1EMS Design Including P2
BMW Manufacturing Corp.
August 24, 1999
2BMW Received ISO 14001 Certification in August,
1998
3New Plant Opened in 1994
- Excellent opportunity establish state-of-the-art
EMS - Associates have no corporate memory to overcome
- Culture includes commitment to the environment
4BMWs Environmental Policy
- Commits us to
- Compliance
- Continual Improvement
- Consistency with BMW AG requirements
- Pollution Prevention
5Plant 10 Environmental Performance
- Recognized as most environmentally-friendly plant
in automobile industry - Winner of 1997 Governors Pollution Prevention
Award - Certified in the Wildlife Industry Together
Program in July, 1998
6Recent Recognition
- Accepted into South Carolina Environmental
Excellence Program - November, 1998 - Recipient Carolina Recycling Association award
for Outstanding In-house Waste Reduction
Program - March 1999
7Performance beyond compliance
- Lowest air emissions in the industry
- Best 5 in industry in toxic chemical releases
- 24 reduction in toxic chemical releases from
1997 to 1998 - 73 of all wastes recycled
- VOC Emissions well below permitted limits
8(No Transcript)
9(No Transcript)
10(No Transcript)
11Do Results Come About by Chance?
- P2 Team was created in 1996
- Members from each operational department
- Waste streams tracked annually
- Menu of possible projects brainstormed
- Environmental targets developed each year
- Progress tracked annually
121998 Waste Minimization Results
13Management's Goal
- To increase the effectiveness of our
environmental management system by making each
department more directly responsible for setting
and achieving agreed-upon goals - To implement ISO 14001 as an integral part of our
business management system - Avoid environmental violations by any regulatory
agency with environmental authority
14Examples of EMS Program Results
- Paint waste was reduced by 145,700 pounds, saving
the company 864,000 - Solvent parts washers converted to aqueous,
eliminating waste stream
15More examples.
- Returnable packaging projects (wiring harnesses
and transmissions) reduced waste by more than 1
million pounds in 1998 - Paint sludge dewatering improvements saved
57,500
16Returnable Packaging for Transmissions
17P2 and ISO 14001 A Perfect Fit
- Little change for P2 team
- ISO 14001 programs are a direct and natural
outgrowth of P2 concept - ISO 14001 makes a P2 practices part of the
management system - Probability of future success improved
18EMS Process
Env. Policy
Legal Requirements
Management Review
Aspects
Audits
Significant Aspects
Programs
Targets Objectives
19Env. Policy
Targets ObjectivesEach Department adopts
environmental targets objectives considering
its significant environmental aspects
Legal Requirements
Aspects
Significant Aspects
Targets Objectives
20Env. Policy
ProgramsEach department adopts specific
environmental programs to achieve targets
Legal Requirements
Aspects
Significant Aspects
Programs
Targets Objectives
21An Important Element of the EMS Is Continual
Improvement
- A good P2 Team functions at the heart of the
continual improvement cycle - Requires good tools from technical support areas,
including effective methods for tracking progress - Requires strong management support
22Whos responsible for protecting the environment?
23And a good P2 team is an essential element that
can champion the continual improvement process
and ensure success
24Thank you