Title: Conventional Facilities Overview
1CF LCLS Commissioning Plan Javier A.
Sevilla Engineering Group Conventional Facilities
2Outline
- Plan
- Team
- Commissioning Process
- Activities
- Deliverables
- Summary
3Commissioning Areas
Beam Transport Hall
Undulator Hall
Near Experimental Hall
Central Utility Plant/ 12Kv Substation 522
Far Experimental Hall
Electron Beam Dump
Front End Enclosure
X-Ray Transport Diagnostics Tunnel
4Commissioning Plan
Prepared by
- Defines Scope of CxA and requirements
- Part of contract documents for each MEP
subcontractor - Part of TCCo Contract
http//www-ssrl.slac.stanford.edu/lcls/cf/commissi
oningplan/
5Scope Definition for CxA
- List Requirements
- List Deliverables
- List team members
- Provides all reference documentation
https//www-lcls-internal.slac.stanford.edu/projec
tspace_L2/Project_Office/SOW/ConvFac/1.9-703-r0.pd
f
6Team
- Commissioning Agent (CxA)
- Engineering Economics Inc. (EEI)
- CF Engineering Group
- CF Construction Group
- LCLS QA Manager
- Turner
- MEP Coordinator
- Cx Coordinator
- SLAC Facilities Dept
- HVAC, Electrical, Fire Alarm, Ops Mechanics
- Subcontractors
- O. C. McDonald-HVAC Piping
- Alpha Air Balancing Agency
- Cupertino Electric (CEI)
- Air Systems, Inc. BMS
- Ceitronics-Fire Alarm
- Mitsubishi-Elevator
- Allied Cranes
- RCM-Fire Protection
7Commissioning Agent (CxA)
- Engineering Economics Inc (EEI)
- Selected by using a competitive bidding process
- Five bids received (AEC, EEI,AEI, and WBI)
- EEI has offices nationwide and able to shift
resources if necessary - Commissioned over 33 million sf
- Data centers, office buildings
- Medical research labs
- Pharmaceutical labs
- Federal facilities
- LCLS Sector 20 Injector Facilities - successful
- LCLS Magnetic Measurement Facilities - successful
8Commissioning Meeting
Started in Nov. 14, 2007- Meetings every 3 weeks
May 2-08 Weekly Meetings
9Commissioning Team
- CF LCLS
- K. Ahmed
- R. Baclit
- D. Ciorbea
- R. Maggi
- J. Saldivar
- J. A. Sevilla
- L. Shewchuk
- K. Yang
- QA Manager
- D. Marsh
- ESH/BIO
- R. Kerwin
- E. Gomes
- B. Smith
-
- Subcontractors-TCCO
- A. Pimentel
- F. Sisca
- C. Farnell
- R. Gonzales
- G. Strickland
- J. Fitzgerald
- H. Limosnero
- K. Minchaca
- D. Swartz
- R. Spina
- R. Furtado
- T. Locatelli
- M. Clayton
- SLAC Facilities
- B. Choate
- G. Kuraitis
- R. Radau
- K. Chan
- R. Candelario
- B. Harrison
- P. Francisco
- S. Poitier
- S. Jensen
- J. Kang and HV electricians
- J. Pfefferkorn
- F. Castillo and LV electricians
- K. Joong
- N. Yeung
- R. Zingsheim
- EEI
- K. Quigley
- A. Parker
- M. Abrahamson
-
-
10Commissioning Team at Work
11Commissioning Process
PLAN
Requirements (FT, PFT, Acceptance, Inspections)
Resources (CxA, CF Engrs, TCCO, Subcontractors,
Facilities
Configuration Control of test results,
observations, inspections, minutes, schedule,
acceptance, etc.
Configuration Control of tests results,
inspections, training, documentation, acceptance,
etc.
http//www-ssrl.slac.stanford.edu/lcls/cf/commissi
oningplan/
12Configuration Management Cx Process
ftp//ftp.slac.stanford.edu/groups/lcls/Turner/LCL
S20Commissioning20Process/
13Commissioning Process
- Activities
- Review of design documents by CxA
- Site inspections (CxA, Facilities Dept, CF LCLS)
- Prepare list of observations (by Category)
- Review of Constructions checklists (CxA and
Facilities Dept) - Witness some PFT (CxA)
- Perform ALL Functional Testing (FT)
14CUP Plan View
Drawing M0203
Boilers
Chillers
Mech Room-NEH
Electrical Rm
15CUP On-Going Cx Activities
Switchgear
Boiler
Chillers
Substation 522
CUP transformers
16Commissioning Activities Completed
- Substation S522
- Energized and completed except pending punch list
- Rating capacity 4,000 amps, 12.47 KV
- Provides power to LCLS three 2.5MVA transformers
and others - New medium pressure underground natural gas
piping to CUP 1,400 LF - 30 Million BTUHs nominal capacity
- BTH West Construction
- BTH Switchboard ( 480 v, 3 ph, 800 Amps)
17LCLS Substation S522
Substation 522 behind the CUP
12.47 kv Switchgear inside
18CENTRAL UTILITY PLANT (CUP)
- Major Equipment to Commission
- Two Chillers (425 tons/ea), Primary and Secondary
CHW loops and Pumps? BTH,UH,EBD,FEE, NEH and FEH - One Boiler (150 BHP/ea) Primary and Secondary HW
loops and pumps - DDC Temperature Control System to be connected to
SLAC network via ALC Web Control - Interface with EPICS (Technical systems)
- One Air Compressor (268 SCFM_at_150psi), Air Dryer
and Receiver. - Will provide service to BTH, UH, EBD, FEE,
NEH,X-RAY, FEH - Wet Sprinkler System-Ordinary Hazard Group 1
- One AHU for electrical room
- Mechanical rooms for NEH HVAC system (MAU) and
AHUs
19Chillers Room in CUP
20Deliverables
- Final Commissioning Report
- Pre-Functional and Functional Test Reports (FT),
PFT, Checklists, observations. Etc. - OM MEP
- Training Records
- All documentation available for future operations
and maintenance
21Summary
- Roles and responsibilities are clearly defined in
the Commissioning Plan - Expectations are documented and well understood!
- CxA reports to CF LCLS and collaborate with TCCO,
MEP subs, SLAC Facilities maintenance and
operations staff - Goal is to deliver a complete and functional
project with all MEP systems fully operational,
inspected, tested, checked, verified and
documented!
22End of PresentationSupporting Documentation to
Follow
23Partial List of MEP Equipment
24Minutes of Meetings
25Review Documentation and PFT
26CUP Plan View
Drawing M0203
Boilers
Chillers
Mech Room-NEH
Electrical Rm