Title: SSD Operations
1SSD Operations
- August 20, 2007
- H. Matis for the SSD group
2Key Active People this Year
- US
- Michael LeVine
- Jim Thomas
- Vi Nham Tram
- Howard Matis
- Poland
- Jacek Plebanek
- Radoslaw Pieniazek
- France
- Christophe Renard
- Stephane Bouvier
- Gerard Guilloux
- Jonathan Bouchet
- Artemious Geromitsos
- Jerome Baudot
- David Bonnet
-
I hope I have not left someone out
3SSD Timetable
4Tasks
- QA, filtering, calibration
- Repair and maintenance
- Upgrade cooling
- L2
- Readout upgrade
- Slow controls
- Runtime operations
- Reinstallation
- QA monitoring
5QA, filtering, calibration(urgency 1 - now)
- Tasks
- Run filtering
- HV shifts
- Alignment
- Cluster detection
- People
- Jonathan (graduating)
- Artemious
- Jacek
- Radoslaw
- Need post doc leading this effort
- Continuity when detector is used again
- To do (when detector is reinstalled)
- Improve QA information so that they are easy to
understand
6Repair and Maintenance(urgency 1 - now)
- Several ladders are broken
- Ladders need to be checked and broken ones
repaired - Repairs must be done at Nantes
- People
- Stephane
- Help from Michael, Jim, and I
- To do
- Create a test bench at BNL for inspection
- Need BNL tech - 20 FTE to learn system, diagnose
and repair - Assemble parts inventory
- CAEN power supply flakey
- Repair or spares - lower priority
7Upgrade Cooling(urgency 2)
- Scenario I October 1
- 1/4 FTE designer for new cooling system
- Transfer SVT slow controls system to SSD
- Slow control group
- Install cooling interlocks
- Scenario 2 - Next year
- Cooling done as part of HFT installation
- Need to relate slow control interface to SSD
interlocks
8SSD Readout Upgrade(urgency 2 start 11/2007)
- Upgrade electronics Design of new readout
- Must be sensitive to DAQ1000
- STAR needs to define triggering requirements
- Personal for upgrade
- Christophe (Nantes) 0.75 FTE-yr
- Michael 0.5 FTE-yr
- Digital electronics engineer (BNL - TBD) 0.75
FTE-yr - Software to decode new data format
- Michael L. 0.1 FTE-yr
9L2 upgrade and fix(urgency 2 Implemented
before DAQ occupied with data taking)
- SSD crashes with L2 trigger
- Large amount of data needlessly sent to be
compatible with existing code - Only needed for scenario 1
- People
- Michael - 2 months
- Christophe
- STAR DAQ person for diagnosis
10New SSD-specific slow controls(urgency 2 start
3/2008)
- Replace EPICS/VxWorks with Linux version
- Can no longer support SUN-based system
- New presentation required for new readout
architecture - David Bonnet did excellent job in pass
- Need new 1 scientist FTE-yr (TBD) both tasks
11Runtime Operations(urgency 2 start 8/2008 or
9/2009)
- Run 7 - 3 people/week - 2 FTE/week
- Run 7 crew
- Michael, Jim, Vi Nham
- Jonathan, Artemious
- Jerome (in France)
- Did not train super expert
- Need one leader for the runtime operations group
- Knows all whims of the detector
- Resident at BNL
12Reinstallation(urgency 2 start 8/2008 or
8/2009)
- Reinstall detector and test - One month
- Installation
- Stephane
- Gerard
- BNL Tech
- Testing
- Christophe
- Train runtime crew
13QA monitoring(urgency 2 start 8/2008 or 8/2009)
- Need instantaneous online monitoring
- Helps to understand the SSD behavior (HV, reboot
of the Slow Control) - And to take action if needed
- Need to revisit the current plots (less but
relevant) - 2D occupancy plot
- (SSD hits/global tracks) distribution
- SSD hit vs. phi
- Plots for shift crew or SSD expert
- QA did not work well in Run7
- Need real-time monitoring
- Implementation 1 FTE for 1 month
14To do Scenario I or 2?(urgency 2 - decision by
January 2008)
- Does the SSD hurt or help the low mass run?
- Does it separate non-photonic electronics from
background? - SSD is used to calibrate the TPC
- How important is this?
- Need analysis by working groups of pros and cons
of having it in - Installation and cone design
- Path of upgrades
- Is upgrade funding available
- Longer the SSD out, the more institutional memory
lost - Decision needs to made by management by say
January 31, 2008
15Homework for SSD Group (urgency 1 - Completed by
October 2007)
- Need to write short proposal
- Jim and I
- Describe in detail how to update SSD
- Memorandum of Understanding
- Michael and Stephane (Christophe)
- Between STAR and SUBATECH
- Formally establish collaboration in DAQ1000 era
16Summary
- This year assembled a good team
- Strong support from the French
- Need to transfer center of gravity of support to
North America - significant training and a Blair for the
detector - STAR management must establish when the SSD will
be reinstalled - Establish formal structure for the group with
institutional responsibilities - Upgrade path must be specified
- Need money, engineering and tech support
- Many key personal are graduate students, postdocs
- French support will not increase
- Need to identify positions and funding for hire
- Excellent project for small university group to
join and provide significant contribution - Any volunteers?