Title: Learning from incidents
1Learning from incidents
- Glasgow Caledonian University
- Neal Stone
- Director of Policy Communications
- British Safety Council
2Three ODA award winners 2010 and lessons learnt
- PROJECTS
- Company A International Broadcast Centre/ Main
Press Centre - Company B Sewerage system
- Company C New utilities
3Company A International Broadcast Centre/ Main
Press Centre The Background
- Whilst erecting the steel Beams and Columns a
slinger fitted the piling clamp to a 10 meter
length column. - The piling clamp is a propriety lifting
attachment and is regularly used to lift the
columns. The slinger failed to ensure the pin had
secured properly through the hole in the web. - As the cranes head was directly above the lifting
point the piling clamp would grip until the angle
of the column altered enough for the piling clamp
to slide free. -
- This then left the piling clamp suspended on the
chain and the column falling to the ground. - Fortunately, an exclusion zone was in place and
nobody was injured.
4The piling clamp
Company A International Broadcast Centre/ Main
Press Centre
The Real Picture
Poorly positioned clamp
Dawson clamp
5Company A International Broadcast Centre/ Main
Press Centre Lessons learnt
- Slingers need to ensure that they double check
that all lifting equipment is attached correctly
before signalling the crane driver to begin
lifting. - The design of the piling clamp means that you
rely on the operator to ensure the clamp engages
in the hole using the spring release. Dawson
clamps should be used instead of piling clamps to
lift the columns because there is less of a risk
of an operational error due to the fact the
operator must physically install the pin through
the hole before signalling the crane driver to
begin lifting. - The resulting investigation and near miss report
was shared across the Park.
6Company B Sewerage system The Background
- On 1 April 2009, an employee suffered multiple
fractures and a cracked heel to the left foot
when a concrete shaft segment (approx. 700 kg)
toppled and fell onto his foot. - In recent years as developments of concrete shaft
segment has progressed, the segments have become
thinner and taller, making them less stable when
stored upright in their correct position. The
standard industry practice was to tie the
segments in a stack which was adequate when the
segments were not being used. - The problem arose when a segment was required to
be removed from the end of the stack for use in
the construction. When the ties were released,
the end segment became unstable.
7Company B Sewerage system The Real Picture
Toppled concrete
Segment into frame
Multiple shaft segments into frame
8Company B Sewerage system Lessons learnt
- Key Learning Opportunities
- Sectional ownership reviewed providing slinger
signallers storage responsibilities - All existing segment storage sites checked to
ensure safe storage i.e. provision of segment
restraints. - New 'L' bracket and segment buffers designed as
permanent preventative solution. - 4 Stage safe segment storage working practice
document to be introduced and implemented as a
mandatory requirement. - New Measures
- Segment buffers available
- New guidance sheets available on safe use of
segment buffers. - Ownership is being rolled out to all
supervisors/site agents. - System used across the business
9Company C New utilitiesThe Background
- Company C was required to install over 50 salmor
pits for the 11kv (LVU) installation works. To
install them the ground has to be excavated to
the correct depth and wide enough to accept the
pit. - During the initial installation works, the teams
reported that the standard industry practice for
access and egress was plainly not best practice.
i.e. two ladders tied and criss-crossed, one on
the inside and one on the outside of the pit. The
operative had to access the actual excavation via
a ladder, then climb another ladder on the
outside of the pit, then cross over and descend
into the pit via another ladder on the inside of
the pit. - The reason the access arrangements were like this
was that the excavation when constructed was
supported by battering the sides to an angle of
45. Therefore the edge of the excavation was
always approximately 1 - 1.5 metres away from the
edge of the salmor pit.
10Company C New utilities The Real Picture
Best practice winners 2010
Access platform
The pit
11Company C New utilitiesLessons learnt
- Something that would span the gap between the
excavation and the salmor pit was required. It
would have to be a least 2 metres in length, have
handrails, wide enough to access a ladder safely
to enter the pit, light weight (two man lift
maximum) and robust with stop ends. A quick
prototype was developed and the solution was
found to be ideal for the task in hand. - The access platform eliminated two ladders.
Handrails provided security when accessing the
pit over the excavation. The risk of falling into
the pit during access was eliminated. The
standards of the ladder accessing the pit were
secured to the platform providing more security
for the person. The platform could not slip even
if the platform had to be placed at angles to
access the pit.
12Company C New utilitiesLessons learnt
- What was particularly pleasing about this
innovation was that it did not require a
committee to decide to do it but from a
ground/workface demand the team felt empowered to
go and make it happen. - Project Director (Company C)
13- Thank you
- Neal Stone
- Director of Policy Communications
- British Safety Council