Title: Planning and Scheduling Highway Construction
1 King Fahd University of Petroleum Minerals
LIFE CYCLE COSTING
Appling The UK Manufacturing Industries
Experience of Value Analysis Into Construction
D
r
ARE-512
Presented by MUBARAK ALQAHTANI
I.D. 969260
SAADI ASSAF
January 12, 2008
2- Abstract
- Value Analysis is concerned with the
identification of best value. Too often its
associated techniques are applied to new
situations without consideration of its
underlying philosophy. - There has been a fall off in the formal
application of Value Analysis within UK
Manufacturing Industries. - The principles are however still claimed to be
accepted. Value Opportunities exist within the UK
Construction Industry but Value Analysis is not
practiced. - Can the experience of the UK Manufacturing
Industries' informal commitment to Value Analysis
be applied to the UK Construction Industry in
order to gain acceptance of the Value Ethos.
Keywords Value Analysis, Quantity Surveying,
Procurement Procedures .
3Outline
- Introduction
- The Development of Value Analysis
- Opportunities for Value Analysis in Construction
- Experience in UK Manufacturing Industries
- Applying the Experience of the UK Manufacturing
Industries to the Construction Industry - Current Reflections of Value Analysis in the UK
Construction Industry - Conclusion
4Introduction
- "Value Analysis is an organized effort to obtain
optimum value in a product, system or service by
providing the necessary function at the lowest
cost".
5"Value Analysis is an organized effort to obtain
optimum value in a product, system or service by
providing the necessary function at the lowest
cost".
- Value analysis is an example of an identifiable
subject area. It however comprises previously
established techniques, discipline and ideas.
Value Analysis derives its uniqueness from the
way in which the component elements are combined.
Similarly the established subject of Value
Analysis assumes further 'newness' when it is
applied in a discipline other than the one for
which it was originally developed.
6Introduction
- "Value may be defined as the relationship between
function and cost. In all cases value is greatest
when the cost of obtaining a required function or
service, at a particular time and place with the
essential qualities, is at a minimum. "
7LOWEST COST REQUIRED PERFDRMANCE (OPTIMUM PERFORMANCE).
Total cost
Figure 1 Cost and Value in Relation to Performance
8- The Development of Value Analysis
- L D Miles(l) is recognized as the 'Father of
Value Analysis'. - He originally conceived the idea some 50 years
ago when, while working as a design engineer with
General Electric, he was surprised by the
apparent lack of consideration given to cost. The
advent of World War 11 put great pressures on
resources.
9- Value Analysis is concerned with the search for
best value To achieve this it must be more than
just a cost control technique as cost can not be
reduced at the expense of performance. - Value Analysis may use many varied techniques,
some of which are more traditionally associated
with cost control, e.g. Life Cycle Costing and
Cost in Use Analysis, but the object is to
establish best value not just lowest cost. This
means that, unlike pure cost reduction, the
levels of qualify and performance are 'not
allowed to deteriorate. - This means that, unlike pure cost reduction, the
levels of qualify and performance are 'not
allowed to deteriorate.
10Opportunities for Value Analysis in Construction
- The objective of Value Analysis is to identify
and eliminate unnecessary cost. Such value
opportunities are not restricted to anyone part
of the life cycle of a building. Value Analysis
does however attempt to focus attention on those
areas where there is potential for the greatest
return on the effort exerted. Value Analysis
would be most profitably applied where the net
savings potential is greatest, as illustrated in
Figure 2.
11(No Transcript)
12A popular stage for applying Value Analysis is
during design which is an identifiable action
which offers large net saving potential.
Traditionally a design would be developed to In
developing a design through the application or
Value Analysis (possibly more properly termed
Value Engineering at this stage)
- Value Analysis recognizes. Aesthetic Value as one
of the needs to be addressed when balancing the
design equation and by developing a Value Index
(the ratio of the cost of the proposed design to
the lowest cost alternative) a more objective
evaluation can be made.
13- A second area popularly chosen for the
application of Value Anal sis is the construction
stage. As is evident from - The net savings potential is substantially
reduced by this stage. Contractors can conduct
Value Analysis exercises on their own operations
to increase efficiency. Part of these benefits
will be passed on to the building
14Experience in UK Manufacturing Industries
- Value Analysis was imported into the UK as a well
developed set of procedures. These procedures had
been developed in the US and were taken on board
by UK managers, tantalized by the apparent
potential for savings or because they were
directed by a multi-national parent company or
even to demonstrate their openness/acceptance for
change.
15- In order to gauge current practice regarding the
use of Value Analysis in the UK interviews were
conducted with 6 firms. These firms represent
heavy engineering, micro engineering, aerospace
and petro-chemicals. All the organizations had
formerly employed specialist Value Analysis
staff. All but one however considered that they
still had a commitment to the principles of Value
Analysis and utilized techniques associated with
Value Analysis. In two of the organizations all
products are subject to review by an independent
group, either during the design stages or at
prototype stage. Although neither firm currently
had Value Analysis staff they both considered
that their staff were sufficiently familiar with
the techniques to ensure that the original design
work and the review embraced the value principle.
16Applying the Experience of the UK Manufacturing
Industries to the Construction Industry
- The early involvement of producers or production
departments is seen as a valuable means of
reducing production costs. In the Traditional UK
procurement procedure the Architect completes the
detail design before the Contractor is selected
and there is no formal means for the Contractor
to contribute to the 'design. The procedure of
Management Contracting has been' developed with
the intention of securing the independent
contribution of a Contractor at the design stage.
17- At the other extreme from the Traditional
procedure, Design and Build places the Contractor
in full control of the design possibly excluding
an independent Architect. Where size or cost
precludes the use of Management Contracting and
the project requires greater Architectural
control than is possible through Design and
Build, the Traditional procedure could be
modified to more fully embrace Performance
Specifications. This would reflect Value Analysis
in that the function is defined in the
performance specification, alternative solutions
are developed by the competing contractors and if
contractor selection is based on cost the lowest
cost, solution is identified. _
18Current Reflections of Value Analysis in the UK
Construction Industry
- The foregoing illustrates how Value Analysis
might be applied within the construction
industry. - The following are two initiatives which introduce
Value Analysis into UK construction
19first is a procurement procedure which
incorporates features of US procedures.
- second is in the Public Works Department of Local
Government where Value
20- Analysis is to be directly applied as part of a
rat1onalisation programmed. British Property
Federation considered that the performance of the
construction industry in the UK compared - unfavorably with other countries. In order to
overcome the e shortcomings they developed their
System for Building Design and Construction (6)
This broke considerably with traditional UK
procedures. Certain aspects can be seen as
reflecting Value Analysis procedures.
21- The client is required to take greater
responsibility especially at the early stages
when a fully considered brief is to be prepared
(functional. analysis). The Architect is required
to develop the design - to the level which requires Architectural control
allowing the Contractor to develop the 'detail'
design - (This allows a variety of technical solutions
to be developed, by the contractors, for the
outstanding features).
22Conclusion
- Value Analysis has not had continuing support
within the UK - manufacturing industries. In formal Value
Analysis terms its use has encountered
'roadblocks' which should be overcome.
23- The principles and some techniques however linger
on " at a level which is apparently
satisfactory to the users and the situations in
which they find themselves. Should this be the
'experience' that the construction industry gains
from the manufacturing industry?
24- Critics of Value Analysis applied in construction
have looked at techniques such as brainstorming,
multi-criteria diagramming and numerical
weighting of factors and have dismissed them as
impractical or inappropriate in the construction
industry. If we look beyond the techniques back
to the origins of Value Analysis the basic
motivation is appropriate to construction, that
is to reduce cost through the development of
alternative solutions.
25- The problems of the construction industry can be
held to be different from other industries. There
is a one-off product required to satisfy
multiple-criteria which is produced by a unique
grouping of personnel. The parties involved may
have conflicting interests and the traditional
approach fosters such divisions by requiring each
party to defend their actions thus resulting in
sub-optimization of the total project .
26- Value Analysis is concerned with the evaluation
of function, cost and worth which can provide a
unifying vehicle, directing effort to the mutual
benefit of all parties and the total project.
Further study is required to identify how best to
apply Value Analysis to the UK construction
situation in order to achieve acceptance of the
procedures.
27Thank you Any ?