Title: DG: Mid Term Review 2006 December


1
Progress Report Business Plan / Strategic Plan
2009 10
Select Committee 5th May 2010
Overall Responsibility Director General Mr J
Manyi
2
Progress Report as of 31st December 2009
2
ITEM TOPIC
1. 2. 3. 4. 5. The DoL Strategic thrust geared for service delivery Programmes / Branches of the DoL Key Result Areas of the DoL (KRAS) - Targets Progress Constraints Corrective Measures Financial Performance Challenges of the Department Assistance by the Select Committee

3
The Core Functions of DoL
3
  • Employment Services (ES) and
  • Inspection and Enforcement Services (IES)

4
Programmes / Branches of the DoL
4
  • Programme 1 Administration
  • Chief Operations Officer
  • Internal Audit
  • Risk Management
  • Security Services
  • Communication
  • Human Resources Management
  • Information Technology
  • Legal Services
  • Chief Financial Officer
  • - Financial Management
  • - Financial Liaison Public Entities
  • - Office Administration and Supply Chain
    Management
  • Programme 2 Inspection and Enforcement Service
    (IES)

5
DoL Strategic / Business Plan 2009/10
5
  • Key aspects of the DoLs Strategic Plan /
    Business Plan 2009/10
  • Targets
  • Performance against key targets
  • Failure to achieve targets (constraints) and
    the reasons
  • Corrective Action

6
KRA 1 Contribute to Employment Creation 6
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators as of the 31st Dec 09 IMPL. BRANCH STATUS
1. 6 500 permanent jobs registered on the Public Employment Services (PES) Database. (See Annexure 1 for PES breakdown per Province Report attached) 6 123 formal/ permanent jobs were registered on ESSA. 21 074 short term job opportunities were registered on ESSA. 1 904 learning opportunities were registered on the ESSA database Public Employment Services (PES)
7
KRA 1 Contribute to Employment Creation 7
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
2. At least 65 of employment opportunities on the database are filled within 90 days. 6 845 registered job opportunities were filled within 90 days. 41 210 unemployed people were provided with careers information. 5 937 job seekers assessed. 13 082 job seekers were counseled. 18 self help career counselling information brochures were printed and distributed. PES
8
KRA 1 Contribute to Employment Creation 8
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
2. Employment opportunities on the database are filled through partnerships Partnerships developed with the Bombela Municipality is yielding positive results for the unemployed people in the Mpumalanga area. Partnerships developed with Sasol resulted in the latter using DoL database to recruit for all their staff requirements. Partnerships is being extended to their big Sasol plant in the Free State. PES
9
KRA 1 Contribute to Employment Creation
9
  • Public Employment Services (PES)
  • Constraints
  • ESSA system was not fully functional and the
    economic recession
  • impacted on the number of opportunities
    referred to DoL.
  • 45 Employment Services counsellors employed to
    service only 45
  • labour centres out of a total of 125.
  • Corrective Action
  • Optimised ESSA System went live as from 23
    March 2010.
  • The DoL will increase networking with
    Government Departments and
  • the Private sector to use DoL ESSA.

10
KRA 1 Contribute to Employment Creation 10
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
3. Draft Public Employment Services Policy and Bill finalized by March 2010. Draft Bill has been developed. PES Organogram for HO component approved. PES
11
KRA 1 Contribute to Employment Creation 11
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
4. Response to the economic crisis through the training of the layoffs R2,4 billion (R1.2 billion NSF R1.2 billion UIF) Training Lay Off Scheme assists companies willing to participate in alternatives training schemes instead of retrenching workers. By end March 2010 companies, along with the associated trade unions, entailing approximately 3,286 workers were participating in the scheme. The CCMA has, through its interventions, saved 16 530 jobs in the period January 2009 to 31 March 2010. PES
12
KRA 1 Contribute to Employment Creation
12
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
4. Response to the economic crisis A pilot project involving 740 retrenched and unemployed learners at a cost of about R50 million is currently underway in Gauteng. The project aims to test how best the UIF and NSF can facilitate re-entry into employment. The pilot project will be evaluated and depending on its success rate, it may be rolled out to other Provinces. PES
13
KRA 1 Contribute to Employment Creation
13
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
4. Response to the economic crisis An amount of R29 million was allocated to Productivity SA under the NSF towards the entities Social Plan programme to develop turn around strategies to companies facing possible closures due to tough competition or economic crisis. 138 future forums were established 9 826 jobs impacted upon 82 strategies developed 161 proactive future forums established 91 early warning systems established and 8 desktop research conducted on sectors. PES
14
KRA 1 Contribute to Employment Creation
14
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
4. Save jobs through strategic investments The Department has set aside under the UIF an amount of R2 billion for investment with the Industrial Development Co-operation (IDC). The IDC will in turn invest in industries that are willing to save jobs or to invest in new job creation ventures. UIF
15
KRA 1 Contribute to Employment Creation
15
  • Constraints
  • Slow uptake - retrenchment packages preferred.
  • Employers not willing to provide detailed
    information confirming their
  • distress status to the CCMA.
  • Insufficient marketing of the Training Layoff
    Scheme (TLS).
  • Corrective Action
  • Improved marketing of the TLS scheme.
  • Address identified challenges with NEDLAC
    social partners.
  • Review or add categories of companies and
    workers to be assisted.

16
KRA 2 promote Equity in the Labour Market
16
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Amendment Bill on EEA finalised by 31 March 2010. Follow-ups conducted on 60 JSE listed companies DG Reviewed by 31 March 2010 The Bill is being finalised for approval. 67 companies have been reviewed. Copies of DG signed letters were sent to the CEOs of 67 companies approving their respective EE Plans. LP LMP
17
KRA 4 Protecting vulnerable workers 17
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Monthly Blitz Inspections conducted Enforce compliance with all labour legislation to 75 of inspected workplaces by 2011/12 (See Annexure 2 and 2.1 for breakdown per province) 122 459 work places inspected and 80 compliance levels were recorded. SD (IES)
18
KRA 4 Protecting vulnerable workers 18
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Conduct focused advocacy in inspections and enforcement in the Hospitality and Security sectors. Each Province to identify companies and conduct inspections in these sectors for focused inspections as follows Hospitality 30 Security 20 (See Annexure 2 and 2.1 for breakdown per province) 3 741 work places were inspected in the hospitality sector with 44 compliance levels recorded. 1 560 work places were inspected in the security sector (717 did not comply with the sectoral determination). SD (IES)
19
KRA 4 Protecting vulnerable workers
19
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Enhance the visibility of the Inspectorate through improved corporate image. The procurement of the Green cars has been finalized, cars have already been serviced and are being branded. Uniform for the inspectors have been procured from the Sheltered Employment Factories. SD (IES)
20
KRA 4 Protecting vulnerable workers
20
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Submit an options paper on regulation of labour brokers to the Minister of Labour and Table paper at NEDLAC A concept paper on labour broking was tabled at NEDLAC for discussion. 3 Task Team meetings were attended to discuss labour broking. There were areas of agreement and disagreement. Draft legal amendments on labour broking are being finalised. LP LMP
21
KRA 4 Protecting vulnerable workers
21
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Draft Bills on LRA BCEA released for public comment LRA and BCEA Bills are being finalised. LP LMP
22
Strengthen Institutional Capacity of
DoL 22
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Develop an internationally benchmarked DoL organisational design through the ILO Technical Assistance The ILO after receiving the Technical report and this led to the following outcomes The DoL Service Delivery Model and the management structure at HQ with the key functional areas of labour administration systems, benchmarked with ILO standards and international best practice. Clarifying the organisation and role of IES and designing the IES Branch structure at HQ. Clarifying the organisation and role of PES and designing the PES Branch structure at HQ. Clarifying the organisation and role of LP LMP at HQ. Creation of the office of the COO. SD (IES)
23
Strengthen Institutional Capacity of
DoL 23
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Finalise the transfer of Skills Development to Higher Education and Training Establish one Gauteng Provincial Office Reduce audit queries and improve corporate governance The transfer has been finalised. Minister has approved the consolidated provincial office. Cannot be measured at this point Only one interim report from the AG for HQ released so far. Interim report from the AG, for all the provinces still outstanding. A clear picture of the audit queries will emerged once full report is released. Admin CFO
24
Strengthen Institutional Capacity of DoL
24
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Reduce the vacancy rate As of 26 March 2010 the PERSAL report reflect about 14 vacancy rate after taking out the vacant posts transfer to DHET. (Vacancy rate includes posts that are in process of being filled). As of 26 March 2010 vacancy rate reduced to 6.76 compared to 15.94 on the 30 September 2009. (The 6.76 vacancy rate excludes posts that are in process of being filled). A significant number of these positions will be filled as new incumbents assume duty on the 1st April 2010. Admin
25
Strengthen Institutional Capacity of DoL
25
Q4 TARGET PERFORMANCE MEASURES IMPL. BRANCH STATUS
Q4 TARGET Q3 Indicators IMPL. BRANCH STATUS
Improve the management of the IT PPP Contract with Siemens Identify and document all outstanding items as agreed in the PPP and agree on an implementation plan to finalise these within the contract period Plans are in place to accelerate delivery of improvement systems and DDGs are championing the implementation of the plans. Admin
26
Expenditure 31 MARCH 2010
26
  • Adjusted Budget 2009/10
  • Main divisions of the vote( Including ESDS
    HRD) 2009/10 Outcome.
  • Main divisions of the vote( Excluding ESDS
    HRD) 2009/10 Outcome
  • Spending Pressures
  • Percentage variance and reasons
  • DoL Medium Term Budget

27
Adjusted Budget 2009/10
27
28
Main divisions of the vote (Including ESDS
HRD) 28 2009/10 Outcome
29
Main divisions of the vote (Excluding ESDS
HRD) 29 2009/10 Outcome
30
Spending
Pressures 30
  • The following amounts have been vired to
    institutions
  • associated with the DoL
  • R62 million to the Commission for Conciliation
  • Mediation and Arbitration (CCMA).
  • R17.9 million to the SEF.
  • R5 million to NEDLAC.

31
Economic classification( Including ESDS
HRD) 31 2009/10 Outcome
32
2009/10 Outcome
32
  • Current payment
  • Slow process on filling of vacancies lead to slow
    spending in Compensation of Employees.
  • Amount invoiced by DPW on Rental and Leases
    exceeded what was originally budgeted.
  • Transfers and subsidies
  • Claims for injuries on duty for civil servants
    less than anticipated.
  • Unexpected severance packages taken by officials
    that could not have been foreseen during the 2009
    ENE process lead to over expenditure.
  • Capital payments
  • Delays have been experienced with regard to
    Capital projects on office buildings for Labour
    Centres.
  • NB Under expenditure amounting to R16,3 million
    from Programme 3 ESDS/HRD was
  • granted a blanket roll-over to the Department of
    Higher Education and Training as start
  • up capital.

33
DoL MEDIUM TERM BUDGET
33
34
  • Key challenges facing the DoL
  • How are these being addressed

35
CHALLENGES
35
  • 1. Distinct economy patterns One is advanced
    and industrialised and well developed with highly
    skilled people, the other is characterised by
    high levels of poverty, poor labour standards and
    informal work relations.
  • 2. High levels of unemployment Two-fold
    crisis
  • Unskilled most likely to loose jobs during
    periods of employment contraction and least
    likely to be hired.
  • The youth which constitutes 75 of the
    unemployed.
  • 3. Inequalities and unfair discrimination in the
    work place despite the introduction of
    progressive labour market policies since 1994.
  • 4. Changing nature of work to atypical forms of
    employment such as casual labour, temporary and
    seasonal work, labour broking, outsourcing and
    subcontracting.
  • 5. Domestic and cross border migration
  • People from rural areas (mostly unskilled)
    migrate to urban areas in search of employment.
  • Economic refugees settled in South Africa hoping
    to find employment.

36
CHALLENGES
36
  • 6. The requirement of very specific skills
    for redress Insufficient integration between
  • supply and demand of skills is adding to
    a large number of unemployed graduates.
  • 7. Strengthening labour market institutions
    and agencies
  • Compliance monitoring and enforcement structures
    (Labour Inspectorate Services, CCMA and
    Bargaining Councils).
  • Increasing our capacity to carry out our mandate.
  • Ensuring efficient and effective system of OHS
    fully integrated with a system of compensation
    for occupational injuries and diseases.
  • Non- compliance breeds unfair competition.
  • Interventions to mitigate new forms of
    vulnerability mainly through atypical forms of
    work.
  • 8. Development and implementation of
    effective instruments for constant performance
  • monitoring and review of the impact of
    labour market policies.

37
Strategic Plan/Business Plan 2010/11
37
  • Measurable Objectives (Key Targets) for 2010/11
    as reflected in our strategic plan 2010 - 2015

38
Inspection and Enforcement Services (IES)
38
  • Measureable objectives
  • Ensure decent work principles are adhered to by
    enforcing compliance with labour legislation by
    employers and employees by 2011, through regular
    inspections.
  • Achieve a reduction in the socio economic cost of
    workplace injuries and diseases incidents by
    2010/11 through regular audit and inspections to
    ensure the health and safety of workers.
  • Improve compliance with all labour legislation
    related to the protection of vulnerable workers
    in targeted sectors, including small, medium and
    micro enterprises, through targeted campaigns and
    regular inspections.

39
Inspection and Enforcement Services (IES)
39
  • Measureable objectives (Cont)
  • Ensure transformation of the labour market by
    achieving compliance with the Employment Equity
    Act (1998) by 2010/11 through awareness raising
    and regular inspections and audits.
  • Reduce silicosis by completing the baseline study
    on the prevalence of silicosis in the non-mining
    sector by April 2010.
  • Reduce exposure to silica by 20 by 2014 by
  • Establishing provincial silicosis working groups
    to conduct awareness raising road shows on the
    dangers of silica dust.
  • Assisting companies to develop programmes for the
    control of exposure to silica dust.
  • Conducting regular inspections.
  • Complete baseline study on prevalence of
    silicosis in non-mining sectors.

40
Inspection and Enforcement Services (IES)
40
  • Measureable objectives (cont)
  • Reduce noise related injuries by reducing
    exposure to noise at the workplace by 20 by 2014
    through the use of baseline study, inspections
    and awareness campaigns.
  • Reduce workplace injuries by at least 2 by
  • Identify 20 major high risk sector companies for
    full compliance auditing in 2010/11.
  • Improving compliance in the high risk sectors by
    80 by 2014 by conducting inspections.

41
Public Employment Services (PES)
41
  • Measureable objectives
  • Facilitate the entry and re-entry of job seekers
    into the labour market through pro-active
    measures to address unemployment and poverty by
    finalising the Public Employment Services Policy
    and the Employment Services Bill by September
    2010.
  • Reduce unemployment by placing unemployed people
    in decent work through
  • Filling at least 60 opportunities on the public
    employment services database within 30 days of
    registration of job opportunities on the system
    by 2011/12.
  • Referring at least 70 of unemployed people
    registered on the public employment services
    database to career counselling, training or
    workplace opportunities or sheltered employment
    factories, Unemployment Insurance Fund and the
    Compensation Fund within 30 days by 2011/12.

42
Public Employment Services
(PES) 42
  • Measureable objectives (cont)
  • Assist in reducing unemployment by providing
    employment services interventions to distressed
    companies within 5 days of receiving
    notification.
  • Facilitate the employment of 500 people with
    disabilities and/or veterans by persuading so
    that at least 30 of government department orders
    are purchased from service products (sheltered
    employment factories) by the end of March 2011.
  • Facilitate the achievement of employment equity
    target for disability by businesses by
    establishing a pilot to train and place at least
    50 learners per shelter employment factory in the
    mainstream economy by the end of March 2011.

43
Labour Policy and Labour Market
Programmes 43
  • Measureable objectives
  • Improve the status of vulnerable workers by
  • Reviewing the working conditions of 3 industrial
    and economic sectors, (civil engineering,
    hospitality, and contract cleaning), learnership
    and the ministerial determination on conditions
    of employment for employees in expanded public
    works programmes by March 2011.
  • Establishing the feasibility of promulgating
    sectoral determinations in the unskilled labour
    and welfare sectors by March 2011.
  • Developing a report on the norms and bench marks
    for proportionate income differentials by March
    2011.

44
Labour Policy and Labour Market
Programmes 44
  • Measureable objectives (cont)
  • Address developments in the labour market,
    including labour broking and legislative
    compliance and enforcement, by publishing
    amendment bills to the labour relations act
    (1995), the basic conditions of employment act
    (1997) and the employment equity act (1998) by
    March 2011.
  • Strengthen employment equity implementation and
    enforcement mechanisms by conducting a
    director-general review at 60 JSE security
    exchange listed companies by March 2011.

45
Labour Policy and Labour Market
Programmes 45
  • Measureable objectives (cont)
  • Create decent work and sustainable livelihoods by
    developing and implementing a research,
    monitoring and evaluation agenda, which includes
    providing labour market information and
    statistical analysis and facilitating compliance
    with international obligations and multilateral
    and bi-lateral relations by March 2011.
  • Manage the implementation of the LRA (1995) by
    extending collective agreements and registering
    or de-registering labour organisations within 90
    days.

46
  • Assistance to the DoL by the Select
  • Committee on Labour and Public Enterprise

47
Assistance by the Select Committee
47
  • Inputs on how the DoL can improve service
    delivery, particularly in the provinces.
  • Ensure parliamentary constituency offices liaise
    and form partnerships with DoL provincial,
    regional offices and Labour Centres in the
    various provinces.
  • The DoL encourages site visits to its development
    projects in the various provinces.
  • The Committee should invite the DoL officials in
    their community outreach initiatives for
    effective partnership in service delivery
    improvement.
  • Regular feedback from the Committee regarding
    service delivery issues that affect the DoL in
    the provinces.
  • Orientation of the Select Committee on the
    reconfigured DoL.

48
Thank you