Chapter 10: Monitoring and Controlling Change - PowerPoint PPT Presentation

About This Presentation
Title:

Chapter 10: Monitoring and Controlling Change

Description:

PMP Study Guide Chapter 10: Monitoring and Controlling Change Chapter 10 Monitoring and Controlling Change Managing Integrated Change Control Managing Cost Changes ... – PowerPoint PPT presentation

Number of Views:169
Avg rating:3.0/5.0
Slides: 17
Provided by: JanetC72
Learn more at: https://web.lemoyne.edu
Category:

less

Transcript and Presenter's Notes

Title: Chapter 10: Monitoring and Controlling Change


1
PMP Study Guide
  • Chapter 10 Monitoring and Controlling Change

2
Chapter 10 Monitoring and Controlling Change
  • Managing Integrated Change Control
  • Managing Cost Changes
  • Monitoring and Controlling Schedule Changes
  • Monitoring and Controlling Risk

3
Managing Integrated Change Control
  • How change occurs
  • Change control concerns
  • Change control techniques
  • Integrated Change Control outputs

4
Change Control Concerns
  • Influencing the factors that cause change and
    reaching agreement on change requests
  • Determining a change is needed or has happened
  • Managing approved changes
  • Updating requirements that impact project plan
  • Documenting requested changes and their impacts

5
Integrated Change Control
  • Configuration management
  • Change control system
  • Configuration control board

6
Chapter 10 Monitoring and Controlling Change
  • Managing Integrated Change Control
  • Managing Cost Changes
  • Monitoring and Controlling Schedule Changes
  • Monitoring and Controlling Risk

7
Managing Cost ChangesPerformance Measurement
Analysis
  • Earned value technique
  • Planned Value (PV) Budgeted Cost of Work
    Scheduled (BCWS)
  • Actual Cost (AC) Actual Cost of Work Performed
    (ACWP)
  • Earned Value (EV) Budgeted Cost of Work
    Performed (BCWP)

8
Earned Value
Figure 10.1
9
Earned Value Formulas
  • Cost Variance(CV) EV AC
  • Schedule Variance(SV) EV PV
  • Performance Indexes
  • Cost Performance Index (CPI ) EV AC
  • Cumulative CPIC EVC ACC
  • Schedule Performance Index (SPI) EV PV
  • Cumulative SPIC EVC PVC

10
Earned Value Formulas (cont.)
  • Estimate to Completion (ETC)
  • ETC (BAC EVC ) CPIC
  • ETC BAC EVC
  • Estimate at Completion
  • EAC ACC ETC
  • EAC ACC ((BAC EV) CPIC)
  • EAC ACC BAC EV
  • Variance at Completion
  • VAC BAC EAC

11
Chapter 10 Monitoring and Controlling Change
  • Managing Integrated Change Control
  • Managing Cost Changes
  • Monitoring and Controlling Schedule Changes
  • Monitoring and Controlling Risk

12
Monitoring and Controlling Schedule Changes
  • Schedule control involves determining status of
    project schedule, if changes have occurred or
    should occur, and influencing and managing
    schedule changes

13
Monitoring and Controlling Schedule ChangesTools
and Techniques
  • Progress reporting
  • Schedule change control system
  • Performance measurement
  • Variance analysis
  • Project management software
  • Schedule comparison charts

14
Chapter 10 Monitoring and Controlling Change
  • Managing Integrated Change Control
  • Managing Cost Changes
  • Monitoring and Controlling Schedule Changes
  • Monitoring and Controlling Risk

15
Monitoring and Controlling Risk
  • Risk Monitoring and Control tools and techniques
  • Risk reassessment
  • Risk audits
  • Variance and trend analysis
  • Technical performance measurement
  • Reserve analysis
  • Status meetings

16
Monitoring and Controlling Risk
  • Risk Monitoring and Control outputs
  • Risk register updates
  • Requested changes
  • Recommended corrective actions
  • Recommended preventive actions
  • Organizational process asset updates
  • Project management plan updates