Title: Office of Project Management Metrics Report Presentation
1Office of Project ManagementMetrics Report
Presentation
- Phil Braun
- Project Management Consultant Alliant Energy
Office of Project Management
2Framework
- Metric Report is run at least monthly (some are
every two weeks) - Every project is assigned two dates and two
dollar amounts - Triangle Inner Finish date (based on Project
Schedule) and dollar amount are updated every two
weeks - Triangle Outer (Goals) Finish date and dollar
amount to include contingency (Determined in
Project Charter and Project Change Requests) - Comparing the current TI to the TO every
reporting period Remaining Contingency
3Metrics (continued)
- When completed, the final report will contain the
following worksheets in an Excel Workbook for
each project governed by OPM - Accomplishments
- Dashboard
- Vendor Scorecard
- Change Management Dashboard
- Metrics Report
- Task Graphs
- Project Performance Graphs
- Resource Allocation
- Resource Non-Working Time
- Triangle Benefit Summary
- Risk Matrix
- Issues Matrix
- Communications Matrix
- Training Matrix
- Decisions
- (Updates at least monthly)
4Accomplishments
- Following questions are answered by the Project
Manager in the Accomplishments page in the
project metrics report - Review Date
- Project Driver (Time, Cost, Scope)
- Overall Project Health (Completed by OPM using
Project Dashboard) - Executive Summary
- Key Decisions, Issues, and/or Risks
- Significant Accomplishments Since Last Meeting
- Major Work Planned Over Next Period
- Comments
- Follow up Items from previous meeting
- Outcome of Action Items from Previous Meeting
5Project Dashboard
- Used to communicate status of the project.
- Information taken from latest metric report and
put into Microsoft Excel - Dashboard is then made into .pdf file and placed
on Company Intranet - Data entered into input area that drives formulas
to calculate variances and determine overall
status color - All Projects are rolled up to Portfolio Dashboard
5
6Project Dashboard (continued)
6
7Project Dashboard (continued)
- Calculated Fields
- Time and Cost Contingency
- Color indicator based on matrix
7
8Project Dashboard (continued)
- Calculated Fields
- Average Task Completion Rate
8
9Project Dashboard (continued)
- Overall score calculation
- Every new project starts with a total of five (5)
points. - The resulting score determines the overall
project health indicator as follows GREEN equal
to or greater than 3.5 and up to 5 points YELLOW
equal to or greater than 2 and up to 3.4 points
RED equal to 0 and up to 1.9 points - If a project is projecting over budget or
late,then its Overall Health will be indicated as
RED.
9
10Project Dashboard (continued)
10
11Vendor Scorecard
- Vendor Scorecard is completed by the Project
Manager to track Vendor performance on a project.
The following data is tracked - Overall Vendor Performance
- Project Name
- Vendor Name (one report done for each vendor if
multiple vendors on project) - Type of Contract
- Contract Dollar Amount
- Purpose for Vendor
- Has this Vendor been used on a previous contract?
- Current Risk Score for Vendor portion of Risk
Matrix and Risk Level for Vendor - Questions on Vendor Performance
- Each section contains a comment area that can be
used if needed
12Vendor Scorecard Questions
- Resource (Red, Yellow, Green, N/A Answers)
- Is the vendor providing enough resources to get
the work done? - Are the vendor resources knowledgeable about the
product? - Is the vendor responsive to questions and
requests? - Is the vendor Project Manager performing
effectively? - Performance (Yes, No, or N/A Answers)
- Are deliverables being completed on time?
- Is the cost still in-line with the current
contract? - Is the vendor providing tasks that are essential
for project success and are they updating those
tasks on timely basis? - Is the vendor meeting quality expectations?
- Issues (Taken from Issues Log Automatically
calculates Red, Yellow or Green) - Customer Satisfaction (Yes, No, or N/A Answers)
- Meets commitments made to Stakeholders?
- Is the Project Manager satisfied with the vendor?
- Is the Project Team satisfied with the vendor?
- Escalation (Yes, No Answers)
- Have you had to escalate any issues to the
vendors management? - If yes, were the issues resolved as expected?
- Vendor Milestones (Green or Red based on if
Milestone is completed on time)
13Example of Vendor Scorecard(Page 1)
14Example of Vendor Scorecard(Page 2)
15Project Change Management Dashboard
16Metrics Report
- The metrics report is ran by using a macro that
exports a Microsoft Project schedule to a Crystal
Reporting engine that then exports the following
information to Microsoft Excel. - Metrics completed in categories
- Project Plan Summary
- Date Summary/Task Summary
- Tracking Milestones
- Cost Summary/ Completion Rate
- Miscellaneous
- Comments
- Audit Summary
- Metrics Summary
- Project Plan Audit
- Project Plan Metrics
17Metrics Report (continued)
18Metrics Report (continued)
19Metrics Report (continued)
- Tracking Milestones
- List of Milestones set by Project Manager
- Fields Tracked include the following
- Task Name
- Triangle Inner Date
- Triangle Outer Date
- Complete
- Difference in weeks
20Metrics Report (continued)
- Cost Summary/ Completion Rate
21Metrics Report (continued)
- Miscellaneous
- Scope Change Requests
- Approved changes to scope on the project
- PMPA Score
- Internal score used to gauge strength of schedule
- CSAT (Customer Satisfaction) Score
- Currently in progress to determine best way to
capture metric
22Metrics Report (continued)
- Comments
- Used to comment on changes that may need to be
made to schedule - Used to relay information regarding schedule and
metrics report
23Metrics Report (continued)
24Metrics Report (continued)
25Metrics Report (continued)
- Project Plan Audit
- Displays activities that are on the Critical Path
- Project Plan Metrics
- Displays following activities
- Tasks scheduled for completion by the current
status date - Tasks scheduled for completion by the current
status date and actually completed - Tasks scheduled for completion by the current
status date that were deleted - Late tasks
- Total tasks deleted
- Total tasks added
- Grand total of tasks completed since last status
date - Tasks scheduled to be completed during next
period
26Task Graphs
27Task Completion History Graphs
- Task Completion History Graphs
- Shows the Task completion rate by reporting period
28Forecasted Project Completion Date
- Calculates Approximate finish date based on tasks
being completed every reporting period - Uses trend lines for analysis
29Project Performance Graphs
30Time Cost Contingency
- Contingency is the difference between the
Triangle Inner Date/Cost and Triangle Outer
Date/Cost - Graph shows contingency history by reporting
period
31Percent Complete
32Time vs. Work
- Graph is created in Microsoft Project using
Analyze Timescaled Data in Excel Add in. - Graphs work to be completed over the length of
the project.
33Resource Allocation
34Resource Allocation
Shows Percent of Allocation by Week
Capacity (Includes Vacation and Holidays)
Resource Name
Shows all projects that resource is assigned to
Data is taken from Project Server 2007 Resource
Center and downloaded to Microsoft Excel. Macro
is then ran to format data and add color, format,
etc.
35Resource Non-Working Time
- Resource Enters Non-Working time into Microsoft
Outlook Add-In - Time is placed in MS Outlook calendar and also
placed into MS Project Server - Resource Calendar impacts project schedule
- Report allows PM to see scheduled time off for
team
36Triangle and Benefit Summary
- Triangle Outer and Triangle Inner information
- Cost broken out by year and summed
- Scope Must have and nice to have
- Explanation of benefits
37Matrix Types
- Risk Matrix
- Updated weekly
- Projects categorized as High, Medium or Low risk
- Following categories are used
- Technical, Quality Performance
- Project Management
- Organizational
- Vendor
- Other External
Header of Risk Matrix
38Matrix Types (continued)
- Issues Matrix
- Used to track issues on the project
Header of Issue Matrix
- Communications Matrix
- Used to track needed communications relevant to
project
Header of Communications Matrix
39Matrix Types (continued)
- Decision Matrix
- Used to track decisions made by project team or
decisions that affect the project
Header of Decision Matrix
- Training Matrix
- Used to track training needs for the project
- Each project can develop and maintain their own
training plan
40Portfolio Dashboard
Legend
41Examples
- Examples of metrics reports are available as a
hard copy here today - If you are interested in receiving a soft copy
please email philipbraun_at_alliantenergy.com