Title: Limpopo Provincial Treasury
1Limpopo Provincial Treasury
- Presentation to the NCOP
- 20 November 2006
2Table of Contents
- Conditional Grants spending as at 30 September
2006 - Observations on Conditional Grants
- Capital Provincial Infrastructure Grant
spending as at 30 September 2006 - Observations on Capital Provincial
Infrastructure Grant - Reasons for under spending
3(No Transcript)
4(No Transcript)
5Observations
- The capacity to spend has improved as department
spent 11 more as compared to the same period of
the previous financial year. - The area of concern is on the following Grants
- Education
- HIV/AIDS 24
6Observations cont.
- Health
- NTSG 28
- FPSG 37
- Housing
- IHHSD 31
- Sport
- MSRPP 17
- Agriculture
- CASP 28
7Observations cont.
- The following conditional grants shows a healthy
spending trends - Education
- FET 50
- Health
- Hospital Revitalization 57
- Agriculture
- Land Care Programme 50
- The under spending clearly demonstrate that
departments approved poor business plans or there
is lack of capacity to implement programmes and
projects
8Corrective Action
- All Conditional Grants business plans for 2007/8
MTEF will be evaluated by treasury in
consultation with departments to ensure that they
are easy to implement and monitor
9Infrastructure Expenditure Trends
10Expenditure Sept 06
11Expenditure Sept 06 incl. rollovers
12Provincial Infrastructure Grant
13Provincial Infrastructure Grant Incl.
adjustments
14(No Transcript)
15Observations
- Expenditure has been slow to pick up across all
sectors - the momentum is been slow to build up
due to late project starting times (expenditure
in subsequent months is affected) - Total expenditure at 39 (with 50 of the time
gone) versus 28.7 for the same period last year - Spending on PIG is at 30 versus 23.8 for the
same period last year - When rollovers and other adjustments are
considered, picture changes for the worse - With total spending going down to 32 (2005/06
24.9) and PIG to 23.1 (2005/06 23.0)
16Observations
- Spending on capital continues to be a challenge
- Key hiccups identified are
- Infrastructure planning (selection of the
projects and business cases not done on time
etc.) - Delay in the procurement processes
- Delays to handover sites due to geo-tech
assessment tests being performed just before
construction as a result of poor planning - Departments not meeting their own cash flow by
projections
17Corrective action
- Multi-year planning processes need to be
strengthened within departments (to avoid
procurement of projects in year of
implementation) - Departments need to review their technical
capacity requirements, i.e. staff - Close monitoring and imposition of heavy
penalties on underperforming contractors
18Corrective action cont.
- Education
- The department has procured the services of a
short-term Technical Assistant to support
infrastructure delivery in the department - The department has also advertised (June 06) for
the services of an infrastructure operational
support team (short-term). The bid was evaluated
in October and an award will be made in due
course. - Health Social Development
- Close monitoring of implementing agents and
contractors. - With hospital projects, these have been packaged
in two lots to speed up delivery. - Established developers are being encouraged to
form joint ventures with CIDB registered emerging
contractors.
19Corrective action cont.
- Agriculture
- A work scheduled was drawn up proposing for the
service providers to do resource audit as well as
drawing a Masterplan within 15 days on whose
basis explicit permission would be given for
final designs and actual physical implementation
of projects. Again it took a long time for
service providers to comply. - Due to the above problems, a decision was taken
to break the Masterplans into implementable
elements without compromising the quality and
integrity of the whole project. Items such as
soil and land surveys, enlargement and lining of
leydams, repairing of bulk water conveyance
systems and repair or replacement of pumps is now
done separately. - The analysis of the unit costs submitted by
Service Providers during tendering has been
completed and one-to-one meetings have been
arranged with Service Providers. Resolution of
this matter will help expedite the submission of
acceptable Bills of Quantity (BoQ) costs and
speedy processing of invoices.
20Corrective action cont.
- Agriculture
- An additional engineer from ARDC (state-owned
entity within the department) has been drafted in
to help with the processing of designs and
related technical work. - The Bid Committee has ratified the appointment of
the Construction Supervision Service Provider in
yet another effort to expedite projects
implementation
21Corrective action cont.
- Roads Transport
- Proactive management of projects, e.g. shifting
of funds to fast-moving multi-year projects that
are already running when delays are encountered
in new projects. - The projects are outsourced to the private sector
with the Roads Agency doing project management.
This enables the department to deliver much
quicker, despite the legal challenges experienced
this year which delayed project implementation,
the department projects to spend all its budget. - The department has a very good project management
capability within the Roads Agency. - In the prior financial year, some districts in
the province experienced very heavy rains and
this affected certain projects, this was also
compounded with the fact that most of the big
contracts were awarded in September. The
department was still able to spend 95 of its
budget.
22Corrective action cont.
- Infrastructure Delivery Improvement Programme
(IDIP) - Phase II of IDIP has commenced (November 2006)
- Two Technical Assistants (TAs) have been seconded
to the departments of Public Works and Education - The TAs will help the departments streamline
planning and delivery processes during the 12
month Technical Assistance programme - This intervention is expected to have an impact
on infrastructure expenditure and delivery in the
medium to long-term as it seeks to address
systemic shortcomings in departments
infrastructure delivery mechanisms, e.g. planning
processes, procurement planning, capacity issues,
etc
23Corrective action cont.
- IDIP..
- A TA will be deployed to the department of Health
in the new year - The Department of Roads Transport enjoys
limited support from a Technical Assistant
stationed at National Treasury. - IDIP also seeks to institutionalize multi-year
planning processes in departments to prevent
planning, procurement and implementation being
done in the same year - this inevitably leads
delays. IDIP extends planning horizons of
departments. - It is expected that once departments are fully
aligned with IDIP principles (e.g. proactive
multi-year planning), under-expenditure will be
eliminated.
24ENDTHANK YOU!!!
25Conditional Grant reasons for under spending
26Reasons for underspending provided by the
department
- Education
- HIV AIDS
- Programmes and workshops are run and conducted
only during school holidays thus hampering
substantial progress as the same target group is
trained on Revised National Curriculum Statement
which is a national priority. - National School Nutrition Programme
- There is always delays in submission of
suppliers invoices and some of those submitted
are erroneous and have to be referred back for
rectification thus causing delays in processing
payments.
27Reasons for underspending provided by the
department--contd
- Health
- HIV and AIDS
- Enormous exercise of verification and payment
processes of 287 NGOs at R 12,5million per
quarter - Delay in filling of vacant posts for which
interviews were conducted. Recommended candidates
had to serve notices at their previous
workstations. - Delay in completion of fixed structures
(Buildings/Containers) intended to increase
working space. - 26 Buildings/Containers on construction. Payment
progress certificates started in the second
quarter. - Shortage of qualified medical personnel in posts
earmarked for ARV and Step Down Facilities
28Reasons for underspending provided by the
department--contd
- Health
- Forensic/Pathology Services.
- Delay in delivery of purchased vehicles due to
conversions required on same vehicles to suit
mortuary specifications. These processes take
longer than five months. - Phased/stepped purchases of 19 mortuary vehicles
to the total amount of R 3,2 million for the year
is in progress. At the end of the quarter
purchases orders for 12 vehicles amounting of
R2,6 million were issued.
29Reasons for underspending provided by the
department--contd
- Health
- National Tertiary Services.
- Shortage of qualified medical personnel in posts
earmarked for Specialists at the Tertiary
Hospital. - Delay in drawing of Specialists Medical
Equipments due to lack of Specialists knowledge
on type of equipments required for specific jobs.
Overall amount involved is R 22 million, and list
of equipments in question follows hereunder - - 2 Portable Ventilators , 2 Bispectral Index
Systems, 4 Infusion pumps, 2 ICU Ventilators, 2
fibre-optic and light source. - Delay in delivery of purchased equipments due to
their extent of sophistication and buildings
alterations needed on installation points. The
statement is with regard to an amount of R7, 2
million on orders as at the end of the quarter.
Another amount of R 3 million worth of
equipments could not be processed for payment at
the Tertiary Hospital due to alterations needed
to be made on the building.
30Reasons for underspending provided by the
department--contd
- Health
- Health Professional Training and Development.
-
- Delay encountered in recruitments and
verifications for appointments of Specialists in
Tertiary and Regional Hospitals. - Delay in delivery of purchased equipments due to
their extent of sophistication and buildings
alterations needed on installation points. This
statement is with regard to the total amount of R
2, 3 million committed on purchases orders placed
by Regional/Provincial and the Tertiary
Hospitals. Lists of break down of commitments on
these orders include amongst others Anaesthetic
Machines, Transport Incubators, Ventilator icu,
Fluid warmers, x-ray machine, Craps, mobile x-ray
units, - Training and development process that follows
specific schedules with external service
providers. - Sizable payments of bursaries for deserving
students will be effected in January/February
2007
31Corrective measures
- Appointment of staff done. Staff linked directly
with the Conditional Grants to avoid delays in
expenditure posting. - Suppliers are being contacted to provide invoices
on completed work in order to allow a progressive
payment that matches with the grants cash flow. - Follow ups are constantly made with Suppliers of
Vehicles. First trench delivery is expected in
the third quarter. - Specification process has been completed.
Adjudication of Specialist Equipments Tender in
progress. Purchases orders will be placed in the
third quarter. - Department has entered into partnership with
United Nations Volunteers in order to intensify
staff recruitment programmes through its program,
UNDP.
32Reasons for underspending provided by the
department--contd
- Local Government and Housing
- Integrated Housing and Human Settlement
Development - The under expenditure is mainly due to late
submission of Geo-tech reports, late
identification of development areas, internal
project management capacity, shortage of building
material (bricks), late submission of beneficiary
forms by municipalities and late pronouncement of
subsidy quantum.
33Corrective measures
-
- Engineers and contractors are closely monitored
to ensure adherence to project implementation
time table. - Creation of additional project management
capacity, i.e. PMU establishment and hiring of
more Project Managers. - The department use trilateral agreement to
purchase building materials for the Developers
(Bricks).
34Reasons for underspending provided by the
department--contd
- Agriculture
- CASP
- The underspending resulted from building of
crush pens, auction pens, dipping tanks, piggery
houses, and holding pens which require more than
a month to be completed.
35Corrective measures
- Due to the above problems, a decision was taken
to break the Masterplans into implementable
elements without compromising the quality and
integrity of the whole project. Items such as
soil and land surveys, enlargement and lining of
leydams, repairing of bulk water conveyance
systems and repair or replacement of pumps is now
done separately. - Additional Capacity
- Internal staff members have undergone training in
Irrigation Design as well as Project Management
during July /September 2006. - An additional engineer from ARDC has been drafted
in to help with the processing of designs and
related technical work. - Repriotization plans are in place to implement
the Biofuels project for R6, 5mill in Sekhukhune.
Reprioritization to pressing Land reform project
of Tea Estates in Vhembe - Engineering Companies have been contracted under
the RESIS program to support other programs on
engineering related activities. - Project Management system - PS Next has been
adopted acquired in September 2006 to improve on
the Database and Reporting. - A shift from micro projects to clustering,
massification and mega projects to improve on the
resource use and impact visibility has been
adopted. The numbers of projects are reduced in
line with HR capacity to implement. - The department has also embarked on the project
massification approach which will also speed the
processes in term of bulk management and spending
36Reasons for underspending provided by the
department--cont
- Sport
- Mass Sport and Recreation Participation Programme
- Underspending as a result of delay in the
advertisement and awarding of tender for sport
equipment.
37Corrective measures
- The tendering process will be finalized in
November and purchases will be done during the
same month. Payments thereof will be done within
the first two weeks of December 2006.
38Capital and Infrastructure reasons for
underspending
39Reasons for under-spending
- Education
- Late project starting times.
- Schools under trees 95 total cost R102, 3M
- 28 projects awarded and handover was delayed due
to the completion of Geo-Tech assessments. - 16 projects under construction
- Award of 15 projects was only finalised at the
end of July 2006.
40Reasons for under-spendingcontd
- Education
- Storm Damaged Schools 239 total cost R272M
- Adjudication of bids for 70 projects was only
finalised during the last week of June 2006. - Adjudication of bids for 67 projects was
finalised during the second week of July 2006. - Bids for 2 x 8 schools advertised on the 15 July
2006 and site hand over in August 2006. - Bids for 40 schools were advertised in the
bulletin of 30 June 2006. Sites were handed over
in August 2006.
41Reasons for under-spendingcontd
- Education
- New Schools 3 total cost R47M
- Contractors took sites in July 2006. surety
42Reasons for under-spendingcontd
- Roads Transport
- The department undertakes new capital projects
through the Roads Agency Limpopo (RAL), an agency
within the department. - Late in the 2005/06 financial year, the agency
was taken to court by bidders who challenged its
procurement policies and awards for certain
projects. This forced the agency to refine its
procurement policies and procedures and awards in
line with the court decision. - The projects that had been advertised in March
2006 were withdrawn/cancelled to enable the legal
department to incorporate the new guidelines into
the advertisements to avoid further legal
challenges. - The number of projects that had to be
re-advertised is 52 projects with a value of
R322, 5M.
43Reasons for under-spendingcontd
- Health Social Development
- Late appointment of contractors which led to
projects starting late. - Clinic Upgrade Programme 20 2006 - 2007
total cost R49, 6M - Bids for 10 clinic projects were advertised on 30
June 2006 and handed over in August 2006. - Bids for 6 projects were advertised on the 15
July 2006 and sites handed over in August 2006.
44Reasons for under-spending cont.
- Health Social Development
- Mortuaries
- Site handed over for Tshilidzini project on 3rd
July 2006 cost R7, 6M.
45Reasons for under-spending cont.
- Agriculture
- Revitalisation of Smallholder Irrigation Schemes
(RESIS) total cost R170M - R70 mil was budgeted for bulk infrastructure
services at various schemes. R100 mil was
budgeted for installation of infield
infrastructure. The plan envisaged the
appointment of Turnkey Service Providers by 1st
April 2006 to perform work on 57 schemes some of
whom were work carried over from 2005. - Due to the experience of 2005 where-in it was
found that Service Providers were using dubious
prices and unacceptable mark-ups, it was decided
to include the provision of pre-approved unit
prices by prospective bidders during the
tendering stage. It took a longer time for
bidders to comply with this requirement as it
negatively impacted on their profit margins.
46Reasons for under-spending cont.
- Agriculture
- Because of the new tender process as explained,
service providers were only officially appointed
at the end of June 2006. - Tenders for poultry houses were concluded and
cancelled due to inability of the service
provider to deliver. - Some delays are caused by the hesitation from
others to take-over work previously done by other
service providers whose contracts were terminated
by LDA in 2005. These service providers site such
issues as professional liabilities for integrity
of designs done by others, to lack of adequate
information from previous reports, e.g. land
surveys not being geo-referenced, etc
47Reasons for under-spending cont.
- Local Govt. Housing
- Review of all service providers contracts led to
delays in projects starting times
48Reasons for under-spending cont.
- Public Works
- R 1 million for land development has not been
spent. Tenders for the development of landscaping
projects closed on 10th July 2006 and they are at
adjudication stage. Expenditure is expected to
start in October 2006. - An amount of R3, 5 million for the refurbishment
of the Parliamentary village was not spent
because the projects are at tendering stage.
Expenditure is expected to start in October 2006. - Other projects linked to the construction of 11
MECs houses amounting to R2, 369 million, were
started in July 2006, and planning design of
the relocation of Legislature to Polokwane is
still continuing. - Construction of 11 MEC houses only started in May
2006 with the first claim for the project
submitted at the end of June 2006 for payment.