Electron cooling at the Recycler Status report - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Electron cooling at the Recycler Status report

Description:

DOE Tevatron Operations Review Lionel Prost. 3. f. Electron cooling system setup at MI-30/31 ... DOE Tevatron Operations Review Lionel Prost. 6. f ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 20
Provided by: mcgi45
Category:

less

Transcript and Presenter's Notes

Title: Electron cooling at the Recycler Status report


1
Electron cooling at the RecyclerStatus report
  • Lionel Prost
  • DOE Tevatron Operations Review
  • March 21, 2006

2
Electron cooling status - Summary
  • The electron cooling system installation was
    finished on February 25th, 2005, at which date
    commissioning began.
  • Cooling of 8 GeV antiprotons with the electron
    beam was first demonstrated on July 15th, 2005
    and was reported at the COOL05 workshop held in
    Galena, IL.
  • Electron cooling was used for almost all collider
    shots since
  • On October 5th, 2005, Recycler-only shots were
    implemented.
  • Availability and reliability of the electron
    cooling system is important for this mode of
    operation to be profitable
  • It effectively passed the burden of cooling from
    the Accumulator onto the Recycler
  • Fermilab now has a world-record operational
    electron cooling system
  • 4.3 MeV, up to 1.5 A DC (U-Bend mode)
  • Beam power 6.5 MW (New world record)

3
Electron cooling system setup at MI-30/31
Added section
(includes additional pumping)
Beam line accommodates both U-bend and vertical
bend magnets
Fast acting valves
Magnetically shielded to protect e beam from
fields imposed by the MI bus
4
Electron cooling system setup at MI-30/31
Pelletron (MI-31 building)
Cooling section solenoids (MI-30 straight section)
5
Electron beam design parameters
  • Electron kinetic energy 4.34 MeV
  • Uncertainty in electron beam energy ? 0.3
  • Energy ripple 500 V rms
  • Beam current 0.5 A DC
  • Duty factor (averaged over 8 h) 95
  • Electron angles in the cooling section
  • (averaged over time, beam cross section, and
    cooling section length), rms ?0.2 mrad

All design parameters have been met
6
Recirculation Stability High duty factor has
been met (gt95)
  • Running at high current (gt 0.2 A) induces full
    discharges (1-2 per week) until the Pelletron
    needs to be reconditioned.

2 nTorr 2 nTorr 0.4 MV 0.2 A
Beam current
Pelletron voltage
No full discharges 5 recirculation interruptions
Decel. side pressure
Accel. side pressure
24 hours
7
Electron angles in the cooling section
Angles are added in quadrature
Part of shutdown activities
8
Electron beam status
  • The electron beam stability and duty factor are
    adequate for providing cooling when needed
  • Days of operation without trips for beam current
    lt200 mA
  • Natural interruptions are taken care of
    automatically (Java application)
  • Duty factor gt95 for beam current up to 500 mA
  • Conditioning of the Pelletron takes a shift (8 h)
    and can be done when the Recycler has a low stack
  • Less than once per month at low current (i.e. lt
    200 mA)
  • Once per 2-4 weeks at high current (i.e. gt 200
    mA)
  • Actually depends on number of full discharges
  • Beam angles are low enough
  • Confirmed by the fact that we successfully cool
    antiprotons !

9
First e-cooling demonstration 07/15/05
10
Run II project milestones
  • Plan Actual
  • Commissioning begins 02/01/05 03/01/05
  • U-bend commissioned 03/14/05 04/15/05
  • Full beam line commissioned 04/04/05 05/04/05
  • A 0.5-A DC beam 07/08/05 07/26/05
  • Cooling of antiprotons 09/08/05 07/15/05
  • Electron cooling operational 01/02/06 10/03/05
  • (contribute to HEP)

11
Electron cooling in operation
  • In the present scheme, electron cooling is
    typically not used for stacks lt 200e10
  • Over 200e10 stored
  • Electron cooling along with stochastic cooling is
    used to maintain a certain longitudinal emittance
    (i.e. low cooling from electron beam) between
    transfers or shot to the TeV
  • 1 hour before setup for incoming transfer or
    shot to the TeV, electron beam adjusted to
    provide strong cooling (progressively)
  • The electron beam current is set to 100 mA
  • Adequate for present number of stored antiprotons
  • Longitudinal emittance of the bunch before mining
    and extraction is typically lt 70 eVs
  • Some indirect interaction may exist between
    electron cooling and stochastic cooling

This procedure is intended to maximize lifetime
12
Adjusting the cooling rate
  • Two knobs
  • Electron beam current
  • Beam stays on axis
  • Dynamics of the gun varies between low and high
    currents
  • Hence, changing the beam current also changes the
    beam size and envelope in the cooling section
  • Electron beam position
  • Adjustments are obtained by bringing the
    antiprotons bunch in an area of the beam where
    the angles are low

Area of good cooling
Schematic transverse profiles Pink pbars Blue
e-beam
5 mm offset
2 mm offset
13
Electron cooling between transfers/extraction
Electron beam out (5 mm offset)
Electron beam current0.1 A/div Transverse
emittance1.5 p mm mrad/div Electron beam
position1 mm/div Longitudinal emittance
(circle)25 eVs/div Pbar intensity(circle)16e10/
div
Electron beam is moved in
Stochastic cooling after injection
100 mA
60 eVs
1 hour
195e10
14
Electron cooling drag rate - Theory
  • For an antiproton beam with zero transverse
    velocity, electron beam 500 mA, 3.5-mm radius,
    300 eV rms energy spread and 200 µrad rms angular
    spread

Non-magnetized cooling force model
Linear approx.
15
Cooling force Experimental measurements
  • Two experimental techniques, both requiring small
    amount of antiprotons, coasting (i.e. no RF) with
    narrow momentum distribution and small transverse
    emittances
  • Diffusion measurements
  • For small deviation cooling force (linear part)
  • Reach equilibrium with electron cooling
  • Turn off electron cooling and measure diffusion
    rate
  • Adding external source of noise (constant) can
    lead to the determination of the entire curve
  • Equilibrium distribution gives the shape of the
    curve
  • Diffusion rate (with the added noise) gives the
    amplitude
  • Electron energy jump method
  • Reach equilibrium with electron cooling
  • Instantaneously change electron beam energy
  • Follow antiprotons momentum distribution
    evolution
  • Both methods characterize the effectiveness of
    electron cooling (hence, the electron beam
    quality) quite locally and not necessarily the
    cooling efficiency/rate for large stacks

16
Drag Force as a function of the antiprotons
momentum deviation100 mA, on axis, nominal
cooling settings
17
Improvements/upgrades to be implemented during
the shutdown
  • The control system of the bending magnets power
    supplies has posed various reliability problems
  • It has been entirely replaced by an in-house
    design using an Internet Rack Monitor (IRM)
  • New system was tested on the bench and showed
    excellent stability
  • New system was also tested on two (out of 10)
    magnets before the start of the shutdown
  • Installation of a ground bypass around the
    cooling section
  • Uncompensated bus currents from MI ramping induce
    currents to the beam pipe, which in turn induce
    an erroneous reading of the bend fields by the
    NMR probes
  • Noisy field readings
  • Connect low resistance cable to the Recycler beam
    pipe
  • Should reduce induced currents by a factor of 10
    (from 100 mA to 10 mA)
  • Improve bending fields regulation

18
Improvements/upgrades to be implemented during
the shutdown (cont)
  • Shielding for cameras in the MI tunnel
  • CCD cameras to be used with Optical Transition
    Radiation (OTR) detectors could not survive more
    than a few hours the level of radiation coming
    from MI losses
  • Affects several diagnostics stations at the end
    of the cooling section and the return line
  • Cameras will now be installed away from the MI
    beam line and shielded from direct radiation
  • Upgrade of the SF6 gas recirculation system
  • Present system is undersized for operational
    conditions
  • Partly because of the larger volume
  • New specifically designed all-in-one skid
  • Operation at a lower gas temperature
  • Reduction of down-time for maintenance and
    service
  • Improved diagnostics to monitor the system

19
Conclusion
  • Although commissioning of the electron cooler
    started 1 month behind schedule, cooling
    demonstration of 8 GeV antiprotons was achieved
    2 months ahead of schedule
  • Fermilab now has a world-record operational
    electron cooling system
  • Since the end of August 2005, electron cooling is
    being used on (almost) every Tevatron shot
  • Recycler not only stores antiprotons but cools
    them to the required emittances
  • Increases of stack sizes are a direct consequence
    of the ability to cool the beam efficiently
    (current record 437e10)
  • Electron cooling allowed for the latest advances
    in the TeV peak luminosity (current record 172e30
    cm-2 s-1)
Write a Comment
User Comments (0)
About PowerShow.com