For small deviation cooling force (linear part)
- Reach equilibrium with electron cooling
- Turn off electron cooling and measure diffusion
rate - Adding external source of noise (constant) can
lead to the determination of the entire curve - Equilibrium distribution gives the shape of the
curve - Diffusion rate (with the added noise) gives the
amplitude - Electron energy jump method
- Reach equilibrium with electron cooling
- Instantaneously change electron beam energy
- Follow antiprotons momentum distribution
evolution - Both methods characterize the effectiveness of
electron cooling (hence, the electron beam
quality) quite locally and not necessarily the
cooling efficiency/rate for large stacks
16Drag Force as a function of the antiprotons
momentum deviation100 mA, on axis, nominal
cooling settings
17Improvements/upgrades to be implemented during
the shutdown
- The control system of the bending magnets power
supplies has posed various reliability problems - It has been entirely replaced by an in-house
design using an Internet Rack Monitor (IRM) - New system was tested on the bench and showed
excellent stability - New system was also tested on two (out of 10)
magnets before the start of the shutdown - Installation of a ground bypass around the
cooling section - Uncompensated bus currents from MI ramping induce
currents to the beam pipe, which in turn induce
an erroneous reading of the bend fields by the
NMR probes - Noisy field readings
- Connect low resistance cable to the Recycler beam
pipe - Should reduce induced currents by a factor of 10
(from 100 mA to 10 mA) - Improve bending fields regulation
18Improvements/upgrades to be implemented during
the shutdown (cont)
- Shielding for cameras in the MI tunnel
- CCD cameras to be used with Optical Transition
Radiation (OTR) detectors could not survive more
than a few hours the level of radiation coming
from MI losses - Affects several diagnostics stations at the end
of the cooling section and the return line - Cameras will now be installed away from the MI
beam line and shielded from direct radiation - Upgrade of the SF6 gas recirculation system
- Present system is undersized for operational
conditions - Partly because of the larger volume
- New specifically designed all-in-one skid
- Operation at a lower gas temperature
- Reduction of down-time for maintenance and
service - Improved diagnostics to monitor the system
19Conclusion
- Although commissioning of the electron cooler
started 1 month behind schedule, cooling
demonstration of 8 GeV antiprotons was achieved
2 months ahead of schedule - Fermilab now has a world-record operational
electron cooling system - Since the end of August 2005, electron cooling is
being used on (almost) every Tevatron shot - Recycler not only stores antiprotons but cools
them to the required emittances - Increases of stack sizes are a direct consequence
of the ability to cool the beam efficiently
(current record 437e10) - Electron cooling allowed for the latest advances
in the TeV peak luminosity (current record 172e30
cm-2 s-1)