Title: SSD Update
1SSD Update
Howard Matis
2Outline
- What is the SSD?
- Why we need it?
- Some tracking results
- Current Status
- How to upgrade?
- Manpower needed to run the detector at its
potential
3The SSD exists!!
- The SSD is thin
- 1 radiation length - double sided Si
- The SSD lies at an ideal radius
- 23 cm - midway between IP and IFC
- The SSD has excellent resolution
- The SSD is too large to be replaced
- More economical to build other detectors
4Two Layers of Tracking
- 95 mm ? 4.2 cm strips
- 300 mm thick
- Double sided
- Crossed at 35 mrad
- 20 ladders
- 67 cm long
- Air cooled
- ??? lt 1.2
5SSD Facilitates Tracking from the TPC to IST
- ?xy 30 µm
- ?z 700 µm
- TPC pointing resolution at the SSD is 1 mm
- SSD pointing at the IST is 300 mm
Inside the IFC
6SSD has been used in STAR analysis
- Needed for SVT tracking
- SSD is essential for SVT analysis
7Data - Cu Cu 62 GeV Impact Parameter
TPC
TPC
SSD
SSD
SVT 1,2,3
SVT 1,2,3
1/p
1/p
- Resolution here includes vertex and hit
resolutions. Real values 20 smaller. - Huge difference in pointing between SVT and
everything else - At infinite momentum limit is 150 µm in XY and
80 µm in Z (vertex resolution) - At 1 GeV/c, it is 220 µm in xy and 150 µm in z
- z is our good (not shifting) coordinate!
8Situation for Upcoming Run
- Ran detector in December
- System ran and stable
- Obtained pedestals and noise
- 70 of the detector good for physics - NOW
- Should be able to recover rest to 95
- L2 aborts acceptable for rate lt30 Hz
- SSD not useful for p-p running
- Jerome Baudot will visit BNL and instruct new
people when ready to run - Need beam and full detector
9SSD Electronics and the Future
Module level - 768 strips per side ( P
and N side ) - Analog signal of 1.5 ?s -
50 mV/MIP - Readout speed 3 MHz
SSD level - 4 Readout Boards (RB)
located on the TPC wheels - Each RB
interfaces 10 ladders with trigger / daq /
slowcontrol - Readout speed 30 MHz
Ladder level - 2 Connexion boards ( 1
per side ) - 2 ADC boards ( 1
per side )
10Current Readout Speed
- Front end Digitization
- FEE runs at 3 MHz
- 96 chips/ladder side with 128 channels/chip
- 4.1 ms to digitize a ladder side
- Transfer to DAQ via RDO
- Readout at 30 MHz
- 1 RDO/10 ladder sides
- 4.1 ms for readout
- 3 ms for 0s to match TPC DAQ format
- 7 ms total
RDO Board
11How to Upgrade
- For 1.2 ms readout time
- Digitize at 10 MHz
- Have a RDO for 3 ladder sides - ?3
- No zeros to fill the ASICS ?2
- Opportunity to upgrade firmware
- Solve L2 abort problem
- Estimated cost (mostly to produce new RDOs )
100 k - Must verify power distribution and cooling
- Need to test concept
12Lessons Learned from STAR Operations
- Detector must be tested with full system before
each run at BNL - Experts must be available to assist ASAP
- Come to BNL if necessary
- Train shift crews
- Testing slots are limited
- Schedule access is not fixed
- Scheduled accesses should stick to the schedule
- SSD must have a mother at BNL making sure
detector is being used - Must be regular maintenance of the detector
13Need a team to succeed
- Physicists
- Subsystem leader (1/4 time)
- Software coordinator (1/2 time)
- Calibration and detector expert (1/2 time and
resident _at_ BNL) - Subsystem Expert (need at least 2 _at_ 1/4 time)
- Slow controls (1/8 time)
- Advice from present experts
- People who want to use it for physics
- Engineers
- French Support (need shops and some travel to
BNL) - Mechanical and electrical tech support (several
weeks during shutdowns) - Electrical Engineer (when problems occur)
14Summary
- SSD provides valuable tracking for current
detector and the Inner Tracker - Low maintenance calibration
- Should be supported by STAR
- Can be maintained
- Should work for this Au-Au run
- STAR must provide sufficient manpower for the SSD
to succeed
15The End
16Backup
17Pedestal
Noise
Ladders 1 - 10
18Pedestal
Noise
Ladders 11 - 20
19Maintenance Needed Next Summer Shutdown
- Solve the problem with one of the LV power supply
boards (ladder 5) - Check all cooling pipes. Understand HV trips
(cooling problem?) - Solved if SVT removed
- One ladder side (7P) is silent
- Fix ADC Board
- Might need to replace ladder
- Check optical fibers
- Need specialized equipment. At BNL?
- Fix L2 abort problem
- Need 1 month of a SSD Engineer and Tonko
20Runtime hardware support
- Requires less effort than the TPC or EMC
- Needs person at BNL watching SSD
- Advocating and assuring for its inclusion in the
run - Basic knowledge of system
- Answer simple questions from shift crews
- At least two people who can provide
- Backup
- Advise
- Help in access (need fixed access times from
RHIC) - Real expert who can consult
- FPGA Programming support
- Should only need this help during shutdowns
21Shutdown hardware support
- Fix known problems
- Tend to routine maintenance
- Assist if changes needed to SVT cone area
- Routine work on infrastructure
- People
- Team of physicists to work on the detector
- Electrical and hardware techs to do
infrastructure maintenance
22Software support
- One person doing daily calibration and checks of
the performance - Jerome Lauret requires a software detector leader
- responsible for making sure SSD is ready when
production starts - People who need SSD for their physics analysis
23(No Transcript)
24(No Transcript)