National Museum of the Marine Corps - PowerPoint PPT Presentation

About This Presentation
Title:

National Museum of the Marine Corps

Description:

... 4-Dimensional Virtual Simulation Modeling for Structural Steel Erection Planning Conclusion National Museum of the Marine Corps Michael R. Lockwood ... – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 36
Provided by: MRL63
Learn more at: https://www.engr.psu.edu
Category:

less

Transcript and Presenter's Notes

Title: National Museum of the Marine Corps


1
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
National Museum of the Marine Corps
Michael R. Lockwood Construction
Management Advisor Dr. Riley
AE Senior Thesis 2005
Final Presentation
2
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

3
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

4
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Project History
Project Overview
Project National Museum of the Marine
Corps Location Quantico, VA Function Marine
Corps Heritage Museum Size 120,000 sq.
ft. Cost 42,000,000 Schedule April 2004
April 2006 Delivery Method Traditional w/ CM
Agent Design National Design Competition Additio
nal Phase I of large Marine Corps Heritage
campus future expansion to include parade
grounds, hotels, and monumental trails
5
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Architectural Features
Project Overview
  • 210-foot tilted stainless steel clad mast
    soaring through a 160-foot glass skylight,
    inspired by the Iwo Jima Memorial
  • Steel mast designed to be seen from nearby I-95
    as cars approach from the North South
  • Two large architectural concrete walls funnel
    visitors to the main entrance
  • Sustainable Design Features
  • Green Roof _at_ Central Gallery
  • Massive Skylight System
  • Backfilled Earth Berms
  • Large open exhibit gallery space beneath the
    skylight for displaying large exhibits such as
    tanks and airplanes

6
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

7
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Overview
Traditional Project Delivery Approach
Schematic Design
Design Development
Bid
Contractor Selection
  • Steps of Traditional Project Delivery Approach
  • Owner contacts architect
  • Architect designs the project and develops
    construction documents over time
  • Project is let out for competitive bid
  • Contractor is selected and construction begins

Role of Construction Manager in the Design Process
8
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Alternative Approach
Proposed Alternative Project Delivery Approach
Schematic Design
Design Development
Construction Documents
Construction Manager Selection
  • Basis of Alternative Approach
  • Communication is key to successful project
    delivery
  • Poor communication leads to cost overruns,
    delayed schedules, and numerous changes
  • Goal of Proposed Alternative
  • Improve overall communication
  • Reduce cost overruns, delayed project delivery,
    and design changes

Role of Construction Manager in the Design Process
9
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Research Means Methods
  • Research Means
  • Alternative approach very feasible and appealing
    to construction managers
  • Owners do not recognize benefit and value of a
    construction manager during the design process
  • Research survey and interview questions
    developed and distributed to industry members
  • Research Goal To determine the value of a
    construction manager in design
  • Research Methods
  • 18 question online survey distributed to
    approximately 52 industry members (19
    architects, 7 owners, 22 construction managers, 4
    general contractors)
  • Interview questions distributed to 8
    individuals (Two of each discipline)
  • Research Results
  • 25 responses to online survey (7 architects, 2
    owners, 12 CMs, 4 GCs)

Role of Construction Manager in the Design Process
10
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Research Results
At what point during design do you feel it is
appropriate to involve a construction manager
Conceptual Design, Schematic Design, Design
Development, Construction Documents?
Construction Managers
Architects
Overall
17
29
36
33
64
57
14
50
Revised Alternative Project Delivery Approach
Conceptual Design
Schematic Design
Design Development
Construction Documents
Construction Manager Selection
Role of Construction Manager in the Design Process
11
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Research Results
Which of the following is the most valuable asset
a Construction Manager can bring to the design
process?
  • Estimating - CM provides accurate cost
    information simultaneously with design
  • Constructability Review - Review design and
    reduce changes during construction

Role of Construction Manager in the Design Process
12
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Case Study NMMC Project
NMMC Project Development Process
Schematic Design
Design Competition Winner Awarded
Design Development
Bid
Contractor Selection
Proposed Alternative NMMC Project Development
Process
Schematic Design
Design Competition Winner Awarded
Construction Manager Selection
Construction Documents
Design Development
Role of Construction Manager in the Design Process
13
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis I
Further Areas of Research
  • Further Research Areas
  • Re-distribution of online survey with
    additional questions
  • Case study projects
  • Methods to quantify and present value
    associated with early CM involvement
  • Determine set of rules and/or guidelines for
    owners to determine if early CM involvement will
    be beneficial for a project

Role of Construction Manager in the Design Process
14
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

15
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Overview
  • Phased Construction
  • Accelerate project
  • IMAX Theatre Additional Exhibit Gallery Space
  • Design Features
  • Earth backfilled walls to maintain the
    architectural experience of the building
  • Results in a more complex design of the exterior
    wall (C1 Wall)
  • Potential for excessive costs associated with
    future expansions


Soil Retention System Design and Analysis
16
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Existing Design Conditions
  • Concrete Wall
  • 45 feet high concrete wall 2 feet thick 192
    feet length
  • Reinforcing Steel
  • VOF - 11 bars _at_ 8 o.c.
  • VIF - 11 bars _at_ 12 o.c.
  • HEF - 6 bars _at_ 12 o.c.
  • Footing System
  • Spread Footing
  • 15 feet wide x 5 feet deep
  • Shear Key
  • 6 ½ feet deep x 2 ½ feet wide
  • Exterior Buried Ductwork
  • Two levels of ductwork attached to wall

Soil Retention System Design and Analysis
17
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Design of Alternate System
  • Sheet Pile Earth Retention System
  • Backfilled sheets driven into ground and
    backfilled on one side
  • Anchored sheets area anchored back into earth
    near top

Soil Retention System Design and Analysis
18
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Design of Alternate System
  • Steel Sheets
  • PZ22 Member
  • Anchor System
  • 3 x 3 x 3 Concrete Deadman Anchors
  • 1 Steel Tieback Rods
  • W6x16 Soldier Beams

Soil Retention System Design and Analysis
19
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Design of Alternate System
  • Sheet Pile System
  • 46 ½ feet sheets 25 feet free length
  • 9 soldier beams
  • 32 tiebacks and deadman anchors
  • 6 feet from concrete wall

Soil Retention System Design and Analysis
20
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Design of Alternate System
Soil Retention System Design and Analysis
21
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Project Impacts
  • Design Impacts
  • Concrete Wall Size Reduction
  • Reduced reinforcing
  • Reduced concrete
  • Removal of Shear Key
  • Constructability Impacts
  • Cavity created for exterior ductwork and future
    access to ductwork
  • Future expansion through wall considerably less
    complex with new wall design

Soil Retention System Design and Analysis
22
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
Project Impacts
  • Financial Impacts
  • Initial Cost Increase
  • 29,373
  • Future Cost Decrease
  • 47,952
  • Overall Cost Reduction
  • 18,500
  • Schedule Impacts
  • Sheet pile system to be installed during bulk
    excavation phase
  • No impact to overall project schedule
    potential cost savings with reduction in bulk
    excavation quantities

Soil Retention System Design and Analysis
23
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

24
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
Overview
  • Structural Steel Skylight System Erection
    Planning
  • Unique and complex system
  • Steel Truss Mast
  • Structural Steel Framing
  • Erection planning took a great deal of time and
    effort
  • 120 page steel erection sequence plan
  • Proposed Use of 4-D Virtual Modeling
  • Use 4-D modeling as a tool to assist in the
    development of the structural steel erection plan

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
25
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
2-D Steel Erection Planning
  • Roof Erection Procedure
  • Step-by-step erection sequence for skylight
    system
  • Developed by one engineer over a 6-month time
    period
  • 120 pages including
  • Written erection procedure
  • Erection sketches
  • Temporary falsework and stabling details
  • Lifting lug details for individual members

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
26
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
4-D Steel Erection Planning
  • 4-D Virtual Model
  • Site Boundaries - Access Roads - Staging Areas -
    Crane Locations -Temporary Facilities
  • Virtually displays erection sequence
  • Easily change and test erection sequences
    multiple times
  • Interactive Model w/ numerous viewpoints
  • Identify conflicts and out-of-order sequence work

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
27
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
2-D vs. 4-D Erection Planning
  • 4D model allows for view from all angles and can
    help identify potential conflicts, safety
    hazards, or sequence errors

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
28
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
Applications of 4-D Modeling
  • Tool for Developing Erection Procedure
  • Allow users to visualize sequence
  • Trial and Error planning techniques
  • Identify potential conflicts prior to erection
  • Reduce the risk of complications during erection
  • Trade Coordination
  • Visually display crane locations staging areas
  • Identify potential safety hazards
  • Project Communication
  • Display erection sequence plan during prepatory
    meetings with general contractor and owners
    representatives
  • Allows contractor to address any questions or
    concerns from all parties prior to beginning the
    erection in the field

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
29
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis III
Case Study NMMC Project
  • Could have identified potential conflicts prior
    to them occurring in the field resulting in
    delays, cost increases, etc

4-Dimensional Virtual Simulation Modeling for
Structural Steel Erection Planning
30
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
  • Presentation Outline
  • Project Overview
  • Analysis I
  • Role of Construction Manager in the Design
  • Process
  • Analysis II
  • Soil Retention System Design and Analysis
  • Analysis III
  • 4-Dimensional Virtual Simulation Modeling
  • for Structural Steel Erection Planning
  • Conclusion

31
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Conclusion
Summary and Conclusions
  • Reducing the Impact of Phasing
  • Utilize the knowledge and expertise of a
    construction manager early in the design process
  • Investigate temporary structures to limit the
    alteration of the final design and to reduce the
    complexity of the future construction
  • Early CM involvement could also allow for early
    involvement of key subcontractors and allow for
    the use of 4-D modeling
  • Impact of Phased Construction
  • Requires a great deal of planning and
    communication between design and construction
  • Potential for extensive over-design of project
    components to accommodate temporary loads

32
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
The End
Acknowledgements
I would like to thank the following individuals
for all their help and support
  • Centex Construction Jason Reece and the Marine
    Corps Project Staff
  • Marine Corps Heritage Foundation
  • Banker Steel Company Chet McPhatter
  • CMT Laboratories
  • CM Faculty Dr. Riley, Dr. Messner, Dr. Horman
  • Kurt Maldovan Jamie Knise
  • AE Faculty and Staff
  • AE Class of 2005
  • Friends and Family

33
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
The End
Questions?
34
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
Analysis II
  • Design Loads
  • Max Moment 4.313 ft-kip / ft of wall
  • Approximately 9.05 feet from the top of the wall
  • Section Modulus 1.725 in3/ft
  • Sheet Pile Member Section Modulus 18.1 in3/ft

Soil Retention System Design and Analysis
35
National Museum of the Marine Corps Michael R.
Lockwood Construction Management
EXTRA
Write a Comment
User Comments (0)
About PowerShow.com