Closing Out a Federal Aid Construction Project - PowerPoint PPT Presentation

About This Presentation
Title:

Closing Out a Federal Aid Construction Project

Description:

Closing Out a Federal Aid Construction Project. Missouri Local Programs. How to Close-Out a Federal Aid. Construction Project – PowerPoint PPT presentation

Number of Views:54
Avg rating:3.0/5.0
Slides: 14
Provided by: epgModot4
Learn more at: https://epg.modot.org
Category:

less

Transcript and Presenter's Notes

Title: Closing Out a Federal Aid Construction Project


1
Closing Out a Federal Aid Construction
Project Missouri Local Programs How to Close-Out
a Federal Aid Construction Project
2
Documentation Required forLPA Project Closeout
  • 1. Semi-final/Final inspection letter
  • 2. LPA Final acceptance letter
  • 3. Testing Results certification
  • 4. Contractor DBE Certification LPA
    Recommendation
  • 5. Final Invoice
  • 6. Final Detailed estimate of quantities
  • 7. Contractors Affidavit Regarding Settle of
    Claims
  • 8. Final Change Order
  • 9. Affidavit (Compliance with Prevailing Wage)

3
1. Semi-final/Final Inspection Letter
  • -All projects are required to have a semi final
    inspection. If any needed corrections to the
    project are found, a final inspection is then
    required after all corrections have been
    addressed.
  • -Those required to attend semi-final inspection
    LPA Representative, contractor, engineer of
    record, MoDOT.
  • -The Final Inspection Letter shall state those in
    attendance, the date inspection took place, and
    any corrections needed.

4
2. LPA Final Acceptance letter
  • -The LPA must submit a final acceptance letter on
    LPA letterhead stating that they accept all work
    completed by the contractor.
  • -The letter must also include the number of
    working days in the contract and the number of
    working/calendar days it took to complete the
    project. If it was a completion date contract,
    list the contractual date and the completion
    date. If liquidated damages were incurred, they
    must be listed.

5
3. Testing Results Certification
  • -The engineer of record shall supply a letter
    certifying the results of the test for acceptance
    of materials. See EPG Figure 136.11.XX for
    example letter.
  • -The certification statements that must be
    included in this letter can be found in EPG
    136.11.20 of the LPA manual. Number 3 lists all
    three required statements ( a., b. c.). (link)

6
4. DBE Contractor Certification LPA
Recommendation
  • Contractor Certification
  • The contractor is to fill out the Contractor
    Certification Form (EPG Fig. 136.11.X). This form
    must list final DBE participation showing all
    work performed and dollar amount paid to each DBE
    used on contract.
  • LPA Recommendation of DBE Performance
  • The LPA must supply on LPA letterhead a
    recommendation to MoDOT as to the fulfillment of
    the DBE requirements.
  • If DBE goals were not met, the LPA must supply
    documentation as to why.
  • MoDOT makes the final determination of DBE
    fulfillment

7
5. Final Invoice
  • The appropriate copies of the final invoice shall
    be included with the close out documentation.
  • The final invoice will not be reimbursed if all
    closeout documentation and certifications have
    not been received by MoDOT within 30 days of
    final inspection.

8
6. Final Detailed Estimate of Quantities
  • A final detailed estimate of quantities must show
    the final adjusted contract amount. This estimate
    will include any overruns or underruns of pay
    items encountered over the length of the
    contract.
  • Typically the detailed estimate is supplied by
    the contractor to the LPA for pay request.

9
7. Contractors Affidavit Regarding Settle of
Claims
  • The Contractors Affidavit Regarding Settle of
    Claims (Figure 136.11.8) shall be filled out and
    executed by the contractor and supplied to the
    LPA.

10
8. Final Change Order
  • A copy of the final change order is required to
    close out a project (if applicable).
  • If all change orders have been approved and there
    is no final change order needed, a copy of
    previous change orders must be supplied.

11
9. Affidavit (Compliance with Prevailing Wage)
  • The Affidavit (Compliance with Prevailing Wage),
    (Figure 136.11.9) shall be filled out and
    executed by the contractor and supplied to the
    LPA.

12
Final Acceptance by MoDOT
  • After items 1-9 have been supplied to MoDOT, they
    will be reviewed for correctness, extra funds
    will be obligated for change orders and final
    reimbursements to the LPA will be approved and
    issued.
  • A final acceptance report will be generated by
    MoDOT and sent to the LPA. This report closes
    the project and no additional funds can be
    obligated or reimbursed.

13
The End!
  • Thank You!!
Write a Comment
User Comments (0)
About PowerShow.com