Overview of the ESKOM Winter 2006 Plan - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Overview of the ESKOM Winter 2006 Plan

Description:

The aim of this presentation is to share the prognosis for the Winter of 2006 (1 ... Excessive load shed in certain areas and increased risk of brown-outs ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 27
Provided by: dpe4
Category:

less

Transcript and Presenter's Notes

Title: Overview of the ESKOM Winter 2006 Plan


1
Overview of the ESKOM Winter 2006 Plan Outlook
for 2007
  • Parliament Briefing
  • May 2006

2
Content
  • Introduction
  • Supply Demand Balance
  • Load Forecast
  • Capacity Plan
  • Risks and Mitigation
  • Transmission Corridors and Bulk Supply Points
  • Corridors
  • Firmness of Supply
  • Risks and Mitigation
  • Distribution Network
  • Risks and Mitigation
  • 2007 Outlook
  • Principles of managing shortage of supply

3
Introduction
  • The aim of this presentation is to share the
    prognosis for the Winter of 2006 (1 May 2006 to
    30 September 2006) in terms of the ability to
    generate sufficient energy to meet the demand in
    South Africa and the ability to transport this
    energy to the customer and to provide a brief
    outlook for 2007.
  • A classification methodology to indicate the
    level of generation capacity adequacy and
    transmission network adequacy is described.
  • The prognosis based on this classification is
    provided on a weekly basis as the base plan.
  • Key risks that could affect this base plan are
    identified and mitigation strategies described.
  • Principles to manage any supply-demand imbalance
    are described.

4
Classification of Generation Capacity and
Transmission Network Adequacy
5
Generation Capacity (MW)
  • The weekly maximum Power Demand is forecast for
    52 weeks in 2006
  • The required Operating Reserves is 1 900MW which
    is needed to manage real time demand variations
    and sudden loss of import or generation.
  • The Required Supply is the sum of Power Demand
    and Operating Reserves.
  • The Actual Supply on weekly basis is the
    operational capacity in ESKOM less the sum of the
    plant on planned maintenance and known unplanned
    or forced outages.
  • The current operational capacity in ESKOM
    excludes the Camden units as their reliability
    has to be established through operational
    experience.
  • The import from Cahora Bassa is planned to be
    1050MW.

6
Classification
  • Green
  • Supply deficit lt1000MW.
  • Probably use of DMP resources and EL1.
  • Orange
  • Supply deficit between 1000 MW and 2000 MW
  • Probably use Interruptible loads.
  • Red
  • Supply deficit between 2000 MW and 3000 MW
  • Probably use interruptible loads and have some
    mandatory load shedding.
  • Brown
  • Supply defeicit gt 3000MW.
  • Probably have rotating mandatory load shedding

7
Winter 2006 Supply Demand Balance
8
Resources Available
(RTS excluded)
9
Emergency Resources
Additional Emergency DMP available in week 19
10
Classification of Capacity Adequacy
11
Supply Demand Balance
12
Risks Mitigation - Generation
13
Key Conclusion Generation Capacity
  • We have enough available capacity but it very
    tight
  • We have about 500MW additional emergency DMP and
    more is being sourced
  • Key risks
  • Impact of Koeberg on the national situation
  • Technical problems on the running plants(loading
    and age)
  • Higher demand than expected( weather and
    commodity prices)
  • We are focused at avoiding mandatory load
    shedding at a national level at all costs.
  • However multiple technical problems can
  • result in load shedding.

14
Transmission Corridors and Bulk Supply Points
15
Transmission Network Adequacy
  • Transmission Corridors supplying a significant
    geographical area from the Mpumalanga Generation
    Pool were identified .
  • The demand in these areas has been forecast and
    the capacity of these corridors assessed through
    power system studies.
  • Classification is as follows
  • Green The corridor can supply the peak demand
    even if a single credible contingency occurs
    (N-1).
  • Orange The corridor can supply the peak demand
    if no contingency occurs (N-0) and a contingency
    plan exists to re-configure the distribution
    network to supply the load. Interruption of
    supply could occur based on the nature of the
    contingency and the load will then be restored.
  • Red The corridor cannot supply the peak demand
    with the existing network and load shedding is
    required over the peak periods.
  • Brown The corridor cannot supply the demand at
    peak periods as well as at other times of the day
    and rotational load shedding is required
    throughout the day.

16
Corridors
17
Firmness of Supply Major Cities
18
Risks Mitigation - Transmission
19
Key Conclusion Transmission Grid
  • The Cape corridor remains a risk until Koeberg
    units are back
  • Risk at the other corridors are considered low
  • Risks of double contingencies are always present

20
Distribution Network
21
Risks Mitigation - Distribution
22
2007 Outlook
23
Capacity outlook for 2007
24
Principles of Managing Shortage of Supply
25
Principles
  • Supplying energy at the lowest cost is a key
    driver
  • Optimize supply side resource usage specifically
    on the primary energy side and the high
    availability of our generation units
  • Creation of innovative demand side products
  • Supplying high quality energy to our customer
    base is a key driver
  • Well defined system reliability (security
    adequacy) requirements
  • Tight operational control with primary focus on
    grid security
  • Equitable execution of supply and demand side
    options to meet lowest cost and high supply
    quality drivers
  • Clear operational procedures for scheduling
    dispatch
  • Operational discretion in special circumstances
  • Merit order of resources to use to meet supply
    mismatch
  • Shortage of Supply does not mean blackouts!
  • One can predict shortfalls and schedule emergency
    resources and if that runs out have controlled
    load shedding managed by regional control
    centres.
  • Sudden loss of generation due to faults are
    managed through the utilisation of operational
    reserves and automatic under-frequency load
    shedding schemes which prevents cascading
    outages.
  • Load is then restored in a controlled fashion.

26
Thank You Questions?
Write a Comment
User Comments (0)
About PowerShow.com