Title: Project Management An Introduction to Project Management
1- Project Management An Introduction to Project
Management
Supervisor eng. Baraq Jumaa Prepared byKhaled
Mohammad SawalhaSuha Tarek Awwad2011-2012
2- Graduating project consists of two parts
- The first part includes preparing a theoretical
research. - The second part includes the application of the
principles in construction project management
3What is a project?
- Project is the collection of activities, that are
related or connected, for developing a product or
a service - Characteristics of Projects
- Temporary
- Unique
- Projects have always a customer who uses the
results
4Project life cycle
5What is Project Management?
- Project Management is the application of skills,
knowledge, tools and techniques to meet the needs
and expectations of stakeholders for a project
6 Triple Project Management Constraints
7Brief Description Part
Two
- The project is a community police station located
in Arrabeh village / Jenin City . - The total area of 842.2 ms Consists of two floor
- Owner Ministry of Interior Affairs
- Supervision Ministry of Public Works Housing
- Donor Germany federation GIZ
8Brief Description cont.
- Tender implementing Duration 300 calendar days.
-
- Scheduled Duration 235 work days
- Commencement order 27- Feb- 2011
- Hand over Date 24-Dec-2011
- Bid cost 3,169,654 NIS
9Work breakdown structure
- The project is divided into activities in a
process called work breakdown structure. In this
project we breakdown it according to the type of
level in building, as the following
10Shows in the following Figure (WBS)
11Calculate the cost
12The bar chart
13The S-curve as shown
14Problem Case
- In the process of foundations establishment a
soil confirmation test is carried out to confirm
the bearing capacity of base strata as per design
bearing capacity (25ton/MS), the lab reports
provided the following - Pure Clay soil layer with variable depth (3-6 m)
- The bearing capacity equal (10ton/Ms)
- High swelling settlement conditions
15Problem Case cont.
- Depending on that soil report the contractor
asked the supervision representative to suspend
the works in the project consider the new facts
in site to redesign the foundation system. - According to the FIDIC 19998.8 Suspension of
Workand the previous condition the Supervision
decided to suspend the project progress to
redesign the foundation system
16Problem solution
- two different type that comply with such soil
conditions we suggested two alternatives
foundation systems - Pile System
- Raft system
17Comparison Sheet
Comparison Sheet
Amount NIS Description No.
356,535 Summary for Bid(single footing) 1
474,640 Summary for Raft 2
545,176 summary for pile 3
118,105 Difference between raft bid
18The modified bar chart
19 The result of the problem case
- Work was suspended for 45 days and recommencement
order was issued to the contractor followed with
a variation order for raft foundation
system and 63 day time extension. - As a result of that extension of time and
according to FIDIC 199920.1 Contractor's Claims
the contractor should be Compensated.
20The total financial claim as shown in the table
below
Summary of expenses
1,032 Nis Indirect cost / day
435 Nis Job over head cost/day
1,467 Nis Total cost / day
45 day Total no. of suspension days
66,015 Nis Expenses earned by the contractor as a result of the extension
21Summary
- Duration of the project has become in this case
298 working days - Total duration(235) (18)(45)298 day
- And the total cost become 3,343,774 NIS
- Total Cost (3,169,654) (118,105)(1,46745)
3,343,774 NIS
22Update process of project Earned value (EVA)
- After the work schedule and start the
implementation, we need to update the project
data to compare between the executed project and
the planned project and the impact on the
schedule. - Will now be an update of the project data and
follow-up activities during the months from 27 \
Feb. \ 2011 to 12\ Dec \ 2011using the theory of
earned value. - That can be explained using this value follow-up
project in terms of time and cost, sometimes
called financial values gained with time and
which we can modify the time schedule through
the right decisions to shift back the original
project if there is a deviation from the
previously planned.
23Earned Value
24Diagram of S-Curve in the project
25Update
- This means that each day one of the actual
duration was obtained only 0.98 of the value of
planned, in other words that the productivity of
the project is only 0.98 of the planned.
- From this table we calculate the following
- Schedule Performance Index (SPI) 0.98
- OR
- SPIBCWP/BCWS2,306,221.29/2,344,862.790.98 lt1
- SPIlt1 behind Schedule (Project
delayed) - Cost Performance Index (CPI) 1 we dont have
educate information
26Thank You