Project Management An Introduction to Project Management - PowerPoint PPT Presentation

About This Presentation
Title:

Project Management An Introduction to Project Management

Description:

... the foundation system two different type that comply with such soil conditions we suggested two alternatives foundation systems: Pile System Raft system ... – PowerPoint PPT presentation

Number of Views:435
Avg rating:3.0/5.0
Slides: 27
Provided by: Stephen801
Learn more at: https://eng.najah.edu
Category:

less

Transcript and Presenter's Notes

Title: Project Management An Introduction to Project Management


1
  • Project Management An Introduction to Project
    Management

Supervisor eng. Baraq Jumaa Prepared byKhaled
Mohammad SawalhaSuha Tarek Awwad2011-2012
2
  • Graduating project consists of two parts
  • The first part includes preparing a theoretical
    research.
  • The second part includes the application of the
    principles in construction project management

3
What is a project?
  • Project is the collection of activities, that are
    related or connected, for developing a product or
    a service
  • Characteristics of Projects
  • Temporary
  • Unique
  • Projects have always a customer who uses the
    results

4
Project life cycle
5
What is Project Management?
  • Project Management is the application of skills,
    knowledge, tools and techniques to meet the needs
    and expectations of stakeholders for a project

6
 Triple Project Management Constraints
7
Brief Description Part
Two
  • The project is a community police station located
    in Arrabeh village / Jenin City .
  • The total area of 842.2 ms Consists of two floor
  • Owner Ministry of Interior Affairs
  • Supervision Ministry of Public Works Housing
  • Donor Germany federation GIZ

8
Brief Description cont.
  • Tender implementing Duration 300 calendar days.
  • Scheduled Duration 235 work days
  • Commencement order 27- Feb- 2011
  • Hand over Date 24-Dec-2011
  • Bid cost 3,169,654 NIS

9
Work breakdown structure
  • The project is divided into activities in a
    process called work breakdown structure. In this
    project we breakdown it according to the type of
    level in building, as the following

10
Shows in the following Figure (WBS)
11
Calculate the cost
12
The bar chart
13
The S-curve as shown
14
Problem Case
  • In the process of foundations establishment a
    soil confirmation test is carried out to confirm
    the bearing capacity of base strata as per design
    bearing capacity (25ton/MS), the lab reports
    provided the following
  • Pure Clay soil layer with variable depth (3-6 m)
  • The bearing capacity equal (10ton/Ms)
  • High swelling settlement conditions

15
Problem Case cont.
  • Depending on that soil report the contractor
    asked the supervision representative to suspend
    the works in the project consider the new facts
    in site to redesign the foundation system.
  • According to the FIDIC 19998.8 Suspension of
    Workand the previous condition the Supervision
    decided to suspend the project progress to
    redesign the foundation system

16
Problem solution
  • two different type that comply with such soil
    conditions we suggested two alternatives
    foundation systems
  • Pile System
  • Raft system

17
Comparison Sheet
Comparison Sheet
Amount NIS Description No.
356,535 Summary for Bid(single footing) 1
474,640 Summary for Raft 2
545,176 summary for pile 3
118,105 Difference between raft bid
18
The modified bar chart
19
The result of the problem case
  • Work was suspended for 45 days and recommencement
    order was issued to the contractor followed with
    a variation order for raft foundation
    system and 63 day time extension.
  • As a result of that extension of time and
    according to FIDIC 199920.1 Contractor's Claims
    the contractor should be Compensated.

20
The total financial claim as shown in the table
below
Summary of expenses
1,032 Nis Indirect cost / day
435 Nis Job over head cost/day
1,467 Nis Total cost / day
45 day Total no. of suspension days
66,015 Nis Expenses earned by the contractor as a result of the extension
21
Summary
  • Duration of the project has become in this case
    298 working days
  • Total duration(235) (18)(45)298 day
  • And the total cost become 3,343,774 NIS
  • Total Cost (3,169,654) (118,105)(1,46745)
    3,343,774 NIS

22
Update process of project Earned value (EVA)
  • After the work schedule and start the
    implementation, we need to update the project
    data to compare between the executed project and
    the planned project and the impact on the
    schedule.
  • Will now be an update of the project data and
    follow-up activities during the months from 27 \
    Feb. \ 2011 to 12\ Dec \ 2011using the theory of
    earned value.
  • That can be explained using this value follow-up
    project in terms of time and cost, sometimes
    called financial values gained with time and
    which we can modify the time schedule through
    the right decisions to shift back the original
    project if there is a deviation from the
    previously planned.

23
Earned Value
24
Diagram of S-Curve in the project
25
Update
  • This means that each day one of the actual
    duration was obtained only 0.98 of the value of
    planned, in other words that the productivity of
    the project is only 0.98 of the planned.
  • From this table we calculate the following
  • Schedule Performance Index (SPI) 0.98
  • OR
  • SPIBCWP/BCWS2,306,221.29/2,344,862.790.98 lt1
  • SPIlt1 behind Schedule (Project
    delayed)
  • Cost Performance Index (CPI) 1 we dont have
    educate information

26
Thank You
Write a Comment
User Comments (0)
About PowerShow.com