Title: IS estimating issues


1
IS estimating issues
  • Unique projects with much innovation
  • Estimates often produced early before
    specification agreed
  • No professional estimators
  • Few published metrics available

2
Analogy method
  • Find a similar project
  • Type of business
  • Size of applications
  • Scope of systems
  • Technical methods and standards
  • Must adjust for
  • Organisational culture
  • Users level of computer literacy
  • Degree of management support for project

3
Analysis and programming approaches
  • Explicitly estimate for one stage
  • Analysis method analysis stage
  • Programming method code/unit test stage
  • Extrapolate whole project outcome from stage
    estimate
  • Must adjust for
  • Project size
  • Familiarity with business and technical
    environment
  • Technical complexity

4
Direct estimate (from project breakdown)
  • Break down project (either using WBS or PBS
    approach)
  • Estimate for each task / product
  • Sum products to get stages
  • Sum stages to get project
  • Takes time
  • and requires expert estimators

5
Delphi technique
  • Several estimators given specification of work
    and asked for estimates
  • Summarised anonymously and results circulated to
    estimators
  • Can revise estimates in the light of others
    ideas
  • Method reduces personal disagreements and
    ego-based issues

6
CoCoMo
  • Formulae based on thousands of delivered source
    instructions (KDSI)
  • Basic, intermediate and detailed versions
  • CoCoMo II now developed for wider range of
    development approaches
  • Useful elapsed time formula

2.5 x (estimated effort in man-months)0.33
7
Function point analysis
  • Based on analysis of inputs, outputs and files
    accessed in system
  • Starts with unadjusted function points
  • Then adjusts for
  • technical complexity
  • performance-influencing factors
  • risks

8
Supporting activities
  • Can considerably inflate base estimates
  • Includes
  • Proportional activities
  • Team leading/supervision
  • Documentation
  • Quality control
  • Customer reviews
  • Elapsed-time activities
  • Project management
  • Systems management
  • Configuration management
  • Project office work