Title: Eskom Generation way forward
1Eskom Generation way forward
2Three drivers of change impacting our business
Market Restructuring
Continue preparation for deregulation (also
requires a degree of divisional independence)
- Need for a more
- integrated approach
- in growing
- capacity
Limited resource availability
Declining surplus capacity
Need to maximise synergies operational
excellence
3Eskoms strategic positioning
- Our core business is electricity
- Generation
- Transporting
- Trading (among producers, wholesalers, and bulk
users) - Retail (to end users)
- Our target market
- South Africa
- SADC and the rest of Africa connected to the SA
grid - Rest of Africa
4Electricity demand and supply key challenges
- South Africa is approaching the end of its
surplus generation capacity - 1st challenge Avoiding mismatch between demand
and supply - Excess capacity - stranded resources
- Capacity shortage - constrained economic growth
- 2nd challenge Correct choice of capacity to be
constructed from an array of available options
that differ dramatically in terms of - Cost (construction and operating)
- Lead time to construction
- Environmental impact
- Operating characteristics
5Eskom's Installed Generating CapacityRed Solid
Line until end 2004 Actual peak demand PLUS
10 RESERVE MARGIN, thereafter _at_ 2.5 growth in
peak demand PLUS 10 RESERVE MARGIN.Fifty year
assumed plant life. Demand Side Management
initiatives NOT included
65 Year Capital Expansion Plan
- In October 2004, Cabinet approved the following
- Eskom to lead this current phase of creating new
electricity generation capacity - Earlier Cabinet decision to exclude Eskom from
future build programme was reversed - Decisions on any future (beyond the current 5
year programme) build programme will be on a case
by case basis - 5-year infrastructure investment plan in South
Africa's electricity infrastructure amounting to
R95 billion (DPE tabling of vote to parliament)
7Capacity Outlook - 2003 to 2022
- 6 year-on-year demand increase
- Major risks of insufficient supply options
- Ageing infrastructure
- Shortages if new build not initiated
8Planning Process Flow
Increasing Certainty
Investment Decision
Concept Screening
Complete business case
PHASE 1 PRE-FEASIBILITY
PHASE 2 FEASIBILITY
BUILD
NEW CONCEPTS
9Eskoms Return To Service (RTS) project
- 3 stations with a combined nominal capacity of
3800MW - built in the 1960s, and were mothballed due to
high excess capacity in the late 1980s and
1990s - An investment expenditure totalling R12 billion
(nominal rand) on the return to service of the 3
stations over the next 5 years
10Budget Vote
-
- Alongside this process, using Eskoms
purchasing power, we would introduce the first
significant Independent Power Producers (IPP).
This allowed for the initial indicative 5-year
investment figures to be provided with some
degree of certainty. - Minister Erwins Budget Vote Speech, 15 April
2005
11SA enjoys globally competitive prices
29 gap
12Eskom remains committed to keep the lights burning
Day Month Year