1
Technical report for ISOLDE
  • Mats Lindroos on behalf of the ISOLDE team

2
Outline
  • Separator status
  • REX
  • Developments and integration status
  • ISOLDE organization
  • Responsibilities
  • New staff
  • Beam preparation activities
  • EURISOL/EURONS news
  • Recent technical development work
  • ECR
  • Shutdown planning

3
GPS and HRS
  • GPS operation limited to 30 kV since July
  • Suspect problem with insulator
  • Peek material better vacuum properties but
    worse resistance to sparking
  • Operation with a single vacuum pump since late
    July
  • To be replaced in March 2005
  • Repair?
  • HRS running well
  • One vacuum pump replaced in October after failure
    of both pumps (staggered in time)
  • Resolution of HRS limited by design fault
  • Decision of the future of HRS in the upgrade
    group
  • Second GPS or Real HRS

4
Front-end 6
  • Front-end 6 assembled
  • Waiting for ceramic insulator
  • To be tested in building 275 before installation
    in March

5
REX integration
  • All (5) REX posts filled and successful shutdown
    and maintenance executed in 2004
  • Staff situation critical for peek need during
    runs
  • Need for scheduled Machine Development (MD) time
    for difficult beams
  • Technical support for low energy stage too low
  • Operation team, supervisor team, must be formed
    for on-call support and setting-up

6
ISOLDE organization
AB
PH
ADM
ATB
BDI
BT
CO
OP
PO
RF
ABP
IS
  • Technical coordination
  • EURISOL coordination
  • Target and ion source production
  • Front-ends and robots
  • ISOLDE experimental area
  • Target RD
  • REX integration
  • RILIS
  • Operation
  • ISOLDE optics (electrostatic)
  • TSO
  • Alignment
  • General technical support
  • Application programs
  • Scientific programme
  • Scientific coordination
  • Liaison with collaboration
  • Liaison Users
  • EURONS
  • Future scientific strategy
  • TARGISOL

New staff at ISOLDE tech. late 2004 Magnus
Eriksson (OP), Nikolai Trofimov (CO) and Pascal
Fernier (OP, 50)
7
ISOLDE responsibilities
  • ISOLDE PH
  • ISOLDE Physics group leader
  • Leads the scientific programme at ISOLDE
  • Chairs the ISOLDE upgrade group
  • CERN representative in the ISOLDE collaboration
    committee
  • Responsible for the ISOLDE collaboration budget
  • Responsible for external scientific collaboration
    at ISOLDE
  • Leads the technical development for isotope
    manipulation within EURONS and EURISOL at ISOLDE
  • CERN responsible for EURONS
  • ISOLDE Physics coordinator
  • Responsible for the ISOLDE schedule
  • Responsible for ISOLDE User liaison
  • Responsible for liaison with AB
  • Scientific secretary for INTC
  • ISOLDE AB
  • ISOLDE technical coordinator (ATB)
  • Coordinates ISOLDE operation, maintenance and
    technical RD
  • Chairs the weekly coordination meeting
  • Responsible for REX integration

8
ISOLDE operation
  • ISOLDE OP team
  • 1 Physicist
  • 2 technicians
  • 50 of a technician
  • Plan for 2005 run
  • Operation with 5 person piquet team
  • Technician available in the ISOLDE control room
    for 4 hours each working day
  • 2 Technicians replace all additional support
    earlier given by 2 technicians and 1 engineer

9
EURISOL and EURONS
EURONS I3 1.5 MCHF Transnational Access 0.6
MCHF Joint Research Activities new staff mostly
in PH (DAQ, admin and RD) EURISOL DS 2.8
MCHF (CERN leads 3 tasks) new staff mostly in
AB (RD) EURONS EURISOL enable RD in
targets b-beam (AB) radioisotope
manipulation (PH) safety (SC)
10
ISOLDE control system
  • All applications except scanners and wire grids
    available in LINUX
  • Problems
  • Slow start-up
  • Slow response
  • Change of log book page each day
  • Report bugs to Tim Giles
  • Shutdown work
  • Address response problems
  • New applications for instrumentation and yield
    measurements

11
REX LE Developments in 2004
Element Charge A/q Breeding time (ms) Comments
9,11Li 2, 3 4.5, 3.0 5-8 Without/with stripper foil Ne and Ar buffer gases
24-29Na 7,8 3.43 4.14 15
28,30,31,32Mg 9,7,8,9 3.11-4.29 14-18
88Kr 21 4.19 38
74,76,78Zn 20,20,21 3.62 3.71 38 (2003)78 (2004)
122,124,126Cd 30,30,31 4.06 4.13 148
156Eu 30 5.2 38 Only RFQ 300 keV/u
153Sm 27,28 5.46-5.67 30 Only RFQ 300 keV/u
70Se 17 4.12 33 Molecular sideband
17F 5 3.4 8 With stripper foil
110Sn 27 4.07 98
148Pm 30 4.93 38? Only RFQ 300 keV/u
  • New isotopes
  • Molecular beams
  • Rotating wall cooling
  • No clear advantage compared to side band cooling
  • New control system from GSI for trap
  • Many thanks to GSI!
  • Record charge breeding efficiency (Trap out to
    EBIS out)
  • 23 for 39K10

Radioactive 110Sn into REXTRAP 110 pA after
REXTRAP 48 pA after mass sep. 115 pA in 27 98 ms
breeding time trap eff 44, EBIS eff 9
12
REX linac developments in 2004
13
Target and ion source development
  • The very active target R D program in close
    collaboration with experiments has always been
    the secret of the success of the ISOLDE physics
    programme
  • The tradition will continue, examples from 2004
  • ISOLDE RILIS used for gt50 of all shifts, RD!
  • Tests with solid state lasers off-line (Mainz
    univ.)
  • Negative ion source (ISOLDE and KENIS, ORNL)
  • Measurement of transverse shockwaves with tests
    with laser vibrometer
  • New target materials
  • LaCx synthesized
  • SiCx from TRIUMF tested
  • Note 3 FTE per new element/isotope!
  • User support essential to advance many
    developments
  • Strongly integrated with ISOLDE EU activities

14
Beam preparation at ISOLDE
  • Successful charge breeding with an ECR Phoenix
    source at ISOLDE of radioactive ions
  • Major problem with background to be addressed in
    6th framework programme
  • The beam preparation activities move to the PH
    ISOLDE physics group in 2005
  • RFQ cooler activity continues in AB-ATB to
    complete started project
  • EURON fellowship and EURISOL beam preparation
    post to work on these activities

Successful charge breeding of 94Rb14,
96Sr13,14,15, (130Inx and 130Csx) 46,47,48Ar,
92xxKr and 138,142,144Xe Efficiency
estimates 96Sr15 2.6-3.7 efficiency 96Sr14
2.9-4.2 efficiency 96Sr13 2.2-3.0
efficiency IS 400, Beam purification of noble gas
beams
15
Shutdown
  • Shutdown planning established
  • Key dates
  • End of run 11/11/2004 am
  • Shutdown courses 29/11-10/12
  • Stable beam stop 10/12
  • No cooling water (possible power cuts)
    10/12-18/1
  • Start of off-line running 21/3
  • Start-up of physics programme 25/4
  • Key tasks
  • Installation of new front-end
  • Repair of REX EBIS magnet
  • Wall removed between extension and hall
  • Dust barrier being installed
  • Schedules at ISOLDE web site and at REX web site
  • CERN schedule holds several key dates even for
    ISOLDE!
Write a Comment