Project and Change Management - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

Project and Change Management

Description:

Project and Change Management Cost management What is Cost and Project Cost Management? Cost is a resource sacrificed or foregone to achieve a specific objective or ... – PowerPoint PPT presentation

Number of Views:107
Avg rating:3.0/5.0
Slides: 58
Provided by: colm158
Category:

less

Transcript and Presenter's Notes

Title: Project and Change Management


1
Project and Change Management
  • Cost management

2
What is Cost and Project Cost Management?
  • Cost is a resource sacrificed or foregone to
    achieve a specific objective or something given
    up in exchange
  • Costs are usually measured in monetary units like
    euros
  • Project cost management includes the processes
    required to ensure that the project is completed
    within an approved budget

3
Cost Management Definition
  • Is the controlling of costs as they apply to the
    project. It includes the estimation of costs,
    cash flows, direct and indirect costs and costs
    associated with the project life cycle

4
Basic Principles of Cost Management
  • Most CEOs and boards know a lot more about
    finance than IT, so IT project managers must
    speak their language
  • Profits are revenues minus expenses
  • Life cycle costing is estimating the cost of a
    project plus the maintenance costs of the
    products it produces
  • Cash flow analysis is determining the estimated
    annual costs and benefits for a project
  • Benefits and costs can be tangible or intangible,
    direct or indirect
  • Sunk cost should not be a criteria in project
    selection

5
Cost Management Overview
  • Resource planning
  • Resource planning involves determining and
    quantifying the resources needed to perform
    project activities
  • Cost estimating
  • Assembles and predicts the cost of a project
  • Cost Budgeting
  • Establishes budgets, standards and a monitoring
    system to measure and manage project costs
  • Cost controls
  • Gathers analyses, reports and manages project
    costs

6
Resource planning
  • People
  • Equipment
  • Materials

7
Resource Planning- Identify the knowledge and
skill requirements
  • Review the WBS, activities list, and network
    diagram to understand the nature and extent of
    the work
  • Identify the types of knowledge and skills
    required
  • Estimate the number of people required to perform
    the work
  • Decide when different people will be needed and
    create a time-phased human resource plan

8
Identify equipment and material requirements
  • Identify the types and quantities of equipment
    that will be required
  • Estimate non-tangible equipment needs such as
    time required on specialised computers or test
    equipment
  • Estimate the types and quantities of materials
    that will be required
  • Estimate when equipment will be needed and create
    a time-phase resource plan

9
Describe the resource pool
  • Consult with the relevant functional managers to
    identify what resources can be made available to
    the project
  • Identify the names and dates of available people

10
Define resource alternatives and trade-offs
  • Creatively identify alternative approaches to
    getting the work done that do not require the use
    of constrained resources
  • Identify how available resources should be
    deployed differently to accomplish project
    resources
  • Evaluate the possibility of using outside sellers
    or contracting out entire deliverables or
    activities
  • When the use of alternative approaches is not
    satisfactory, identify potential trade-offs that
    can be made, including hiring new staff, reducing
    the project scope or delaying the schedule
  • Review critical resource concerns with the
    project sponsor to get input and advice

11
Types of cost estimating
  • Order of magnitude estimate (-25 to 75 )
  • Normally used during formative stages for initial
    evaluation of the project
  • Budget estimate (-10 to 25 )
  • Prepared from flow sheets, layouts and equipment
    details. Used to prepare funding and obtain
    project approval
  • Definitive estimate (-5 to 10 )
  • Well defined information specs etc. normally used
    fro proposals, bid evaluations, contract changes
    and extra works

12
Estimating Methods
  • Top down
  • Relate to cost of projects which are similar in
    fact and not just in appearance
  • Parametric
  • Use parameter such as cost per m2, line of code
  • Bottom Up
  • Break into little tasks
  • Standards
  • Estimate the job components using standard cost
    and times
  • Ratios
  • Get minor items cost and time by ratioing them
    to major items on previous projects

13
Estimating effort techniques
  • Historical approach how long has it taken for
    similar tasks/
  • Catalogue of time standards are there industrial
    engineering or other standards available?
  • Process mapping data while analysing work
    processes a length of time is usually assigned to
    each process element
  • PERT formula an algebraic formula

14
Estimating duration efficiency impact
  • Learning curve for a new task and/or an
    inexperienced team member
  • Meetings can consume 5 to 10 hours a week
  • Administrative tasks may take anywhere between 5
    and 30 hours per week
  • Team members may be working on other projects
  • Training and development time can account for 10
    days per year
  • Vacation time 20 days per year
  • Public holidays 10 days per year
  • Sick time 10 days per year
  • Paternal/maternity leave

15
Estimating duration efficiency impact
  • Unlikely that an efficiency rate greater than 75
    in a 40 hour week i.e. 30 hours would be
    planned for a person
  • If a task requires 80 hours of expended effort or
    time and a person will be working on the activity
    for approximately 30 hours per week use the
    following formula to convert expended time to
    duration
  • 80/30 2.6 weeks duration

16
Things to remember when estimating
  • Better estimates require better information
  • Never estimate alone
  • Approximately right v absolutely wrong
  • Use a consistent process
  • Overly optimistic ends in trouble
  • Must be combined with risk assessment
  • Changes are inevitable

17
Typical Problems with IT Cost Estimates
  • Developing an estimate for a large software
    project is a complex task requiring a significant
    amount of effort. Remember that estimates are
    done at various stages of the project
  • Many people doing estimates have little
    experience doing them. Try to provide training
    and mentoring
  • People have a bias toward underestimation.
    Review estimates and ask important questions to
    make sure estimates are not biased
  • Management wants a number for a bid, not a real
    estimate. Project managers must negotiate with
    project sponsors to create realistic cost
    estimates

18
Contingency allowance
  • Provides for unforseeable elements of cost within
    the defined project scope which we know will
    happen but which we cannot quantify
  • Example Rework is certain but we dont know how
    much
  • It is used to reduce the impact of missing cost
    and schedule objectives
  • It is not normally carried in the cost or
    schedule baseline

19
Contingency examples
  • False assumptions
  • Unavailability of resources when needed
  • Lack of competence in key individuals
  • Lack of timely info. For project performance
  • Disruption due to personal conflict or internal
    politics

20
Managerial reserves are for unknown unknowns
  • A reserve for situations that are impossible to
    predict
  • E.g. Natural disasters, political crises

21
Building the budget
  • Direct costs e.g. Labour and materials
  • Indirect costs overheads travel, accommodation
    etc.
  • Contingency safety net or profit. For known
    unknowns

22
Building The Budget Direct Costs Labour
Materials
23
Building The Budget Indirect Costs
24
Building the Budget Total
25
Techniques used to rank capital investments
  • NPV net present value
  • Payback period
  • Return on investment

26
NPV
  • The expected value of future cash flows of the
    investment are discounted at the cost of capital
    to the base year (present time) to obtain the
    present value of these flows
  • The initial cost of the investment is subtracted
    from the Present Value (PV) to obtain the net
    present value (NPV)
  • If the cost of the investment is spread over more
    than one year, future cost must also be
    discounted at the cost capital of the base year.

27
Present Value
  • A method of discounting future cash flows based
    on a minimum desired rate of return
  • PV FV/(1i)n
  • PV Present value
  • FV Future value
  • i interest rate
  • n number of periods
  • Projects with a positive NPV exceed the minimum
    rate of return
  • Projects with a negative NPV do not

28
Present Value once off expenditure
  • Example what is the PV of 2000 tw0 years from
    now at 12 per annum
  • FV 2000
  • N 2
  • I 12
  • PV 2000/(10.12)2 2000/1.2544 1594.39

29
Present value Annual Expenditure
  • Example what is the present value of an annual
    expenditure of 3000 over the next three years _at_
    14 per annum
  • PV 3000(0.877) 3000(0.769) 3000 (0.675)
    3000(2.321) 6936

30
Equipment purchase evaluation NPV calculation
  • Example Management is considering an equipment
    purchase which costs 20,000 and is expected to
    save 7500 per annum over three years should we
    proceed with the investment. Use 14 as the rate
  • NPV -20000 7500 (0.877 0.796 0.675)
  • NPV -20000 17407.5 - 2592.5
  • Since NPV is less than zero the purchase should
    be rejected

31
Payback Period
  • The payback period is the number of years needed
    to recover the initial cost of the investment
    from the future net cash flows resulting from the
    investment
  • Shorter payback periods are more attractive. A
    cut-off number of years is often used to select
    or reject projects
  • It may lead to the wrong decision as it ignores
    the time value of money
  • The payback period is popular because it is easy
    to calculate
  • Some organisations use it in conjunction with NPV
    method in this case NPV is used to indicates
    profitability while payback period is used as an
    indicator of risk

32
Return on investment (ROI)
  • Investment 100,000
  • Expected return on investment is 40,000 per
    annum for four years 160,000
  • ROI 160,000/100,000
  • 160

33
Investment returns without reference to time
value of money
Year Project A Project B Project C
0 - 1000 -1000 -1000
1 300 1500 525
2 300 250 525
3 300 250 525
4 300 250 525
5 1500 250 525
Total 1700 1500 1625
34
Investment Returns comparison of techniques
Ranking Method Project A Project B Project C
NPV 882.34 1084.06 990.16
Payback 3 yrs 4 mths 8 mths 2 years
35
Incorporating Risk
  • Often cant just look at the project with the
    shortest payback period need to incorporate risk
  • E.g.

Risk Event Project A Project B Project C
Unproven Technology 3 5 4
High Investment 3 5 3
Tight Delivery 3 5 3
Risk score 9 15 10
36
Cost Management is managed by the project manager
through
  • Gathering accumulating, analyzing, reporting and
    managing the cost on an ongoing-basis
  • Monitoring actual vs. budgets
  • Integrated cost/ schedule reporting
  • Contingency and change management
  • Corrective action
  • Variance analysis

37
Cost control - compliance
  • Review the guidelines and procedures for making
    changes to the cost baseline with the project
    team, as defined in the cost management plan and
    overall change management system
  • Require that all requests for cost baseline
    changes be formally managed
  • Review the rate of project expenditure to ensure
    that no unauthorized changes to the cost baseline
    take place

38
Cost control - changes
  • Identify the root cause of the change request
  • Prepare the benefits of making the change to the
    proposed increase in costs
  • Identify the implications of the cost change on
    the other elements of the project plan, including
    scope, time and quality
  • Assess the risks involved with making the change
  • Assess the direct impact on the customer if any
  • Discuss the implications of making the change
    with key project stakeholders, especially the
    project sponsor and upper management

39
Cost Control Monitor
  • Attempt to contain costs in other areas before
    authorizing increasing the baseline
  • Ensure the proposed action is properly authorized
    as defined in the cost management plan and change
    control system
  • Require feedback or formal status reporting on
    the change
  • Evaluate the actual versus planned costs after
    authorizing the change
  • Initiate further action as needed

40
Cost control documentation
  • Make changes to the cost baseline and spending
    plan
  • Use a consistent version control numbering system
    to identify each document update and effective
    date
  • Review the updated documents for completeness and
    distribute as needed to affected project
    stakeholders
  • Document the causes of cost variance, rationale
    for decisions along with other lessons learned
    from the change to become part of the project
    history file as reference for current and future
    projects

41
Why variances occur?
  • Estimating errors
  • Technical Problems design, software, test
  • Manpower problems personnel skill level,
    manpower availability, organisation matrix
  • Economic / inflation
  • Acts of nature
  • Changing business base
  • Subcontractors/ vendors

42
EV earned value
  • EV is the primary project management tool that
    integrates the technical, schedule and cost
    parameters of the contract

43
Acronyms and definitions
  • ACWP actual cost of work performed (AC)
  • BCWP Budgeted cost for work performed (BC)
  • BCWS Budgeted cost for work scheduled (PV)
  • CV Cost variance
  • SV Schedule variance
  • ETC Estimate to complete ( how much to finish)
  • EAC Estimate at completion (forecast final cost)
  • BAC Budget at completion (original or baseline
    budget)
  • PMB Performance measurement baseline
  • VAC Variance at completion ( baseline budget
    forecast)
  • MR Management reserves

44
Earned Value Analysis (EVA)
  • a.k.a. Earned Value Management (EVM)
  • a.k.a. Variance Analysis
  • Metric of project tracking
  • What you got for what you paid
  • Physical progress
  • Pre-EVA traditional approach
  • 1. Planned time and costs
  • 2. Actual time and costs
  • Progress compare planned vs. actual
  • EVA adds third dimension value
  • Planned, actual, earned

45
Earned Value Analysis
  • Forecasting
  • Old models include cost expenditure
  • EVA adds schedule estimation
  • Measured in dollars or hours
  • Often time used in software projects
  • Performance Measurement Baseline (PMB)
  • Time-phased budget plan against which contract
    performance is measured
  • Cost schedule variances go against this
  • Best via a bottom-up plan

46
Earned Value Analysis
  • Different methods are available
  • Binary Reporting
  • Others include
  • Based on complete
  • Weights applied to milestones
  • EVA can signal errors as early as 15 into
    project
  • Alphabet Soup

47
Earned Value Analysis
  • 3 major components
  • BCWS Budgeted Cost of Work Scheduled
  • Now called Planned Value (PV)
  • Yearned
  • How much work should be done?
  • BCWP Budgeted Cost of Work Performed
  • Now called earned value (EV)
  • Earned
  • How much work is done?
  • BCWS complete
  • ACWP Actual Cost of Work Performed
  • Now called Actual Cost (AC)
  • Burned
  • How much did the work done cost?

48
Derived EVA Variances
  • SV Schedule Variance
  • BCWP BCWS
  • Planned work vs. work completed
  • CV Cost Variance
  • BCWP ACWP
  • Budgeted costs vs. actual costs
  • Negatives are termed unfavorable
  • Can be plotted on spending curves
  • Cumulative cost (Y axis) vs. Time (X axis)
  • Typically in an S shape
  • What is the project status?
  • You can use variances to answer this

49
Earned Value Analysis
50
Derived EVA Ratios
  • SPI Schedule Performance Index
  • BCWP / BCWS
  • CPI Cost Performance Index
  • BCWP / ACWP
  • Problems in project if either of these less than
    1 (or 100)

51
Summary of variance formulae
  • CPI (cost performance index) BCWP/ACWP (EC/AC)
  • CV (cost variance) BCWP -ACWP
  • SPI (schedule performance index) BCWP/BCWS
  • SV (schedule variance) BCWP- BCWS
  • EAC ((BAC BCWP)/CPI) ACWP
  • VAC BAC EAC
  • Percent complete BCWP/BAC 100

52
Earned Value Analysis
  • BCWS
  • Use loaded labor rates if possible
  • Direct pay overhead
  • Remember its an aggregate figure
  • May hide where the problem lies
  • Beware of counterbalancing issues
  • Over in one area vs. under in another

53
Earned Value Analysis
  • Other Derived Values
  • BAC Budget At Completion
  • Sum of all budgets (BCWS). Your original budget.
  • EAC Estimate At Completion
  • Forecast total cost at completion
  • EAC ((BAC BCWP)/CPI) ACWP
  • Unfinished work divided by CPI added to sunk cost
  • If CPI lt 1, EAC will be gt BAC
  • CR Critical Ratio
  • SPI x CPI
  • 1 everything on track
  • gt .9 and lt 1.2 ok
  • Can be charted

54
Earned Value Analysis
  • Benefits
  • Consistent unit of measure for total progress
  • Consistent methodology
  • Across cost and completed activity
  • Apples and apples comparisons
  • Ability to forecast cost schedule
  • Can provide warnings early
  • Success factors
  • A full WBS is required (all scope)
  • Beware of GIGO Garbage-in, garbage-out

55
Earned value exercise
  • You have a project to build a four sided wall.
    Each side is scheduled to take one day and is
    budgeted for 2000 per side. The sides are
    planned to be completed one after the other.
    Today is the end of day three Calculate BCWS,
    BCWP etc from the following status chart. Key S
    start, F finish, PS- planned start, PF -
    planned finish

Task Day 1 Day 2 Day 3 Day 4 Status at the end of day 3
Side1 S-----F Complete spent 2000
Side 2 S---PF ---F Complete spent 2400
Side 3 PS-----PF Half done spent 1200
Side 4 PS--PF Not started
56
Solution
What is Calculation Answer Interpretation of the answer
BCWS 2000 2000 2000 6000 We should have done 6000 worth of work
BCWP Complete, complete half done or 2000 2000 1000 5000 We budgeted 5000 for the work we completed
ACWP 2000 2400 1200 5600 We actually spent 5600
BAC 2000 2000 2000 2000 8000 Our project budget is 8000
CV 5000 (5600) (-600) We are over budget by 600
CPI 5000/5600 0.893 We are only getting 89 cent out of every euro we put into the project
SV 5000 - 6000 (-1000) We are behind schedule
57
Solution
What is Calculation Answer Interpretation of the answer
SPI 5000/6000 0.833 We are only processing at 83 of the rate planned
EAC 8000/0.893 8959 We currently estimate that the total project will cost 8959
ETC 8959 - 5600 3359 We need to spend 3358 to finish the project
VAC 8000 - 8959 (-959) We currently expect to be 959 over budget when the project is complete