Eskom - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Eskom

Description:

Title: Cogeneration Framework Subject: AMEU Author: Rob Higgo Last modified by: Ris Sign in Created Date: 8/23/2005 6:46:50 AM Document presentation format – PowerPoint PPT presentation

Number of Views:127
Avg rating:3.0/5.0
Slides: 22
Provided by: RobH199
Category:

less

Transcript and Presenter's Notes

Title: Eskom


1
Eskoms Pilot National Cogeneration Project
60th AMEU Convention
  • Rob Higgo, Project Development Department
  • Stuart van Zyl, Industry Association Resource
    Centre
  • 16 October 2007

2
Contents
  • Background
  • Strategic issues
  • The need for a pilot project
  • Objectives Principles of the pilot project
  • Eskoms Pilot Project
  • What is Eskom Offering
  • Consideration of Connection Billing Issues
  • Network considerations

3
What is Co-generation?
  • Co-generation a source of electrical power that
    is a co-product, by-product, waste product or
    residual product of an underlying industrial
    process.
  • Type I projects utilizing process energy which
    would otherwise be underutilized or wasted (e.g.
    waste heat recovery).
  • Type II Primary fuel based generation projects
    which produce other usable energy in addition to
    electricity (e.g. Combined Heat and Power
    projects).
  • Type III Renewable fuel based projects where
    the renewable fuel source is a co-product of an
    industrial process (e.g. use of bagasse and/or
    forestry waste from the sugar and paper
    industries).

4
The Eskom challenge
  • During June 2006, Eskoms Exco challenged the
    organisation to develop new cogeneration
    opportunities in South Africa
  • A target of 900MW1 was established, to be
    achieved within a 5 year window, ending March
    2011
  • In so doing, Eskom would
  • Support NERSAs initiative to established a
    cogeneration framework (guidelines) that will
    promote new cogeneration
  • Pursue and actively procure cogeneration
    opportunities that make good business sense
  • An Eskom cogeneration workgroup was established
    internally to support the initiative
  • Eskom has worked jointly with the EIUG workgroup,
    NERSA and others in industry to meet its
    objectives

1) The target is not definitive, and actual
cogeneration developed will be dependent on
market response
5
Strategic Considerations
  • Cogeneration has potential to deliver capacity
    quickly
  • Cogeneration may provide electricity at lower
    cost than conventional generation (not all
    Cogeneration is cheaper)
  • Cogeneration potentially reduces investment in
    networks and supports distributed generation
  • Transmission cost savings
  • Cogeneration may improve industrial efficiency
    and can be environmentally friendly e.g.
    Combined Heat and Power (CHP)
  • Deferred investment at (possible) lower cost
  • Overall efficiency gains
  • Environmental benefits
  • Improved reliability and quality of supply
  • Employment / BEE opportunities

Eskoms strategic considerations closely mirror
those of the EIUG and Industry
6
The need for an Eskom pilot project
  • NERSAs guidelines, regulations and
    implementation programme may take some time to
    conclude
  • Window of opportunity exists between now and
    approximately 2012
  • Eskoms first new base load power plants due to
    come on line during 2012 to 2013
  • The initial pilot will allow both Eskom and
    NERSA an opportunity to gauge the cogeneration
    market in SA
  • Quantity and size of the market offering
  • Cogeneration mix, location, profile
  • Pricing of cogeneration options being proposed
  • Timing of potential cogeneration projects
  • Results from the pilot project will feed into
    the current NERSA guidelines and thinking
  • Lessons learned will be carried forward into the
    long term model for SA

7
Objectives Key principles
  • Develop the necessary tender documentation to
    attract new cogeneration
  • Obtain NERSA support and approval for the process
  • Develop a standard contract for cogeneration
    developers which is bankable (PPA)
  • Have a transparent evaluation process to evaluate
    tender submissions
  • Implement the process in a timely fashion
  • Develop a ceiling price which will be approved by
    NERSA beyond which contracts will not be offered

8
Objectives Key principles
  • Transparency
  • Well defined and clearly understood process
  • Known implementation parameters
  • Equitable treatment across projects
  • Determination of qualifying projects
  • Simplicity
  • Procedural simplicity for projects to achieve
    regulatory approval
  • Minimisation of transaction negotiations
  • Minimisation of transaction costs

9
What is Eskom offering?
  • An opportunity to attract and contract new
    cogeneration into the market
  • Requirements
  • new build or re-commissioned plant of nett
    capacity gt1MW.
  • Must be co-generation not renewable generation
    that requires renewable energy grants (i.e. must
    be cost effective as a stand alone co-generator)
  • Cheapest bids from technically and commercially
    qualified bids win contract provided that they do
    not exceed the ceiling price set by Eskoms
    avoided cost model
  • there are modifiers for siteing and timing (first
    on line) advantages
  • Maximum 15 year contracts are offered
  • A standard contract (PPA) was developed for the
    Cogeneration projects which include inter alia
  • Payment profiles aligned with energy needs
    support TOU / peaking periods Winter vs. Summer
    etc.

10
Progress to date
  • Pilot project is essentially a tender process.

11
Progress to date
  • Summary of EOIs received Co-generator Types

Waste Energy
Renewable Energy
Generation with 2ndary Process Energy
12
Progress to date
  • Summary of EOIs received Generator net output

13
Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
14
Contractual vs Physical Flow
Physical flow
Eskom Generation
Contractual flow
Eskom Wholesaler purchases Eskom energy generated
at existing Eskom generation tariff
Eskom Wholesaler
Eskom Tx Network
ESAa (Meter 1 2)
Eskom Wholesaler purchases gross energy
generated at Meter 2 at cogen PPA tariff
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
15
Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
Eskom Wholesaler bills for energy summating
Meters 1 and 2 at standard power sales tariff
within identified and ring fenced area
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
16
Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
Retailer similarly bills for energy summating
Meters 1 and 2 at standard power sales tariff
within identified and ring fenced area
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
17
Connection Billing Arrangements
  • The export of energy may be physical or only a
    commercial arrangement (own use but paid for by
    Eskom)
  • The commercial arrangement (PPA) will not impact
    the distributors revenue (no netting off of
    usage)
  • PPA will be with co-generator and ring-fenced
    contractually from the usage by the end user
    (load)
  • Standard tariff paid by end user (load) for
    energy purchased by consumer is that metered by
    the distributor plus energy generated by
    co-generator and sold to Eskom via the PPA
  • No impact on sales and revenue
  • Distributor to take into account technical
    factors arising from generator connection
  • The associated costs payable by the generator
  • Physical export will increase technical
    complexity and impact connection costs

18
Technical Considerations
  • Penetration levels of Embedded Generation are
    low Experienced SA engineers are few.
  • Consultant(s) to be appointed to assist in
    evaluating technical impact and provide designs
    where required
  • Includes skills transfer on network studies
  • Embedded Generator connection policy is handled
    in the Grid and Distribution codes
  • Distribution Code approved by NERSA October 2007
  • Principle of open access to Embedded Generators
  • Each Distributor to develop interconnection
    standards
  • Detailed technical guidelines lacking
  • Eskom interconnection standard
  • Planning guideline

19
Technical factors to be considered
  • Fault level contribution
  • Detection of Loss-of-Grid
  • Difficult to detect in some instances
  • Guidelines given on when dedicated protection is
    required
  • Network earthing and earth fault protection
  • MV networks are resistively earthed at the
    source. Generator neutral to be left unearthed
  • Protection and protection settings
  • Related to generator operating philosophy
  • Isolation of system for safe working
  • Metering
  • Installation near generator terminals

20
Conclusion
  • Eskoms Pilot National Co-generation project
    seeks to connect 900MW of new-build generation by
    2011.
  • Effectively a tender process
  • Expression of interest netted 124 submissions,
    5000MW.
  • Power Purchase Agreements (PPAs) and Technical
    Standards presently under development.
  • Distribution Code is a second driver for
    interconnection standards
  • Earthing, loss-of-grid protection some of the key
    technical aspects

21
ESKOMHoldings Ltd
  • Thank You

22
Connection Billing Arrangements
  • The co-generator is required to sign a connection
    and use-of-system agreement with the distributor.
  • Eskom is currently developing a pro-forma
    contract for generators connected to Eskoms
    Distribution network
  • Sets out the financial, technical and legal
    conditions
  • Challenges
  • No national policy on use of system charges for
    distributed generators
  • Eskom formulating a stance (still in development
    phase)
  • Technical criteria being developed
  • Task team looking at Eskom connection standard
    for Embedded Generators (as required by
    Distribution Code)
  • Need to develop skills regarding connection
    quotations
  • Proposed to include munic reps in a broader
    stakeholder workshop to discuss the technical
    connection criteria (once we have internally
    reviewed/work shopped). This would also include
    the co-generators

23
Industry PerspectivePower Generation in South
Africa
  • GDP growth of 6 per annum projects electricity
    growth of 4 per annum
  • Generation capacity will need to be expanded
    annually 1200MW
  • Cost of new generation capacity high a large
    percentage of the world is currently expanding
    its generation base Sellers market
  • 2005 power generation by Eskom Munics 92 coal
    and 6 nuclear
  • Short term base load generation capacity
    expansion Coal fired
  • Cogeneration in SA approximately 3
  • Waste gasses and waste heat potential in large
    industry is potentially 2.2 of national demand
    (could be achieved by 2010) increasing to 6 by
    2016 / 2018
  • No current national policy exists to introduce
    cogeneration into the South African energy /
    generation mix
  • Current decision making on cogeneration projects
    takes far too long, frustrating industry

Extracts taken from an EIUG presentation dated
January 2007
24
Industry PerspectiveEnergy Management in South
Africa
  • Compared to Europe relatively inefficient
  • Government policy frameworks include
  • The energy efficiency policy of South Africa
  • The White Paper on Renewable Energy
  • The Energy Efficiency Accord (EEA)
  • Targets established for energy improvements
    include
  • 15 improvement in energy efficiency by industry
    by 2015
  • 10,000 GWh (4) of projected demand to be from
    renewable energy sources 2013
  • Several EIUG members have endorsed the EEA in
    support of energy efficiency improvements
  • Efficiency improvements promote and ensure
    sustainable development
  • Department of Minerals and Energy (DME) have
    committed to supporting and providing incentives,
    enabling industrys response to meeting
    established targets

Extracts taken from an EIUG presentation dated
January 2007
25
Industry PerspectiveEnvironmental benefits
  • Cogeneration has in most cases, a direct and
    immediate beneficial impact on the environment at
    large
  • South Africa is amongst the worlds highest per
    capita CO2 emitters due to its large installed
    coal generation base
  • Development of CDM projects in South Africa have
    proven difficult to justify, primarily due to the
    relatively low avoided costs of electricity
    purchases
  • European Union (EU) targets established for
    emission reductions will in time, impact on the
    South African economy

Extracts taken from an EIUG presentation dated
January 2007
26
Industry PerspectiveCogeneration can make a
difference
  • Energy to be used for cogeneration is already in
    the system Overall emissions would therefore be
    reduced by harnessing this energy, as well as an
    improvement in energy efficiency
  • Cost of cogeneration (electricity) will be less
    than costs of alternative new base load power
    plants
  • Lead time for cogeneration plants estimated to be
    24 to 30 months from order substantially
    quicker than alternative base load power plants
  • Unit sizes significantly smaller than existing
    Eskom power plants, reducing risk associated with
    unplanned outages
  • Cogeneration units are directly linked to an
    industrial process, so in most cases, reduction
    in net electricity demand is associated with
    generator outages
  • Transmission system losses may be reduced due to
    distributed generation advantages, with
    associated capacity being freed up on the system
  • Cogeneration projects create employment
    opportunities

Extracts taken from an EIUG presentation dated
January 2007
27
Industry PerspectiveLarge industry participation
  • Power generation is not core business!
  • Large industry is required to produce acceptable
    investment returns for its shareholders
    Cogeneration projects will therefore compete for
    Capital Expenditure
  • Large industry is however committed to energy
    efficiency projects in support of government and
    associated initiatives
  • Eskoms current average cost of electricity
    generation does not make cogeneration projects
    financially viable A mechanism will need to be
    introduced to close the gap between cogeneration
    and existing power generation in South Africa
  • Many EIUG industry players are able to convert
    waste energy into cogeneration (electricity) at a
    lower cost than new generation capacity in South
    Africa

Extracts taken from an EIUG presentation dated
January 2007
28
Industry PerspectiveEnabling drivers
  • Fast and efficient implementation of the long
    term cogeneration framework developed by NERSA in
    conjunction with Fieldstone, Eskom and industry
  • An avoided cost model, based on the cost of new
    base load power plant should be adopted in
    determining the ceiling price of competitive
    cogeneration projects, as adjusted and determined
    by NERSA
  • Industry should be given an opportunity to bid
    for cogeneration against the avoided cost (as
    above), and where cheaper, be contracted to
    supply cogeneration (electricity) to the market
  • Promulgation and implementation of the NERSA
    guidelines allowing industry to develop, bid for,
    and develop cogeneration projects, to be
    contracted with Eskom
  • In many cases, industry have completed
    feasibility studies for cogeneration projects,
    and are ready to respond

Extracts taken from an EIUG presentation dated
January 2007
Write a Comment
User Comments (0)
About PowerShow.com