1 LIFE12 ENV/IT/000652 CLEANSEDInnova
tive integrated methodology for the use of
decontaminated river sediments in plant nursing
and road building Start 01/10/2013 End
31/03/2016 03/04/2014 6 month progress
meeting PISA NAVICELLI premises
2LIFE12 ENV/IT/ 652 CLEANSED
- AGENDA
- PROGRESS MEETING
-
- 0930 NAVICELLI Welcome and opening of the
meeting - 0935 All Actions carried out by each partner
(please prepare a ppt presentation and include
CLEANSED logo and LIFE logo in each slide) and
scheduled activities till the end of March 2014. - 1100 All Open discussion on actions carried
out - 1115 All Coffee break
-
-
3LIFE12 ENV/IT/ 652 CLEANSED
- AGENDA
- PROGRESS MEETING
-
- 1130 All CLEANSED Technical future issues
- ISECNR Technical activities scheduled in the
next six months of the project - All Open discussion on actions to be carried
out in the next six months of the project. - 1200 ISECNR Management and dissemination
issues - 1250 All General questions
- 1300 End of progress meeting
- 1300 Tour of Navicelli premises
- 1330 Lunch
-
-
-
4LIFE12 ENV/IT/ 652 CLEANSED
- AGENDA
- ADMINISTRATIVE MEETING
-
- 1500 EC Monitor team CLEANSED administrative
issues - All the EC monitoring expert will check all
the project administrative documents (timesheets,
invoices, etc.) with each partner -
-
5LIFE12 ENV/IT/ 652 CLEANSED
6Technical Actions carried out by each partner in
the last six months
- B.1 Dredging, analysis and characterization of
contaminated sediments - B.2 Sediment treatment
-
7Technical Actions carried out by each partner in
the last six months
- Presentations of
- NAVI
- ISECNR
- CEBAS
- DICI
- UNIFI
- IBIMET
-
8Technical Actions carried out by each partner in
the last six months
- All Open discussion on actions carried out
9Dissemination activities carried out by each
partner in the last six months
- D1 Project website
- D2 LIFE information boards (end M3)
- D4 Diffusion material preparation
- D5 Press and media releases
- D6 Networking
- D9 Demonstration workshop, seminars, conferences
and other events - D10 Dissemination to Institutions and policy
makers - D11 International fairs and other events
- D12 Digital supports for international diffusion
-
10Dissemination activities
- ACTION D.1 Project web site
- ECOFATTING website in English and in Italian
www.lifecleansed.com - CEBASCSIC is preparing the Spanish version
- Each beneficiary is implementing the link between
the CLEANSED website to the beneficiary website -
11Dissemination activities
- ACTION D.2 LIFE information boards
- ISECNR produced 12 CLEANSED Notice boards and
sent them to all the beneficiaries - All the beneficiaries put the CLEANSED Notice
board in a public space - All the beneficiaries sent the photos of the
CLEANSED Notice board in a public space in each
beneficiary premises -
12Dissemination activities
- ACTION D.4 Diffusion material preparation
- 500 CLEANSED brochures
- 1,000 CLEANSED leaflets (two types)
- 1,000 CLEANSED plastic leaflets
- 1,000 CLEANSED copybooks
- 1 CLEANSED roll-up
- Decision of the project gadget
-
-
13Dissemination activities
- ACTION D.5 Press and media releases
- 4 articles related to the CNR event in local (La
Nazione, Tirreno) and web newspaper - article in Navicelli news
-
14Dissemination activities
- ACTION D.6 Networking
- Cluster with ECOFATTING,OXATAN, SHOELAW, PODEBA,
SOREME, BioNaD, BIOREM, After-Cu, MICROTAN,
C02SHOE, SHOEBAT, GREEN SITE, SOILPRO, RESAFE,
SEKRET, EVERGREEN (LIFE 09-10-11-12 projects) - Specific meetings with photos with GREENSITE and
After-Cu - All the coordinators were invited to the CNR LIFE
event at Pisa on 25th March 2014 - Some coordinators presented the projects at the
CNR LIFE event at Pisa on 25th March 2014 -
15Dissemination activities
- ACTION D.9 Demonstration workshop, seminars,
conferences and other events - ISECNR organised the LIFE CNR event in CNR
premises on 25 March 2014
16Dissemination activities
- ACTION D.10 Dissemination to Institutions and
policy makers - Some beneficiaries started to have some contacts
with Institutions and policy makers in order to
organise specific meetings and events
17Dissemination activities
- ACTION D.11 International fairs and other events
- EFUF 2014 June 3 - 7, Lausanne, Switzerland
- REMIDA 28-29/11/2013 at Terni (Italy)
- SICA 17-20/02/2014 at Piacenza (Italy)
- ECOCITY fair in November 21-24, 2013 at Pisa
- ECOMONDO fair in November 5-8, 2013 at Rimini
- International Congress on Phytoremediation of
Polluted Soils. Vigo, July 28 29, 2014 - Request for EXPO2015
18Dissemination activities
- ACTION D.12 Digital supports for international
diffusion - Each beneficiary started to define the specific
video of each beneficiary activity - ISECNR started to have some contacts with some
expert video companies in order to organise the
general structure of the video - ISECNR started to work on the video text
19Management activities
- ACTION E.1 Project management
- ACTION E.2 Monitoring
- ISECNR has continuous contact with all project
partners for monitoring project activities - ISECNR prepares and sends a summary of the
project activities carried out to monitoring team - ISECNR needs to receive from each partner
technical inputs for the monitor summary
20SOREME Technical future issues
- ACTION B.3 Demonstration of the use of
decontaminated sediments as a substrate for plant
nursing - ACTION B.4 Demonstration of the use of
decontaminated sediments in road construction - ACTION C.1 Monitoring and validation of treated
sediments - ACTION C.2 Monitoring and validation of the use
of decontaminated sediments for plant nursing - ACTION C.3 Monitoring and validation of the use
of decontaminated sediments for road
construction(start)
21SOREME Technical future issues
- All Open discussion on actions to be carried
out in the next six months of the project
22SOREME Dissemination future issues for the next
six months
- D1 Project website update
- D2 LIFE information boards (end M3) OK
- D4 Diffusion material preparation more material
(foreseen 24 Posters,12,000 leaflets/brochures/fac
tsheets, 2,400 gadgets, 6 roll-ups,
presentations, now 2,000 brochures/leaflets,
presentation) - D5 Press and media releases more articles
(foreseen 30 articles, now 5) - D6 Networking OK OK (foreseen 7 projects, now
16) - D9 Demonstration workshop, seminars, conferences
and other events organisation and participation
in many more events (foreseen maximum
dissemination, now 1 event) - D10 Dissemination to Institutions and policy
makers more contacts and event
definition(foreseen successful communication) - D11 International fairs and other events
participation in many more events (foreseen
maximum dissemination, now 5 events) - D12 Digital supports for international
diffusion start (foreseen project video)
23ADMINISTRATIVE ISSUES
- Next Deliverables
- Partner costs March 2014
- Inception Report
- Next meeting
24NEXT DELIVERABLES
- All the following Deliverables will be annexes of
the Inception Report - Website Action D.1
- LIFE notice board Action D.2
- Poster Action D.4
- Roll-up Action D.4
- Brochures and factsheet Action D.4
- Report on monitoring indicators Actions E.2
- Report on treatment Action B.2
- Sediment characterization reports Action B.1
- Stationery/gadgets Action D.4
- Technical specifications of sediment treatment
Action B.1 - Visual documentation Action B.2
- Sediment samples Action C.1
- Executive design of demonstartion road Action
B.4 - Photographic evidence Action B.4
- Sediment characterization reports (chemical,
biological, nano, etc.) Action C.1
25Partner costs March 2014
PARTNER PARTNER CLAIM
Personnel Personnel March 2014 Travel Travel March 2014 External assistance External assistance March 2014 Consumables Consumables March 2014 Other costs Other costs March 2014 Overheads Overheads March 2014 TOTAL TOTAL March 2014
ISECNR 192,710 38,911.91 12,500 253.30 69,970 218.04 36,500 1,789.24 1,920 345.11 21,955 2,906.23 377,073 44,423.83
IBIMET 146,300 4,186.57 12,500 73,720 54,500 - 20,091 293.06 311,298 4,479.63
CEBAS 100,935 21,180.32 12,500 1,809.90 39,870 3,640.00 73,000 5,676.01 1,920 15,975 2,261.44 276,506 34,567.67
NAVI 160,000 32,421.75 7,400 107,240 57,697.96 15,000 - 20,274 6,308.38 400,034 96,428.09
DICI 124,550 8,478.02 12,500 100,720 60,000 20,843 593.46 327,091 9,071.48
UNIFI 70,020 15,577.07 7,400 5,400 48,000 - 9,157 1,090.39 155,554 16,667.46
TOTAL 794,515 120,755.64 64,800 2,063.20 396,920 61,556.00 287,000 7,465.25 3,840 345.11 108,295 13,452.96 1,847,555 205,638.16
26Inception Report
- ISECNR will be responsible of the production of
the Inception report which will be made up by - Progress report with the summary of technical,
administrative and dissemination project issues - Dissemination Annex
- Deliverables
- Output indicator tables
- The Inception Report will produce the CLEANSED
GO/NO GO from the EC - The Inception Report deadline is 30 June 2014
- All the beneficiaries have to send the technical
and administrative contribution to ISECNR
27Inception Report
- Deadline
- ISECNR will send to each partner a form for
technical and dissemination contribution for the
Inception Report no later than 15th of May - Each partner has to send to ISECNR all the
technical contribution no later than 10th of June
2014 (except some June activities) - Each partner has to send to ISECNR all the
dissemination contribution no later than 10st of
May 2014 (except some June activities) - Each partner responsible for a Deliverable has to
send to ISECNR the Deliverable no later than 10th
of June 2014 - ISECNR will send to EC and Monitoring agency all
the Inception Report documents no later than 30th
of June 2014
28Project meetings
- 1st Kick off meeting in ISECNR in Italy in
October 2013 - 2nd Coordination meeting in NAVICELLI in Italy in
April 2014 - Next Project meeting
- 3rd Coordination meeting in UNIFI in Italy in
October 2014