Title: Proposal for Renovation Project b. 151
1EL-TC 27.4.2005
- Proposal for Renovation Project b. 151
1. Overview 2. Photos of old installation 3.
Outline of new project 4. Budget 5. Conclusions
K. KAHLE, TS-EL
21. Project Overview
b. 151
PS Test (2006)
ME6
3 MeV (2006)
LEIR (2005)
LINAC 4 (2008)
b. 152
b. 150
31. Overview
- Hall 151
- Test of PS magnets
- Test of RF equipment
42. Old installation
EBD13SHC - obsolete
52. Old installation
EBD11SHC - obsolete
62. Old installation
EBD30 and EBD31SHC - obsolete
72. Old installation
Disconnected OIL CABLE in the cable duct
82. Old installation
Old switchboard, disconnected
92. Old installation
Spaghetti Bolognese
102. Old installation
The purple snake
112. Old installation
Socket box - obsolete
123. Outline of new project
- dismantle obsolete switchboards
- (ERD30SHC, ERD31SHC, EBD11SHC, EBD13SHC,
EBD14SHC) - NEW one single switchboard 1000A (type EBD)
- existing incoming cables remain (200m x 11 PVC
240 Cu from b.264) - this would free feeders from s/st ME6
- OPTION
- one large switchboard ERD one switchboard EBD
for Gen. Serv. - clean all cable ducts, dismantle unused cables
- replace all outgoing cables from the new
switchboard - remove all oil cables in the zone
134. Budget
Work kCHF
Dismantling of old switchboards 10
New single switchboard EBD, incl. installation 30
Support structure for new switchboard or false floor 7
Dismantling of oil cables 20
Dismantling of old and unused cables in the cable ducts 10
Adaptation of 11 incoming feeder cables (extensions, joints, terminations) 5
New cabling (outgoing feeders) 18
New cable ladders, where necessary 3
Documentation 5
Contingency for bad surprises (will certainly be needed!) 10
Total 118
145. Conclusion
- Project is necessary Safety Reasons
- Project Duration 6 months
- no manpower available
- Project is defined now
- START depending on available manpower budget
15Questions ?
Thank you.