Title: Practically Enforceable Permit Conditions


1
Practically Enforceable Permit Conditions
  • Ray Vogel
  • U.S. EPA/OAQPS

2
Practical Enforceability
  • Purpose is to make sure permit limits are
  • Clear as to who limit applies to
  • Clear as to when compliance is required
  • Short-term, so that compliance can be determined
    relatively quickly
  • Clear as to what standard a source must meet
  • Clear as to how compliance is to be determined

3
Practical EnforceabilityExample 1
  • The operator shall maintain adequate records, as
    determined by the Director.
  • Not practically enforceable
  • No standard on adequate?
  • Director, not EPA or citizens, has sole
    discretion to determine if records are adequate

4
Practical Enforceability Example 2
  • The operator shall take corrective action if
    parameters are significantly out of range.
  • Problem vague and subjective
  • How is significantly out of range determined?
    By whom?
  • What kind of corrective action?

5
Limits on Potential to Emit (PTE)
  • PTE limits must be practically enforceable
  • Short-term (monthly or rolled monthly)
  • Limit operation or production, if source has
    capacity to emit at major source levels
  • Recordkeeping to verify compliance

6
Unenforceable PTE Limits Example 1
  • Plant capable of emitting 300 tpy of CO has only
    a 249 tpy emission limitation
  • Problems annual limit, no limit on operation or
    production, no recordkeeping
  • Step 1 Impose a monthly limit on hours of
    operation or production which, when multiplied by
    CO emission rate, 249 tpy
  • Step 2 Require recordkeeping to verify
    compliance with operation/production limit

7
Unenforceable PTE Limits Example 2
  • Plant with rock crusher, permit limits 0.05 gr
    PM/dscf fabric filter must be used and operated
    at 99 efficiency
  • Problem does not specify means of determining
    efficiency
  • Correction periodic testing and monitoring of
    fabric filter to ensure 99 efficiency is achieved