Title: EASTERN CAPE DEPARTMENT OF HOUSING
1 EASTERN CAPEDEPARTMENT OF HOUSING
-
- PRESENTATION TO SELECT COMMITTEE ON FINANCE
- 13/02/08
- HOUSING EXPENDITURE FOR THE FIRST 9 MONTHS
- 2007/08 FINANCIAL YEAR
- MEC HLTA Mrs. T Xasa
2Key challenges
- Practical realities on the ground
3- Poor planning
- Approval of projects that are not ready
- Land issues
4- Lean pool of established contractors attracted to
low cost housing resulting in retendering - Inability of bidders to produce NHBRC
certificates - Slow NHBRC project and home enrollment
- Material Supplies
5- Slow take off of the established contractor
construction - Re tendering for the emergency housing
- NHBRC slow start on the rectification programme
- EIA
6HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENT1st
9 MONTHS OF 2007/08
7 CASH FLOW FORECASTS vs. EXPENDITURE IRO
PROJECTS PER DISTRICT - THE 1ST 9 MONTHS OF
2007/8
8ACTUAL OUTCOME HOUSING CONDITIONAL GRANT 2007/08
- HOUSING ALLOCATION 2007/08 R1,052 ,554
- LESS
- FUNDS SURRENDERED R 543,078
- REVISED ALLOCATION 2007/08 R 509,476
- LESS
- EXP. AS AT END DECEMBER 2007 R 155,219
- BALANCE OF FUNDS 31Dec. 2007 R 354,257
9HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENTNOV
DEC - 2007/08(AFTER REVISION)
10AREAS TO BENEFIT FROM R500M
- Alternative sanitation and energy
- Military Veterans Programme
- Inclusionary housing
- Delivery on social housing
- Intensify rural housing
11HOUSING CONDITIONAL GRANT - 2007/08CASH FLOW
FORECAST 4TH QUARTER
- JANUARY 2008 R 71,399
- FEBRUARY 2008 R 146,816
- MARCH 2008 R 136,042
- TOTAL R 354,257
122007/8 Non Financial Performance
- Land acquisition for inclusive housing
- The department is currently busy with Audit of
well located suitable land for Housing
Development. - Negotiations are already in process for land in
identified areas e.g. Maletswai Buffalo City
Municipalities - 192 units in Amalinda (SOHCO) have had their
consents signed and are in the process of taking
transfer
13- Rural Housing Summit and launch of innovation hub
- 37 new projects and 16 385 housing subsidies
approves - 2 Locrete Technology show houses from Kuwait
completed and packaged for shipping
14- 6342 sites serviced
- 4569 houses completed and 3000 at various stages
of completion - 3519 transfers registered
15Progress on the Turn Around Plan
- Operation Thunderstorm
- Various Housing Projects Nine projects allocated
to established contractors - Construction commenced in all nine projects
- Expenditure kicked in December
16Progress on the Turn Around Plan
- Proactive Planning for 2008/9
- Department Driven projects
- Tenders for 14 projects translating into 5191
units now under adjudication - Appointments to be made by end Feb and
contracting and site establishment planned for
March
17Progress on the Turn Around Plan
- Proactive Planning 2008/9
- Municipal Driven projects
- Tender process completed for 15 projects
amounting to 8461 housing units with a value of
R329, 082, 134 - Awarding of tender during February
18Progress on the Turn Around Plan
- Capacity Enhancement
- The appointment of a Rapid Delivery Team (multi
disciplinary) to augment the capacity of the
department in various disciplines and assist with
fast tracking delivery has been done and the team
is in operation. - 3 GM and 2 Senior Managers appointed
- 39 positions advertised 16 are technical