EASTERN CAPE HOUSING DELIVERY
  • REVIEW FOR THE FIRST 9 MONTHS OF THE 2006/07
    FINANCIAL YEAR

2
PRESENTATION OVERVIEW
  • FINANCIAL NON-FINANCIAL DELIVERY OUTPUTS
  • IDENTIFIED PERFORMANCE CONSTRANTS
  • Strategic,
  • with the related
  • Operational impacts
  • REMEDIAL INTERVENTIONS THE PARADIGM SHIFT
  • UPDATE ON INTERVENTIONS UNDERTAKEN
  • CONCLUSION

3
(No Transcript)
4
EXPENDITURE vs CASH FLOW FORECASTIN DISTRICT
ORDER
5
NON-FINANCIALS
6
OUTPUTS FOR THE 1ST 9 MONTHS
  • Number of emergent contr. 686
  • Jobs created 3
    539
  • Houses completed 11 791
  • Subsidies approved 6 799
  • Title Deeds transferred 4 913
  • Municipalities accredited (in process) 2
  • Disaster housing assistance 100

7
NEGATIVE FACTORS INFLUENCING HOUSING DELIVERY.
  • STRATEGIC CONSIDERATIONS
  • The challenges facing E/Cape housing delivery
    must be seen against the following strategic
    approaches, initially undertaken
    fordevelopmental reasons
  • Use of PHP delivery vehicle (60 of E.C.
    projects are PHP) (slow delivery due to
    layered coordination communication processes)
  • Majority of Developers are Municipalities
  • Use of Emerging Contractors
  • 40 sq.m. size unit on 30sq.m National Norm
  • Allocation (Unfunded extra 10m²)
  • The negative impact of these factors has been
    building up over the years to what is now
    possibly the highest point

8
HOUSING RECOVERY INTERVENTIONS
  • Departmental take-over of some of the
  • unblocked projects which are slow-moving
  • through engagement of Established
  • Contractors inclusive of Thubelisha
  • Addresses twin-problem of Municipal and
    Emerging Contractor capacity shortfalls
  • The involvement Established Contractors allows
    for a number of advantages
  • Speedier Procurement Processes
  • Bulk material purchases
  • Sourcing of additional resources to reinforce
    existing construction teams

9
HOUSING RECOVERY INTERVENTIONS (ROLE OF
ESTABLISHED CONTRACTORS)
  • The Established Contractors are performing
  • the normal contractor role, inclusive of
  • Execution of Construction Works to Scope,
    Budget, Spec, Schedule (Penalty clauses to be
    enforced)
  • Materials and labour procurement
  • Site Management Handover of Works
  • Key Ingredient
  • Embracing emerging contractors in order to mentor
    them to graduate to higher skills expertise
    levels within requirements of allocating projects
    to them in accordance with requisite capacity

10
PROGRESS TODATE
  • A fast-tracked procurement process affecting a
    total of 18 projects ( combined value R433m) will
    ensure on-site activity early in March
  • Projects in new financial year are being packaged
    for execution through Established Contractors.
  • A quantum leap in provincial delivery is envisaged

11
CONCLUSION
  • 1. The Department is confident that the
    dominant elements of the delivery
    under-performance problem have now been exposed,
    and are being dealt with in a meaningful way.
  • 2. Even though the paradigm shift and strategic
  • intervention currently embarked on will
    only begin to take effect at the tail-end of
    current financial year, a solid basis has been
    laid for higher-level delivery performance in
    the remainder of the MTEF cycle

12
Thank You