Title: Eskom
1Eskoms Pilot National Cogeneration Project
60th AMEU Convention
- Rob Higgo, Project Development Department
- Stuart van Zyl, Industry Association Resource
Centre - 16 October 2007
2Contents
- Background
- Strategic issues
- The need for a pilot project
- Objectives Principles of the pilot project
- Eskoms Pilot Project
- What is Eskom Offering
- Consideration of Connection Billing Issues
- Network considerations
3What is Co-generation?
- Co-generation a source of electrical power that
is a co-product, by-product, waste product or
residual product of an underlying industrial
process. - Type I projects utilizing process energy which
would otherwise be underutilized or wasted (e.g.
waste heat recovery). - Type II Primary fuel based generation projects
which produce other usable energy in addition to
electricity (e.g. Combined Heat and Power
projects). - Type III Renewable fuel based projects where
the renewable fuel source is a co-product of an
industrial process (e.g. use of bagasse and/or
forestry waste from the sugar and paper
industries).
4The Eskom challenge
- During June 2006, Eskoms Exco challenged the
organisation to develop new cogeneration
opportunities in South Africa - A target of 900MW1 was established, to be
achieved within a 5 year window, ending March
2011 - In so doing, Eskom would
- Support NERSAs initiative to established a
cogeneration framework (guidelines) that will
promote new cogeneration - Pursue and actively procure cogeneration
opportunities that make good business sense - An Eskom cogeneration workgroup was established
internally to support the initiative - Eskom has worked jointly with the EIUG workgroup,
NERSA and others in industry to meet its
objectives
1) The target is not definitive, and actual
cogeneration developed will be dependent on
market response
5Strategic Considerations
- Cogeneration has potential to deliver capacity
quickly - Cogeneration may provide electricity at lower
cost than conventional generation (not all
Cogeneration is cheaper) - Cogeneration potentially reduces investment in
networks and supports distributed generation - Transmission cost savings
- Cogeneration may improve industrial efficiency
and can be environmentally friendly e.g.
Combined Heat and Power (CHP) - Deferred investment at (possible) lower cost
- Overall efficiency gains
- Environmental benefits
- Improved reliability and quality of supply
- Employment / BEE opportunities
Eskoms strategic considerations closely mirror
those of the EIUG and Industry
6The need for an Eskom pilot project
- NERSAs guidelines, regulations and
implementation programme may take some time to
conclude - Window of opportunity exists between now and
approximately 2012 - Eskoms first new base load power plants due to
come on line during 2012 to 2013 - The initial pilot will allow both Eskom and
NERSA an opportunity to gauge the cogeneration
market in SA - Quantity and size of the market offering
- Cogeneration mix, location, profile
- Pricing of cogeneration options being proposed
- Timing of potential cogeneration projects
- Results from the pilot project will feed into
the current NERSA guidelines and thinking - Lessons learned will be carried forward into the
long term model for SA
7Objectives Key principles
- Develop the necessary tender documentation to
attract new cogeneration - Obtain NERSA support and approval for the process
- Develop a standard contract for cogeneration
developers which is bankable (PPA) - Have a transparent evaluation process to evaluate
tender submissions - Implement the process in a timely fashion
- Develop a ceiling price which will be approved by
NERSA beyond which contracts will not be offered
8Objectives Key principles
- Transparency
- Well defined and clearly understood process
- Known implementation parameters
- Equitable treatment across projects
- Determination of qualifying projects
- Simplicity
- Procedural simplicity for projects to achieve
regulatory approval - Minimisation of transaction negotiations
- Minimisation of transaction costs
9What is Eskom offering?
- An opportunity to attract and contract new
cogeneration into the market - Requirements
- new build or re-commissioned plant of nett
capacity gt1MW. - Must be co-generation not renewable generation
that requires renewable energy grants (i.e. must
be cost effective as a stand alone co-generator) - Cheapest bids from technically and commercially
qualified bids win contract provided that they do
not exceed the ceiling price set by Eskoms
avoided cost model - there are modifiers for siteing and timing (first
on line) advantages - Maximum 15 year contracts are offered
- A standard contract (PPA) was developed for the
Cogeneration projects which include inter alia - Payment profiles aligned with energy needs
support TOU / peaking periods Winter vs. Summer
etc.
10Progress to date
- Pilot project is essentially a tender process.
11Progress to date
- Summary of EOIs received Co-generator Types
Waste Energy
Renewable Energy
Generation with 2ndary Process Energy
12Progress to date
- Summary of EOIs received Generator net output
13Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
14Contractual vs Physical Flow
Physical flow
Eskom Generation
Contractual flow
Eskom Wholesaler purchases Eskom energy generated
at existing Eskom generation tariff
Eskom Wholesaler
Eskom Tx Network
ESAa (Meter 1 2)
Eskom Wholesaler purchases gross energy
generated at Meter 2 at cogen PPA tariff
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
15Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
Eskom Wholesaler bills for energy summating
Meters 1 and 2 at standard power sales tariff
within identified and ring fenced area
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
16Contractual vs Physical Flow
Eskom Generation
Physical flow
Contractual flow
Eskom Wholesaler
Eskom Tx Network
Retailer similarly bills for energy summating
Meters 1 and 2 at standard power sales tariff
within identified and ring fenced area
ESAa (Meter 1 2)
Retailer (Eskom Dx / Munic / RED)
Dx Network (Eskom Dx / Munic / RED)
PPA (Meter 2)
ESAb (Meter 1 2)
Meter 1
Meter 2
Industrial Load
Cogeneration
Within embedded generation networks
17Connection Billing Arrangements
- The export of energy may be physical or only a
commercial arrangement (own use but paid for by
Eskom) - The commercial arrangement (PPA) will not impact
the distributors revenue (no netting off of
usage) - PPA will be with co-generator and ring-fenced
contractually from the usage by the end user
(load) - Standard tariff paid by end user (load) for
energy purchased by consumer is that metered by
the distributor plus energy generated by
co-generator and sold to Eskom via the PPA - No impact on sales and revenue
- Distributor to take into account technical
factors arising from generator connection - The associated costs payable by the generator
- Physical export will increase technical
complexity and impact connection costs
18Technical Considerations
- Penetration levels of Embedded Generation are
low Experienced SA engineers are few. - Consultant(s) to be appointed to assist in
evaluating technical impact and provide designs
where required - Includes skills transfer on network studies
- Embedded Generator connection policy is handled
in the Grid and Distribution codes - Distribution Code approved by NERSA October 2007
- Principle of open access to Embedded Generators
- Each Distributor to develop interconnection
standards - Detailed technical guidelines lacking
- Eskom interconnection standard
- Planning guideline
19Technical factors to be considered
- Fault level contribution
- Detection of Loss-of-Grid
- Difficult to detect in some instances
- Guidelines given on when dedicated protection is
required - Network earthing and earth fault protection
- MV networks are resistively earthed at the
source. Generator neutral to be left unearthed - Protection and protection settings
- Related to generator operating philosophy
- Isolation of system for safe working
- Metering
- Installation near generator terminals
20Conclusion
- Eskoms Pilot National Co-generation project
seeks to connect 900MW of new-build generation by
2011. - Effectively a tender process
- Expression of interest netted 124 submissions,
5000MW. - Power Purchase Agreements (PPAs) and Technical
Standards presently under development. - Distribution Code is a second driver for
interconnection standards - Earthing, loss-of-grid protection some of the key
technical aspects
21ESKOMHoldings Ltd
22Connection Billing Arrangements
- The co-generator is required to sign a connection
and use-of-system agreement with the distributor. - Eskom is currently developing a pro-forma
contract for generators connected to Eskoms
Distribution network - Sets out the financial, technical and legal
conditions - Challenges
- No national policy on use of system charges for
distributed generators - Eskom formulating a stance (still in development
phase) - Technical criteria being developed
- Task team looking at Eskom connection standard
for Embedded Generators (as required by
Distribution Code) - Need to develop skills regarding connection
quotations - Proposed to include munic reps in a broader
stakeholder workshop to discuss the technical
connection criteria (once we have internally
reviewed/work shopped). This would also include
the co-generators
23Industry PerspectivePower Generation in South
Africa
- GDP growth of 6 per annum projects electricity
growth of 4 per annum - Generation capacity will need to be expanded
annually 1200MW - Cost of new generation capacity high a large
percentage of the world is currently expanding
its generation base Sellers market - 2005 power generation by Eskom Munics 92 coal
and 6 nuclear - Short term base load generation capacity
expansion Coal fired - Cogeneration in SA approximately 3
- Waste gasses and waste heat potential in large
industry is potentially 2.2 of national demand
(could be achieved by 2010) increasing to 6 by
2016 / 2018 - No current national policy exists to introduce
cogeneration into the South African energy /
generation mix - Current decision making on cogeneration projects
takes far too long, frustrating industry
Extracts taken from an EIUG presentation dated
January 2007
24Industry PerspectiveEnergy Management in South
Africa
- Compared to Europe relatively inefficient
- Government policy frameworks include
- The energy efficiency policy of South Africa
- The White Paper on Renewable Energy
- The Energy Efficiency Accord (EEA)
- Targets established for energy improvements
include - 15 improvement in energy efficiency by industry
by 2015 - 10,000 GWh (4) of projected demand to be from
renewable energy sources 2013 - Several EIUG members have endorsed the EEA in
support of energy efficiency improvements - Efficiency improvements promote and ensure
sustainable development - Department of Minerals and Energy (DME) have
committed to supporting and providing incentives,
enabling industrys response to meeting
established targets
Extracts taken from an EIUG presentation dated
January 2007
25Industry PerspectiveEnvironmental benefits
- Cogeneration has in most cases, a direct and
immediate beneficial impact on the environment at
large - South Africa is amongst the worlds highest per
capita CO2 emitters due to its large installed
coal generation base - Development of CDM projects in South Africa have
proven difficult to justify, primarily due to the
relatively low avoided costs of electricity
purchases - European Union (EU) targets established for
emission reductions will in time, impact on the
South African economy
Extracts taken from an EIUG presentation dated
January 2007
26Industry PerspectiveCogeneration can make a
difference
- Energy to be used for cogeneration is already in
the system Overall emissions would therefore be
reduced by harnessing this energy, as well as an
improvement in energy efficiency - Cost of cogeneration (electricity) will be less
than costs of alternative new base load power
plants - Lead time for cogeneration plants estimated to be
24 to 30 months from order substantially
quicker than alternative base load power plants - Unit sizes significantly smaller than existing
Eskom power plants, reducing risk associated with
unplanned outages - Cogeneration units are directly linked to an
industrial process, so in most cases, reduction
in net electricity demand is associated with
generator outages - Transmission system losses may be reduced due to
distributed generation advantages, with
associated capacity being freed up on the system - Cogeneration projects create employment
opportunities
Extracts taken from an EIUG presentation dated
January 2007
27Industry PerspectiveLarge industry participation
- Power generation is not core business!
- Large industry is required to produce acceptable
investment returns for its shareholders
Cogeneration projects will therefore compete for
Capital Expenditure - Large industry is however committed to energy
efficiency projects in support of government and
associated initiatives - Eskoms current average cost of electricity
generation does not make cogeneration projects
financially viable A mechanism will need to be
introduced to close the gap between cogeneration
and existing power generation in South Africa - Many EIUG industry players are able to convert
waste energy into cogeneration (electricity) at a
lower cost than new generation capacity in South
Africa
Extracts taken from an EIUG presentation dated
January 2007
28Industry PerspectiveEnabling drivers
- Fast and efficient implementation of the long
term cogeneration framework developed by NERSA in
conjunction with Fieldstone, Eskom and industry - An avoided cost model, based on the cost of new
base load power plant should be adopted in
determining the ceiling price of competitive
cogeneration projects, as adjusted and determined
by NERSA - Industry should be given an opportunity to bid
for cogeneration against the avoided cost (as
above), and where cheaper, be contracted to
supply cogeneration (electricity) to the market - Promulgation and implementation of the NERSA
guidelines allowing industry to develop, bid for,
and develop cogeneration projects, to be
contracted with Eskom - In many cases, industry have completed
feasibility studies for cogeneration projects,
and are ready to respond
Extracts taken from an EIUG presentation dated
January 2007