PRESENTATION TO NCOP BY THE MEC LIMPOPO PROVINCIAL TREASURY - PowerPoint PPT Presentation

About This Presentation
Title:

PRESENTATION TO NCOP BY THE MEC LIMPOPO PROVINCIAL TREASURY

Description:

The commitment is R10,117m which will increase expenditure to R16,554m at the ... is speeded up, the revised plans were forwarded to National Health in November 2005. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 39
Provided by: pmg8
Category:

less

Transcript and Presenter's Notes

Title: PRESENTATION TO NCOP BY THE MEC LIMPOPO PROVINCIAL TREASURY


1
PRESENTATION TO NCOPBY THE MEC LIMPOPO
PROVINCIAL TREASURY
__________________________________________________
__________
  • 16TH JANUARY 2006

2
(No Transcript)
3
EDUCATION
  • HIV/AIDS
  • The commitment is R10,117m which will increase
    expenditure to R16,554m at the end of the
    financial year.
  • Redesigning of the HIV/Aids Conditional Grant is
    being proposed in order to enhance impact.
  • Primary School Nutrition Programme
  • This grant feeds about 1 400 000 school children.
    The Department projects full utilisation of the
    grant by the end of the financial year.

4
Conditional Grants Actual expenditure as at 31
December 2005 of the financial year 2005 / 06
5
Conditional Grants Actual expenditure as at 31
December 2005
6
Conditional Grants
  • Expenditure 2005 / 06
  • The department has managed to increase the
    expenditure per quarter as follows
  • 6.27 R40.67m in the first quarter
  • 22.1 R 106.391m in the second quarter
  • 43.5 R 241 860 in the third quarter
  • The inability of the department to secure Tenders
    for the purchase of Medical Equipment has
    resulted in limited expenditure to date on the
    following grants
  • Hospital Management and Quality Improvement at
    37.26,
  • National Tertiary Services at 28.76
  • The tenders for Medical Equipment was finalised
    in November and expenditure is expected to
    substantially increase in the last quarter as the
    business plans include the assets required.
  • Equipment has been ordered and deliveries are
    awaited

7
Conditional Grants
  • Expenditure - HIV AIDS
  • The business plans for HIV AIDS was adjusted in
    an attempt to ensure that service delivery is
    speeded up, the revised plans were forwarded to
    National Health in November 2005.
  • Some R20 million was transferred to NGOs during
    October 2005, after proper screening the NGOs
    ability to deliver on the part of the
    Comprehensive HIVAIDS programme that they are
    expected to deliver service on.
  • Personnel Expenditure is not expected to increase
    as health professional posts catered for are not
    being filled as anticipated under spending of R
    11 m or 8.2 .
  • Expenditure increased from 7.7 in Sept. to 45.3
    in Dec 2005
  • The expenditure should be increased once a system
    to account for medicines and tests used on
    HIVAIDS related treatments in the hospitals is
    agreed upon.
  • Identifying the medicines used for the treatment
    of Aids Patients remains to be a challenge as all
    medicines are procured at a central point on the
    equitable share and have to be journalised to
    capture the expenditure under the Conditional
    Grant.

8
Conditional Grants
  • Expenditure and interventions - I N P
  • The participation on the National Tender RT 289
    has not been available to the department.
  • R 2 m for food supplements committed in November,
    purchased via quotations.
  • R 1.5 m for equipment already delivered, invoices
    awaited.
  • An additional R 2 m for equipment has been
    ordered.
  • Future participation on RT 289 is being
    negotiated to streamline procurement.
  • Vitamin A supplements (tablets) is being procured
    via the Pharmacy Depot to comply to contract
    requirements including the Bar Coding, to the
    value of R 700 000 to year end.

9
Conditional Grants
  • Expenditure and interventions - I N P cont.
  • The use of multi vitamins was also slowed down
    due to contract requirements, R 1.5 m yet to be
    procured.
  • Skills development for food service management
    personnel to take place in February 2006 for R 2
    m and the programme will continue into the next
    financial year.
  • Backlog of R 600 000 in Greenery projects in
    Bohlabela district due to un-availability of the
    system.
  • R 3 m yet to be spent by year end on all Greenery
    projects.
  • HPTD Grant
  • Expenditure on the HPTD Grant has been above the
    average and no problems is foreseen in spending
    the funds on service delivery in this regard, as
    equipment tenders are now in place.

10
Conditional Grants
  • Expenditure and interventions HMQI
  • The training of management is ongoing but
    availability of management for training over
    extended periods are restrictive.
  • Personnel costs are below norm due to vacant
    posts.
  • The purchase of equipment R 2.8 m has not taken
    place-
  • Computers
  • Filling systems - Delay in the implementation of
    the Information and Records Management tender
  • Lack of equipment tender for medical equipment
    that was only finalized in December

11
Conditional Grants
  • Expenditure - NTSG
  • Purchase of equipment has been delayed due to the
    unavailability of a tender that is now being
    finalised, has resulted in low expenditure
    patterns but an amount of R 32 m has since been
    committed.
  • It is envisaged that the full budget for
    Equipment of R 46 m will be utilised
  • Personnel costs for Specialists employed on the
    equitable share has been identified to be funded
    from this grant for the first three years of
    their employment and the Grant does carry these
    costs.
  • Expenditure - Cholera / Malaria
  • The full amount of R 2.718 m received as a roll
    over will be spent during the year on-
  • Pesticides for Malaria control
  • Vehicles for Vector control have been ordered
  • In response to the recent instances of reported
    Malaria cases R1.26m has been committed against
    the grant.

12
Conditional Grants
  • Expenditure Hospital Revitalisation
  • The department surrendered R10 m to National
    Health with a request to increase the allocation
    for the 2006/07 year with the same amount due to
    the projects being completed in the following
    financial year.
  • This grant is fully committed but expenditure is
    dependant on the progress made by contractors.
  • The capacity of emerging contractors together
    with the availability of building materials
    especially Building Bricks has been a constraint
    that impacts on the timeous completion of the
    current contracts
  • Upgrading of the filing system at Revitalised
    Hospitals to the value of R 4.6 m has been
    ordered.

13
Local Government
  • Housing Subsidy
  • Shortage of clay bricks in the province,
    difficulties experienced by contractors in
    raising funding for the acquisition of materials
    for construction and delays in implementing
    contracts by developers contributed to the low
    levels of spending on the Housing Subsidy.
  • Spending improved gradually and total spending is
    projected at R417.29 million which is 91.32.
  • 3 880 houses will be completed as at the 31 March
    2006.

14
Local Government (Cont)
  • Human Settlement and Redevelopment Programme
  • The overspending is as a result of the
    expenditure on projects whose budgets were rolled
    over from 2004/05 to 2005/06

15
Social Development
  • HIV/AIDS
  • The expenditure is high because the Department
    has already transferred funds to 64 NGOs for the
    smooth running of the programme. The transfers
    are in line with the Departments planning.
  • Social Assistance Admin Grant
  • The underspending is as a result of the delay in
    filling of posts identified as critical, and also
    on goods and services as a result of shared
    items, e.g. Stationery, telephone, water and
    electricity. South African Social Security Agency
    is currently housed within the Department of
    Health and Social Development.

16
Social Development
  • Social Assistance Transfers Grant
  • A growth of 2 is projected and the actual growth
    in our province is about 2.6.
  • Integrated Social Dev Grant
  • There is no actual expenditure to date due to the
    delay of business plan approval. The delay was
    caused by the change of the conditions of the
    grant by National Department and identification
    of the projects to be funded. The business plan
    has now been approved and the expenditure will
    start to reflect in the third quarter.

17
Sports, Arts and Culture
  • Mass Sport and Recreation Programme
  • The underspending on the grant is due to the fact
    that new hubs were supposed to have been launched
    during November, but was postponed to February
    2006. Grant will be fully utilised.

18
Agriculture
  • Comprehensive Agricultural Support Programme
    (CASP)
  • The underspending is due to limited capacity for
    infrastructure development and project
    registration in districts. There are numerous
    small projects that makes it difficult to manage.
  • Land Care Programme Grant
  • The underspending is due to the delay in supply
    of fencing materials by suppliers. Orders were
    issued but payments could not be processed due to
    non delivery.

19
Provincial Infrastructure Grant
20
PIG
21
Reasons for underspending (PIG)
  • Total Total spending on the grant is at 40.2 is
    projected to be at 98 by yearend.
  • Education
  • Spending on the grant is at 44 of the grant.
  • It is expected the department will end the year
    at 100 of its budget (including commitments at
    yearend).
  • The low expenditure to the end of September is
    due to projects starting late (the departmental
    business plan was changed due a review of
    priorities, i.e. focus areas).
  • Roads Transport
  • 41.2 has been spent so far. Most of the big
    contracts were awarded in September, spending is
    low as a result. (Spending has been picking up
    since September which stood at 14.8).
  • The department projects to spend all its budget.

22
Reasons cont
  • Health Social Development
  • 26.2 of the grant has been spent so far.
    Spending on projects is dependant on stages of
    completion of the projects and most of these
    started late. There were other project related
    problems such as
  • 1. The late Appointments of Main Sub
    Contractors.
  • 2. Project delays by the Implementing Agent, i.e.
    project implementation taking more time than it
    should.
  • 3. Poor performance by the main Contractors.
  • The department projects an underspending of 10
    of its budget (R9.0M).
  • Agriculture
  • The department has spent 40.2 of the grant and
    this is due to the review of the small-holder
    irrigation schemes that were targeted to benefit
    from the grant (during the review process, these
    projects were put on hold).
  • With regard to fencing projects, supplier
    capacity for the poles to be used for fencing was
    overstretched, with the major suppliers being
    affected, leading to further delays in project
    starting times.
  • The department will underspend its budget by 15
    (R5.9M).

23
Intervention strategies (PIG)
  • Health Social Dev.
  • The department has adopted a proactive approach
    in project management, e.g. the project
    documentation stages are started earlier in order
    to pre-empt delays in tendering, etc.
  • Most of the grant is used for clinic projects (33
    projects, most of these have just started and
    some will start in Feb ave. cost per clinic
    R3M).
  • The department is unlikely to spend its full PIG
    budget in this financial year and could end the
    year at around 90 of its budget.

24
Intervention strategies
  • Education
  • The department is identifying projects for
    fasttracking and this will boost expenditure
    (almost all the budget is already committed).
  • (NOTE There could be some amounts that are not
    PAID but committed by yearend).

25
Cont
  • Agriculture
  • The department is unlikely to spend its full PIG
    budget and will end the year at around 85 of the
    budget (underspending of R5.9M).
  • Roads Transport
  • Engineers from the Roads Agency are currently
    assessing the projects in the province and
    identifying fast-moving projects and reallocating
    funds to these in order to eliminate the risk of
    underspending.

26
Total Infrastructure Budget
27
Total Nov YTD Spending
28
Total Spendingcont
29
Total budget reasons for underspending
  • Total Total capital spending (incl. PIG) is at
    34.3 and is projected to be at 96 by yearend).
  • Roads Transport
  • Most of the big contracts were awarded in
    September.
  • Education
  • Projects started late due to a review in
    priorities (which impacted on the business plan,
    i.e. it was changed).

30
Agricreasons
  • Lack of skills to undertake technical
    infrastructure planning functions, e.g. the
    inability to compile the bills of quantities
    required for the projects.
  • Progress on projects has been delayed by the
    demand planning processes whereby a certain level
    of technical expertise, e.g. engineering is
    inadequate to expedite most projects.
  • With regard to fencing projects, supplier
    capacity for the poles to be used for fencing was
    overstretched, with the major suppliers being
    affected, leading to further delays in project
    starting times.

31
Agric..reasons
  • The decentralization process of both the planning
    and financial processes of several programs to
    the Districts affected CASP as District Senior
    Managers had to take full charge of the several
    programs with inadequate capacity.
  • Most districts did not develop detailed project
    implementation plans on time and as such this led
    to a slow start for some of the projects.

32
Agricreasons
  • In order to boost project performance and
    delivery, the department has
  • Developed a Project Database which will improve
    the monitoring of the projects.
  • Initiated the buying of materials for fencing in
    bulk.

33
Health Soc. Dev
  • Reasons that contributed to delays are the
    following
  • For 15 of the main contracts, contractors went on
    site from the 15th of July, which negatively
    affected spending.
  • Delays on supply of medical equipment for the
    hospital projects, orders were issued in April
    2005 but to due to delays in delivery, no
    payments were made for these projects in the 1st
    Quarter of 2005/06.
  • Spending on clinics (both new construction and
    upgrades), health centres and mortuaries was also
    hampered by delays in the documentation phase of
    project implementation (e.g. tender evaluations,
    etc in line with the Construction Industry
    Development Board (CIDB) guidelines which require
    contractors to be registered and categorised per
    amount of project that they can undertake).

34
Health
  • The department is also taking proactive measures
    to ensure that delays are minimized, e.g. by
    appointing contractors early and having them take
    site before the scheduled departmental project
    starting time.

35
Health Soc. Dev
  • Reasons that contributed to delays are the
    following
  • For 15 of the main contracts, contractors went on
    site from the 15th of July, which negatively
    affected spending.
  • Delays on supply of medical equipment for the
    hospital projects, orders were issued in April
    2005 but to due to delays in delivery, no
    payments were made for these projects in the 1st
    Quarter of 2005/06.
  • Spending on clinics (both new construction and
    upgrades), health centres and mortuaries was also
    hampered by delays in the documentation phase of
    project implementation (e.g. tender evaluations,
    etc in line with the Construction Industry
    Development Board (CIDB) guidelines which require
    contractors to be registered and categorised per
    amount of project that they can undertake).

36
Health
  • The department is also taking proactive measures
    to ensure that delays are minimized, e.g. by
    appointing contractors early and having them take
    site before the scheduled departmental project
    starting time.

37
Possible risks of underspending
  • Education
  • Projects will be fasttracked to avert
    underspending. By yearend all the money will be
    committed.
  • Agriculture
  • This sector will underspend its budget by 15
    (R35.6M).
  • Health Social Development
  • This sector will spend about 90 of its budget
    (underspending of R42.5M)
  • There are 33 clinic project at a cost of R3M each
    which have just started. Some of the projects
    will start in Feb which will impact on spending.
  • Roads Transport
  • The full budget will be spent.
  • About R179M was spent in Dec.
  • With the balance spent as follows about R100M in
    Jan, about R100M in Feb and the balance, about
    R250M in March.
  • Rain could derail projects in other areas but the
    department is proactively moving funds to
    projects that are not affected by rain.

38
The End