Title: Overview of the ESKOM Winter 2006 Plan
1Overview of the ESKOM Winter 2006 Plan Outlook
for 2007
- Parliament Briefing
- May 2006
2Content
- Introduction
- Supply Demand Balance
- Load Forecast
- Capacity Plan
- Risks and Mitigation
- Transmission Corridors and Bulk Supply Points
- Corridors
- Firmness of Supply
- Risks and Mitigation
- Distribution Network
- Risks and Mitigation
- 2007 Outlook
- Principles of managing shortage of supply
3Introduction
- The aim of this presentation is to share the
prognosis for the Winter of 2006 (1 May 2006 to
30 September 2006) in terms of the ability to
generate sufficient energy to meet the demand in
South Africa and the ability to transport this
energy to the customer and to provide a brief
outlook for 2007. - A classification methodology to indicate the
level of generation capacity adequacy and
transmission network adequacy is described. - The prognosis based on this classification is
provided on a weekly basis as the base plan. - Key risks that could affect this base plan are
identified and mitigation strategies described. - Principles to manage any supply-demand imbalance
are described.
4Classification of Generation Capacity and
Transmission Network Adequacy
5Generation Capacity (MW)
- The weekly maximum Power Demand is forecast for
52 weeks in 2006 - The required Operating Reserves is 1 900MW which
is needed to manage real time demand variations
and sudden loss of import or generation. - The Required Supply is the sum of Power Demand
and Operating Reserves. - The Actual Supply on weekly basis is the
operational capacity in ESKOM less the sum of the
plant on planned maintenance and known unplanned
or forced outages. - The current operational capacity in ESKOM
excludes the Camden units as their reliability
has to be established through operational
experience. - The import from Cahora Bassa is planned to be
1050MW.
6Classification
- Green
- Supply deficit lt1000MW.
- Probably use of DMP resources and EL1.
- Orange
- Supply deficit between 1000 MW and 2000 MW
- Probably use Interruptible loads.
- Red
- Supply deficit between 2000 MW and 3000 MW
- Probably use interruptible loads and have some
mandatory load shedding. - Brown
- Supply defeicit gt 3000MW.
- Probably have rotating mandatory load shedding
7Winter 2006 Supply Demand Balance
8Resources Available
(RTS excluded)
9Emergency Resources
Additional Emergency DMP available in week 19
10Classification of Capacity Adequacy
11Supply Demand Balance
12Risks Mitigation - Generation
13Key Conclusion Generation Capacity
- We have enough available capacity but it very
tight - We have about 500MW additional emergency DMP and
more is being sourced - Key risks
- Impact of Koeberg on the national situation
- Technical problems on the running plants(loading
and age) - Higher demand than expected( weather and
commodity prices) - We are focused at avoiding mandatory load
shedding at a national level at all costs. - However multiple technical problems can
- result in load shedding.
14Transmission Corridors and Bulk Supply Points
15Transmission Network Adequacy
- Transmission Corridors supplying a significant
geographical area from the Mpumalanga Generation
Pool were identified . - The demand in these areas has been forecast and
the capacity of these corridors assessed through
power system studies. - Classification is as follows
- Green The corridor can supply the peak demand
even if a single credible contingency occurs
(N-1). - Orange The corridor can supply the peak demand
if no contingency occurs (N-0) and a contingency
plan exists to re-configure the distribution
network to supply the load. Interruption of
supply could occur based on the nature of the
contingency and the load will then be restored. - Red The corridor cannot supply the peak demand
with the existing network and load shedding is
required over the peak periods. - Brown The corridor cannot supply the demand at
peak periods as well as at other times of the day
and rotational load shedding is required
throughout the day.
16Corridors
17Firmness of Supply Major Cities
18Risks Mitigation - Transmission
19Key Conclusion Transmission Grid
- The Cape corridor remains a risk until Koeberg
units are back - Risk at the other corridors are considered low
- Risks of double contingencies are always present
20Distribution Network
21Risks Mitigation - Distribution
222007 Outlook
23Capacity outlook for 2007
24Principles of Managing Shortage of Supply
25Principles
- Supplying energy at the lowest cost is a key
driver - Optimize supply side resource usage specifically
on the primary energy side and the high
availability of our generation units - Creation of innovative demand side products
- Supplying high quality energy to our customer
base is a key driver - Well defined system reliability (security
adequacy) requirements - Tight operational control with primary focus on
grid security - Equitable execution of supply and demand side
options to meet lowest cost and high supply
quality drivers - Clear operational procedures for scheduling
dispatch - Operational discretion in special circumstances
- Merit order of resources to use to meet supply
mismatch - Shortage of Supply does not mean blackouts!
- One can predict shortfalls and schedule emergency
resources and if that runs out have controlled
load shedding managed by regional control
centres. - Sudden loss of generation due to faults are
managed through the utilisation of operational
reserves and automatic under-frequency load
shedding schemes which prevents cascading
outages. - Load is then restored in a controlled fashion.
26Thank You Questions?