Title: J-Cal%20Construction%20Plan
1J-Cal Construction Plan
- Tatsuya Chujo
- University of Tsukuba
- (for the ALICE J-Cal Project)
2Organization (as of April 2009)
- Staff 6
- Y. Miake (Prof. project leader)
- S. Esumi (Assoc. Prof. physics analysis,
simulation) - T. Chujo (Assist. Prof. design, construction)
- M. Inaba (Assoc. Prof. trigger, readout,
electronics) - T. Horaguchi (new post-doc)
- M. Shimomura (new RA)
- Students 104
- D2 K. Watanabe
- D1 D. Sakata, M. Sano
- M2 H. Yokoyama, K. Midori, T. Todoroki, E.
Hamada, M. Kimura - M1 Y. Sekine, T. Takeuchi
- UG 4 students.
3Detector assembly, workflow and costs
- We visited Wayne State Univ. on Dec. 2008, and
leaned how to build the modules, strips, and SM
from Tom C. and company. - We think that it is possible to make modules
(and maybe strips) at Tsukuba, if we have
stacking stations locally. - Current plan building modules (or strips) at
Tsukuba, and ship them to CERN (or Wayne State)
for the final SM assembly, then install to ALICE.
4Stacking station (_at_ Wayne State Univ.)
- To make one module
- lt 2 hours for stacking (Pb, Scint)
- 24 hours for compression
- 24 hours for pressure control and monitor.
- Total 2.1 days
- 288 moduels x 2.1 days 604 days per SM.
- We need at least 2 or 3 stacking stations, and
pressure control/monitoring systems, in order to
make modules in the reasonable speed. - Detail planning and discussions with Wayne State
U. are necessary.
5Back/front plates, compression plate, support
side plates
Special parts developed at Wayne Sate. Can be
purchased from Wayne State.
6Lead Absorber Plates/Scint. Plates.
- Pb plates Vulcan.
- Scint Uniplast, Russia
- takes 6 months for the new production.
- need a special cutting (at Wayne state)
7Fibers, APD, pre-amp., light guide
Can be purchased them in Japan WLS fiber Y11 Si
APD S8664-55 pre-amp GN-0261-3A APD charge
sensitive amplifier
8Costs estimates
- Budget Total of ?1 M (USD) in 5 yrs (Grant in
Aid, JSPS). - 1 ALICE EMCal module (4 towers) 1,327 (USD, w/o
assembly labor, APD, pre-amp, Strong back, FEE). - 3 SM ( 864 modules)
- Mechanical 1,327 x 864 1,146,528 (USD)
- Readout 50 (APD, preamp) x 4 x 864
172,800(USD) - FEM (4x864 3,456 ch, 26 CHF/ch)
89,856(USD) - Total 1.4 M (USD)
- Mechanical support shipping cost.
9Timeline
2009
2010
2011
2012
Install SM
Install Frame
B-to-B Trigger inst
Detector Construction
Proto-type building
Buying Parts, Production prepare
APD calibration and make DB
Analysis tool development
Data Analysis (pp, PbPb)
Trigger programming dev.
Physics Results
pp
PbPb
pp
6 month LHC shutdown
10Parts for proto-type (for 1 module)
Lead tiles (inside the box)
Courtesy of Tom Cormier
11Summary on construction
- We are proposing to build and install the same
EMCal on the opposite side of the ALICE-EMCal, to
enhance the capability of B-to-B jet physics. - Acceptance 3 SM of ALICE-EMCal (1.0 x 0.7).
- Modules (or Strips) can be built at Tsukuba, and
ship them to CERN (or Wayne State Univ.) for the
final SM assembly and installation . - Need new support structure for the J-Cal.
- Start the mass production in Fall/Winter 2009.
- Current target date installation from summer
2010.
12Backup
13Naming conventions (ALICE-EMCal)
- 1 module 4 towers (4 APD readouts, 1 readout
6x6 (holes) 36 WLS fibers) - 1 strip 12 modules
- 1 super module (SM) 24 strips
- 1 SM ½ sector
- 1 sector 2 SMs.
14ALICE-EMCal Physics Parameters
1SM 22 degrees (0.4 rad) in phi, 0.7 in eta.