Title: Fargo Flood Control


1
Fargo Flood Control Southside
Flood Protection Landowner Meeting, Chrisan
West September 15, 2008
2
Fargo
Moorhead
Interstate 29
Rose Coulee
Frontier
25th Street South
Red River
Cass Co Hwy 81
Wild Rice River
1997 Spring Flood South of Fargo
3
Southside Flood Control
Wild Rice Levee Alternative with Channel
Extensions Recoverable Storage
4
Southside Flood Control
Preliminary 100 500 Year Floodplains
Existing 100 500 Year Floodplains
5
Chrisan West
Basic Protection
Project Cost 1.4 Million
6
Chrisan West
Option 1 FEMA Protection Levee West of Cass
County Highway 81
Project Cost 1.6 Million
7
Chrisan West
Option 2 FEMA Protection Raise Cass County
Highway 81
Project Cost 3.2 Million
8
(No Transcript)
9
Chrisan West Resident Feedback
10
Chrisan West Resident Feedback
11
Chrisan West
Technical Committee Preferred Option FEMA
Protection Levee West of Cass County Highway 81
12
Chrisan West Concerns Raised
  • Snow Removal
  • Parking
  • Interior Drainage
  • City utilities under frontage road
  • Frontage road paving (desire to have paved road)
  • Disruption to trees/landscaping
  • Property value reduction (with levee in front)
  • Annexation
  • Existing drainage west of homes

13
(No Transcript)
14
(No Transcript)
15
Project Schedule
Development of options east of University Drive April-June 2008
City Commission Selection of preferred base alternative July 14, 2008
Public input meetings April 15 - September 2008
Environmental Assessment July December 2008
Consultant Selection July - December 2008
Begin Design December 2008
CLOMR Submittal July December 2008
CLOMR Approval March 2009
ROW Acquisitions October 2008 October 2009
Permitting September 2008 April 2009
Special Assessment District September December 2008
Begin Construction June 2009
Functional Completion March 2011
Final Completion July 2012
16
Southside Flood Control
Questions / Discussion