Title: LHC
1D. Lissauer Brookhaven National
Laboratory Presentation to HEPAP Future
Facilities Subcommittee
U.S. Participation in LHC Upgrade
- LHC Upgrade Schedule and Options
- Physics Motivation
- Detector Upgrades
- Machine Upgrade Options
- Conclusions
- Questions/Answers
2LHC Schedule Upgrade Options
- LHC Schedule
- First Beams April 2007
- Physics Run July 2007
- LHC Upgrade Options
- Luminosity upgrade SLHC L 1035 cm-2 s-1
- --extends LHC mass reach by 20-30
- --modest changes to machine
- --very challenging for experiment
- --time scale 2014
-
- Energy Doubled LHC - EDLHC ?s 25 TeV L
1034-1035 cm-2 s-1 - --extends LHC mass reach by 1.5-2 for
L1034-1035 - --requires new machine (e.g. 15 T magnets )
- --very expensive option
- --time scale gt 2020
3Physics Potential of SLHC
- integrated luminosities
Detector Performance at SLHC - LHC 100 fb-1/year L ? 2 x 1034
needs to be similar to LHC.
- SLHC 1000 fb-1/year L 1035
- Higgs physics
- rare decay modes
- Higgs self-couplings
- Higgs couplings to fermions and bosons
- Supersymmetry
- Heavy Higgs bosons of the MSSM
- Mass reach up to 3 TeV
- New Gauge Bosons
- Strongly-coupled vector boson system
- WLZL g WLZL WLWL g WLWL , ZLZL
- Extra Dimensions
- Quark substructure
- Electroweak Physics
- production of multiple gauge bosons (nV .ge. 3)
- triple and quartic gauge boson couplings
4Strongly Coupled Vector Boson System
If no Higgs, expect strong VLVL scattering
(resonant or non-resonant) at
- Difficult at LHC
- At SLHC
- degradation of fwd jet tag and central jet veto
due to pile-up - BUT factor 10 in statistics ? 5-8? excess in
WL WL scattering - ? other low-rate channels accessible
5Indicative Physics Reach
Units are TeV (except WLWL reach) Integrated
luminosities correspond to 1 year of running at
nominal luminosity for 1 experiment
PROCESS LHC SLHC
EDLHC 14 TeV 14 TeV 28 TeV
100 fb-1 1000 fb-1
100 fb-1 Squarks 2.5
3 4 WLWL
2? 4? 4.5? Z
5 6
8 Extra-dim (?2) 9 12
15 q
6.5 7.5 9.5 ?
compositeness 30 40
40
6Detectors General Considerations
7ATLAS
8CMS
9Inner Tracking
- The inner tracker will need to be re-built using
higher granularity detectors in a harder
radiation environment in order to preserve the
current pattern recognition, momentum resolution,
b-tagging capability. - a Radiation increase by 10.
- a To keep Occupancy constant granularity has to
increase by a factor 10. - Small Radius Region Vertex detector (r lt 20cm)
-
- aim for a pixels size factor 5-8 smaller than
today - (50x400 mm2 g 50 x 50 mm2) g benefit
b-tagging, t-tagging - RD
- Pixels Sensor Technologies
-
- Super rad-hard electronics to achieve small
pixel sizes.
10Inner Tracking
- Intermediate Radius 20ltrlt60 cm
- Aim for cell sizes 10 times smaller than
conventional Si strip - detectors.
- benefit momentum-resolution and pattern
recognition - RD
- Lower cost/channel compared to present Si strip
detectors - Si macro-pixels of an area 1mm2 pads or
shorter strips ? - Single sided two dimensional readout (new
concepts) - Large Radius 60ltr
- Large area Si detectors.
- Could use present day radiation resistant
strip technology, - or new single sided technology
- RD
- Similar to intermediate radius less demanding
except for cost.
11Inner Tracking
Engineering/Integration Aim at a factor of 10
more channels but with less material. This means
that the System aspects have to be integrated and
understood from the start. RD new light
weight materials for stable structures, Power
Multiplexing of readout cooling,
alignment installation and maintenance
aspects Activation 250 mSv/h implications for
access and maintenance Timescale Need 8-10
years from launch of RD 4-6 years of
RD and prototyping , 4 years to build,
12Calorimeter
Increased Luminosity will increase the
contribution of the pile up to the noise by a
factor of 3. Increased radiation will imply
moderate changes to the detectors mostly in the
forward direction. RD Endcap find an
alternative to plastic scintillator (CMS) Long
term irradiation effects on crystals.
(CMS) Readout electronics some will need to
be upgraded for increased radiation level.
E.g ATLAS Front end board should be redesigned
either by making components more radiation
resistant,and/or use analog optical links to
bring the signals out.
13Muon System
- Current ATLAS/CMS Muon systems have a safety
factor of 3-5 with respect to background
estimations. - Background has strong geometric dependence
-
- Detectors that now function at high-h at LHC will
function at low-h in SLHC - Radio-activation at high h, of shielding,
supports and nearby detectors - may limit maintenance access
- Strategy
- Balance robust detectors vs. shielding and
reduced high-h acceptance - RD
- Study limits of current detectors possible
use of CSCs at lower h. - At high-h - higher rates higher granularity
CSCs, GEMs?
14Level-1 Trigger/DAQ
- Increased LHC Luminosity up to SLHC means trigger
and DAQ needs to evolve in time. - Reduced Bunch crossing to 12.5 n-sec will have an
impact on the Level 1 trigger architecture. - RD
- Study Required modifications to LVL1 trigger and
detector front end - electronics.
- Data transfer for processing at 80 MHz sampling.
- Synchronization (TTC, etc) becomes an issue for
short bunch crossing - period.
- How to handle bandwidth (rate ? size) is an
issue both for readout and - for event building.
15LHC Upgrade Options
- SLHC Luminosity upgrade to 1035
- -- increase bunch intensity to beambeam limit
? L 2.5 x 1034 - -- halve bunch spacing to 12.5 ns (electron
cloud limitation?) - --Reduce ? to ??0.25 m (from 0.5 m)
- --Increase crossing angle.
- --Reduce bunch length. (new RF)
- --Super Bunch option being investigated.
-
moderate hardware changes time scale ? 2014
- EDLHC ? s upgrade to 25 TeV
- -- ultimate LHC dipole field B 9 T ? ?s
15 TeV - ? any energy upgrade requires new machine
Injector - -- present magnet technology up to B 10.5 T
- small prototype at LBL with B 14.5 T
- -- magnets with B17 T may be reasonable
target for operation - in gt2020 provided intense R D
- on new superconductors (e.g.
Nb3Sn)
major hardware changes time scale ? 2020
16U.S. Role in Machine RD
- LHC RD by the U.S. Labs will focus on increasing
the luminosity. - Understand the limitations of the current machine
configuration, particularly the IRs, and
develop proposed modifications. - Low b insertion sections (separation dipoles,
triplet quads) - Develop high-field Nb3Sn magnets for new low b
insertion b 15-20 cm seems possible. - Next Generation Machine Instrumentation and
feedback systems. - Other luminosity upgrade RD to be addressed by
CERN, e.g. - r.f. upgrades for halving bunch length or
handling superbunches - collaborate with U.S. labs on RD on luminosity
upgrade magnets - RD for EDLHC adequately covered by U.S. base
program. - High-field Nb3Sn dipole RD and BNL, FNAL and
LBNL addresses either EDLHC or VLHC.
17Conclusions
- Physics reach of LHC can be extended
significantly by increasing the Luminosity by a
factor of 10 or by doubling the energy of the
machine. - Luminosity upgrade can be achieved by 2014
- Detectors must preserve (the expected LHC)
performance to realize the physics potential. - RD for both machine and detectors upgrades
needs to start soon. (Note that many present
ATLAS/CMS detectors started RD in 87) Assuming
sufficient funds, this is covered by the
LHC Research Program. - US Machine RD projects are well suited to the
capabilities at - the three national labs. (FNAL, BNL LBNL)
18Conclusions
- Tracking system upgrade is the most challenging.
The system - will need to be almost completely rebuilt.
Significant RD is - needed covering the full spectra from generic
new materials - to system integration.
- Calorimeters and Muon systems should be able to
perform well with moderate upgrades.This will
involve mostly increasing the radiation hardness
of the readout electronics. - Trigger,DAQ will be upgraded benefiting from
commercial developments. - Strong US involvements in the SLHC will ensure
significant U.S. presence at the physics frontier
for the coming decades.
19Questions from the Committee
- What is the estimated cost of the tracking
upgrade, given the greatly increased channel
count associated with the Luminosity upgrade? - 2. Can you give more information on the scope
and cost of the Nb3Sn magnet RD for the
luminosity upgrade? More generally , what would
be the scope of the U.S. part of the accelerator
upgrade? - 3. What is the scope and cost of the U.S. part of
the detector upgrades?
20Tracking Cost estimate
- The estimate is very preliminary and is based on
the following assumptions The active components
of the tracker are all Si. The inner radius has
upgraded Si Pixel detectors, followed by Si Strip
detectors, in the outer radius we use single
sided 2-D Si detectors. - The estimate was done by scaling the cost of the
ATLAS Si detector as well as information from
CMS, and the CDF/D0 upgrade cost. - In scaling the costs we had to make assumptions
on how the main cost drivers will scale with the
number of channels, the area and the expected
time evolution. - The RD and final design will have to be driven
by optimizing the cost to performance of the
overall system.
21Tracking Cost estimate
- Mechanics The mechanics does not scale with the
number of channels. - One has to keep the services and the total
weight to a minimum. - The cost estimate assumes there is added
complexity due to light weight - Si Detectors Scale with the detector area and
only marginally with the granularity. - The optimization of the number of layers and
exact location has not been finalized. The total
amount of Si will be factor of 5-10 greater
than the present ATLAS detector. -
- Possible cost reduction
- Si detectors Cost is driven to a large extent
by the size of the wafers and industry is
moving toward larger wafers. - Minimize the the amount of Si by using
advances in detector technology. For example
single sided 2D readout can be used in the
medium and larger radii where the segmentation
needs are dominated by tracking accuracy rather
than occupancy. -
22Tracking Cost estimate
- On detector read out electronics
- The readout electronics cost is driven by the
number of channels. - Take advantage of the reduction in the feature
size of the electronics. (ATLAS design used
ATMEL/DMILL rad hard technology that has a
conservative feature size of 1.2 Micron in the
Strips. CMS and ATLAS pixels are using sub micron
technology of 0.25 micron) - Present industry standard is 0.18 moving
toward 0.13 microns. We expect that by the time
we go into production the standard feature size
will be as low as 0.08 microns. Allowing for a
substantial reduction in the power and space
needed for the electronics and allowing for finer
granularity without an increase in power and
space needed. - The reduction in power has important
implication also on the cooling and services that
will be needed. -
-
23Tracking Cost estimate
- Module integration
- Module integration costs include costs of
Hybrids and the components assembly. - In the case of the Pixel detectors the cost of
bump bonding Si is a significant part of the
module integration. - Significant cost reductions are possible
assuming one of the integrated developments
matures in time. They integrate the readout and
the active detector on the same wafer
eliminating the need for individual bonds. -
- Cables Data Links
- Assumed a higher level of multiplexing compared
to the present solutions. In particular the
amount of power cables that need to be reduced
for physics (reduced mass), space and cost
reasons. -
- Power Supplies
- Power supplies will need to be optimized and
serve a larger number of modules. This has
implication on coherent noise and very detailed
system integration will be needed to achieve
this. -
24Tracking Cost estimate
- Cooling (Additional) The needed cooling capacity
will scale with the number of channels, but we
have taken advantage of the lower power
requirements of the lower feature size
electronics. A large part of the external cooling
can be reused. -
- Off detector electronics (Read out Drivers) We
have to take advantage of advances and reduction
in the cost of electronics. We assume that a
factor of 10 more data 10 years from now will
cost factor of 1.5 more than present cost. -
-
- The Tracker cost for one detector thus estimated
to be between - 150-180 M. (assuming the full detector is built
in the US) - These numbers are only given as a rough
estimate. We are not ready for an engineering
estimate, which will have to be done after RD
has progressed and better optimization done.
25U.S. Machine RD
26Scope and cost of U.S. involvement.
- Scope
- The U.S. has 20 of the Physicists on both
experiments and contributes close to 20 toward
the construction of ATLAS CMS. -
- In the RD phase of the LHC program the U.S.
contributions have been more significant. The
U.S. participation in electronics development and
production is significantly higher than 20 . - We expect this to hold true also in the SLHC
era. - We note that the Upgrade will take place while
the LHC will be fully operational and a large
maintenance and operations effort will be in
place. - The maintenance and operation will be
concentrated at CERN. In principle this
responsibility will be shared equally between all
collaborators. - The division of responsibility for the upgrade
has not been finalized. We assume the U.S. Share
will be the same as during the construction of
the experiments. (20). -
- There is a good possibility that the U.S. will
trade off some of the MO responsibility for
additional responsibility in the Upgrade. - .
27U.S. cost for SLHC experiments.
- Cost
- The total cost estimate of the upgrade is hard to
predict. - We expect the main cost to be in the tracking
upgrade. - The exact scope of the upgrade for the different
systems is not clear and will be somewhat
different in the two experiments. - The split between the different systems and what
upgrade will be done will have to be a result of
optimization based on actual LHC experience. - One can only make a straw man upgrade model
for the detector upgrade. - This cost does not include RD that we expect to
be covered from the ongoing LHC Research Program.
- We expect that the experiments share will be more
than 2/3 and the rest for the accelerator.