DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT
NORTHERN CAPE
- PRESENTATION TO
- PUBLIC HEARING ON CONDITIONAL GRANTS
- 22 MAY 2007
2(No Transcript)
3ALLOCATION VS EXPENDITURE 2006/07
- The Northern Cape was allocated a budget of
R104, 774m for the 2006/07 in respect of the
Integrated Housing and Human Settlement
Development grant. - The expenditure for 2006/07 was R104,713
- A rollover request of R60,000 was submitted to
treasury
4(No Transcript)
5DRAW DOWNS VS. ACTUAL EXPENDITURE2006/2007
6(No Transcript)
7REASONS FOR SLOW SPENDING
- The first two quarters expenditure trends was low
due to non-performing contractors on a number of
projects - Capacity constraints within the department
8HOUSING ACHIEVEMENTS DURING 2006/07
 Houses Houses Services Services
District Running Blocked Running Blocked
Frances Baard 701 247 528 0
Kgalagadi 277 0 180 0
Siyanda 278 153 311 0
Namakwa 21 76 10 181
Pixley ka Seme 327 215 319 56
Total houses and services 1604 691 1348 237
Grand total 2295 2295 1585 1585
9PROGRESS ON BLOCKED PROJECTS
- The department had 52 blocked projects
- 25 of these projects have been completed
- 24 are currently under construction for
completion by March 2008 - 3 blocked projects under construction will only
be completed by March 2009
10(No Transcript)
11(No Transcript)
12SUMMARY OF PLANNED HOUSES PER DISTRICT 2007-08
District Top structures Service Sites Allocation R000
Frances Baard 507 522 37,899
Kgalagadi 180 100 6,717
Siyanda 455 922 25,560
Namakwa 290 0 12,203
Pixley Ka Seme 1 234 1241 42,798
TOTAL 2 666 2785 125,177