Value Engineering Study and Risk Assessment - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Value Engineering Study and Risk Assessment

Description:

1. Value Engineering Study and Risk Assessment. Highway 7 New ... Highway 7 is a congested 2-lane. highway (AADT 21,000 - 32,000) Planning study ... resubmitted ... – PowerPoint PPT presentation

Number of Views:351
Avg rating:3.0/5.0
Slides: 22
Provided by: mmm63
Category:

less

Transcript and Presenter's Notes

Title: Value Engineering Study and Risk Assessment


1
Value Engineering Study and Risk Assessment
Highway 7 New - Kitchener to Guelph
2
Presentation Outline
  • Project Background
  • Value Engineering and Cost Risk Analysis
  • Study Outcomes

3
Key Plan
4
Highway 7 Background
  • Highway 7 is a congested 2-lane
  • highway (AADT 21,000 - 32,000)
  • Planning study commenced in 1989
  • Individual EA submitted in 1997
  • EA resubmitted in 2002
  • Individual EA approval obtained in March 2007 for
    an 18 km long, 4-lane freeway, following a new
    alignment generally north of and parallel to
    existing Highway 7

5
Value Engineering Study
  • Largest single VE study ever undertaken by MTO
  • VE Team jointly lead by Marshall Macklin Monaghan
    (MMM Group) and iTrans
  • Additional members from FaithfulGould, MACTEC,
    Davis-Langdon, WCS, Thurber, Human Factors North,
    HCi, and MTO
  • Site visit and information meeting was held April
    2007
  • Safety Audit of base case undertaken pre-study.
  • Value Engineering Study completed in Kitchener
    April 30 to May 4, 2007.
  • VE Team presentation to MTO Senior Management
    held May 15, 2007.
  • Focused 5 days on workshop. Split pre/post
    activities as concerned over maximizing time for
    workshop.

6
VE Scope
  • The EA approved alignment was assessed
  • The Study Team generated 212 ideas (of which 56
    were developed) in eight Target Areas and
    evaluated using seven Performance Measures

7
Value Target Areas
  • Team identified 8 Target Areas
  • Kitchener-Waterloo Freeway to Freeway Interchange
  • Grand River Bridge and Bridge Street
  • Regional Road 17 Interchange
  • Regional Road 30 Interchange
  • County Road 86 Interchange
  • Highway 6 Interchange
  • Sideroads
  • Mainline

8
Performance Measures
  • Team Developed 7 Performance Measures
  • Weight
  • Safety (collisions) 22
  • Human Factors (predictability, signs, geometry)
    17
  • Traffic Operations (v/c, weaving, queuing) 19
  • Access (interchange access, local road across)
    13
  • Sustainability (environmental, growth) 12
  • Constructability (staging complexity, resources,
    access) 8
  • Maintainability (structures, roadway
    cross-section) 8

9
VE Ideas
10
VE Scenarios
  • Of the 56 ideas evaluated in detail, 29 were
    developed into VE alternatives.
  • The VE Team grouped these alternatives into 5
    Scenarios based on function or impact.
  • Scenario 1 - Minimal Improvements
  • Scenario 2 - Minimal Improvements with various
    interchanges deferred
  • Scenario 3 - Moderate Improvements with
    Roundabouts
  • Scenario 4 - Moderate Improvements
  • Scenario 5 - Reduced Expenditure / Constrained
    Funding

11
VE Conclusions
  • Scenarios 1-5 had performance benefits over the
    base case.
  • 29 VE Proposals were used to develop numerous
    other scenarios.
  • 30 VE Design Suggestions were generated for
    consideration during preliminary and detail
    design.

12
Implementation Plan
  • VE team developed 29 individual alternatives and
    packaged them into an Implementation Plan to
    Senior Management.
  • Implementation of some alternatives are
    considered a substantive change to the approved
    EA.
  • It will be necessary to prepare an addendum to
    the TESR to document the changes and obtain
    environmental approval from MOE.
  • The alternatives from the VE Study that were
    recommended for implementation are currently
    being evaluated for performance and cost
    benefits.

13
Risk Assessment
  • No construction project is risk free. Risk can
    be managed, minimized, shared, transferred, or
    simply accepted, but it can not be ignored.
  • C.R.I. Clayton, 2001. Managing Risk

14
Cost Risk Analysis
  • Objectives
  • Review MTO concept base construction estimate
  • Incorporate latest property estimate
  • Review schedule
  • Identify constraints to schedule
  • Quantify risks as to likelihood of occurrence and
    impact in terms of and extended project
    duration
  • Discuss possible mitigation reduce, avoid and /
    or transfer risks

15
Process
  • Risk identification (completed concurrently with
    the VE Study)
  • Pre workshop Top Risk questionnaire issued to
    VE team
  • Risk analyst compiled draft risk register
  • Risk analyst built schedule and cost model base
    case working with VE / MTO team
  • Risk analyst identified constraints to schedule
    with VE team
  • Draft risk register circulated to VE team for
    confirmation / comments on risks identified
    risk register updated
  • Production of risk analysis, summary and report

16
Cost Risk Analysis
  • Greatest Risks to Projects Cost and Schedule
  • Grand River Bridge Issues
  • Material price volatility
  • Market forces/number of bidders
  • Escalation
  • Environmental Mitigation
  • Relocation of Utilities
  • Variability in earthwork quantities
  • Complex KWE structures

17
Project Schedule Constraints
  • Key Project Constraints identified as
  • In-water timing restrictions
  • Bird nesting season impacts tree clearance in
    wetlands
  • Winter work impacts paving and influences
    structure and earthworks construction
  • Wetlands clearance requires special protective
    measures and consultation
  • River crossings requires detailed consultation
    with First Nations
  • Funding Availability impacts phasing of project
  • Minimizing traffic impact during construction
  • Reducing Rail impact CN under-bridge
    construction

18
Top Risks from Risk Register
19
Top Risks from Risk Register
20
Study Outcomes - Where are we now?
  • Implementation Plan endorsed by MTO Sr. Mgmt.
  • 2 engineering assignments currently underway.
  • MMM Group developing VE recommendations within a
    Preliminary Design/Detail Design assignment.
  • Thurber Engineering undertaking a Foundation and
    Pavement Field investigation.
  • Property Request to be available in early 2009.

21
Study Benefits
  • New perspective on study
  • New PM had no ownership
  • Risk analysis (cost/schedule)
Write a Comment
User Comments (0)
About PowerShow.com