Title: MINE LIFE CYCLE, DOWNSTREAM PROCESSING, AND SUSTAINABILITY
1MINE LIFE CYCLE, DOWNSTREAM PROCESSING, AND
SUSTAINABILITY
- STAGE 1 - Exploration and Assessment
- STAGE 2 - Construction
- STAGE 3 - Operation
- STAGE 4 - Closure
2MINE LIFE CYCLE, DOWNSTREAM PROCESSING, AND
SUSTAINABILITY
- STAGE 1 - Exploration and Assessment (1-10 years)
- Exploration - Geophysics
- Exploration - Drilling (1/10)
- Geology - Analytical and Mineralogical Assessment
- Economic Feasibility Assessment (1/10)
- Orebody Modeling (1/10)
- Mine Planning and Metallurgical Testwork
33-D Orebody Model for Mine Planning
- INCO's Research Mine at Sudbury, Ontario
4Underground LHD
Campbell Mine, Ontario
5Remote-LHD
Olympic Dam Mine, Australia
6Mine Life Cycle (continued)
- STAGE 2 Construction (0.5-2 years )
- Mine
- Shaft-sinking tunnel/stope development (U/G)
- Adit tunnel/stope development (mountain-top)
- Top soil removal, key-cut, haul road development
(Open-Pit) - Plant
- Site Preparation, Foundations, Construction of
buildings - Procurement and Installation of Equipment
- Waste and Tailing Disposal
- Site Selection and Preparation
- Construction of Initial Coffer Dam for tailing
disposal
7Open Pit Mining
Shovel Loading - Porgera Mine, Papua New Guinea
8Strip Mining
Coal Mine Shovel-Truck Operation
9200 T Haulage Truck
10Open Pits are Colorful
Florida Phosphate Mining
11Diamond Pipe Deposit
12Ekati Diamond Mine
Kimberlite Pipe Deposit
13What its all about at Ekati!
Diamonds are forever!
14Canadian Diamonds
15Polar Diamond Certificate
16Ekati's Polar Diamond
17Open Pit Mine
Bingham Canyon Mine
18Mill Complex
Bingham Canyon Mill
19Secondary Crushing Plant
20Grinding Mills
Bingham Canyon Grinding Mills
21Grinding Mills
22Mill Control Room
Carlin Mine, Nevada
23Mine Life Cycle (continued)
- STAGE 3 - Operation ( 3 - 400 years )
- Mine
- Blast, Load, Haul, Dump
- Transport (hoist, convey, truck, rail), Stockpile
- Safely Store Waste (on site or in-mine)
- Mill
- Crush, Grind (comminution)
- Physical Separation (maybe chemical)
(beneficiation) - Thicken and Filter (dewater)
- Safely Store Tailing
24Mine Life Cycle (continued)
- STAGE 3 - Operation ( 3 - 400 years )
- Waste Disposal
- Dump
- Contour, Spread top soil
- Hydro-seed and plan for final drainage
- Tailing Disposal
- Plan for Lifts as Tailing Dam builds
- Control Water Levels
- Recover water for recycle
- Revegetate dam walls
25Tailing Dam Reclamation
26Revegetation
Hydro-Seeding a Waste Dump
27Mine/Mill Complex
Musslewhite Mine, Ontario
28Downstream Processing
- Mine/mill complex
- produces ore or concentrate or unrefined
metal/product - product transported by airplane, rail, truck or
ship to smelter or refinery - if leaching is used at mine/mill, unrefined
metal or final product is produced - Smelting
- pyrometallurgical processing (multi-stage)
- roasting to partially remove/control sulfur
content - melting to separate oxides from sulfides (flux
and slag) - oxidation to remove sulfur and iron
- need SO2 control and slag disposal system
29Downstream Processing
- Leaching
- hydrometallurgical processing
- vat leach, agitation leach, heap leach, in-situ
leach - Pressure Oxidation or Biological Leaching
- solid/liquid separation or ion adsorption process
- solution purification (solvent extraction/ion
exchange) - need residue disposal method (dewatering/storage)
- Refining
- electrometallurgical processing
- electrowinning to recover metals from solution
- electrorefining to purify unrefined metal
- treatment of slime deposits for PMs recovery
30Copper Ores Concentrating
- Simplest Copper Flotation Circuit
31Copper Ores Concentrating
- Copper Oxide Processing to final metal
32Heap Leach Operation
Installing a Plastic Membrane Liner
33Zaldivar Copper Heap Leach
34Copper Downstream Processing
- Kidd-Creek Smelter flowsheet
35Copper Anode Casting Wheel
36Downstream Processing
- Nickel
- Typical Mine/Mill Treatment
37Downstream Processing
- Nickel
- Matte Separation processing
38Chuquicamata Mine/Mill/Smelter
39Downstream Processing
40Downstream Processing
41Downstream Processing
42Uranium Mines - Australia
43Uranium Resources
44Copper-Uranium Ore
Olympic Dam Mine, Australia
45Olympic Dam Refinery, Australia
46Olympic Dam Refinery, Australia
47Downstream Processing
48Gold Flakes
49Gold Panning
50Gold Flakes
51Grinding and Cyanide Leaching
Musslewhite Mine, Ontario
52Smelting Gold
Campbell Mine, Ontario
53Pouring Slag
Musslewhite Mine, Ontario
54Pouring Gold Bullion Bars
55What its all about!
Gold Bullion
56Samarco Iron Ore Flowsheet
57Samarco Iron Ore Concentrator
58Samarco Iron Ore Pipeline
59Iron Ore Pellets
Malmberget, Norway
60Downstream Processing
61Downstream Processing
62Downstream Processing
63Downstream Processing
64Downstream Processing
65Mine Life Cycle (continued)
- STAGE 4 - Closure( 1 - 20 years )
- Mine
- Flood Pit
- Seal Underground workings
- Long-term Acid Rock Drainage plan for waste dumps
- Mill
- Salvage Equipment
- Raze Buildings
- Contour and reseed site
- Long-term ARD plan for tailing dam
66Sustainability
- Important Factors
- Technical
- Economic
- Social/Political
- Environmental
- Past mining activities focused on only the first
two - The latter two have now become equally, if not
- more important
67Sustainability
- A Mine must plan for closure before it starts up
- A mining company must always consider local
communities in all parts of the world - As an industry, we must find ways to enhance our
image and to influence government decision-making - Future methods must reduce the footprint of
mining - no more open pits
- waste returned to the mine
- processing at the face
- robotics and remote-mining systems
68Sustainability
- The BC Mining Industry must encourage its members
to institute vertical integration policies - We need to invest in much more value-added
processing (i.e. smelting and refining in BC) - Downstream manufacturing industries must be
encouraged to develop in BC - This will provide the necessary systems to begin
significant recycling of metals and other
materials in the Pacific North-West
69Sustainability
- Social/Political Issues
- Land Use
- Government policies
- The Influence of Activism
- Environmental concerns
- Aboriginal peoples and treaties
- Need for jobs and a diversified economy
- In BC, the Tatsenshini/Windy Craggy decision has
- had important long-term impact on Mining
- Similarly, the Delgamuk decision and Nishka
Treaty are important to the future of BC's mining
industry