Title: CITY OF FORT COLLINS NEW FACILITIES
1CITY OF FORT COLLINS NEW FACILITIES
- KEN MANNON,
- Operations Services Director
2CITY PARK POOL REPLACEMENT 1.75M - SCD MAY
2003
3COLLINDALE CLUBHOUSE -14,660 SF 2.6 M SCD
DEC 2002
4CSU TRANSIT CENTER 11 DROP/ PICKUP SITES 2.37M
PHASE I COMPLETED SEPT 2002
5CSU TRANSIT CENTER SITE LAYOUT
6EPIC / TWICE THE ICE - 36,400 SF 3.93M SCD
MARCH 2003
7FIRE STATION 14 - 10,800 SF 2.4M - SCD
APRIL 2003
8FOSSIL CREEK MAINT. BUILDING 6,550 SF 700K
SCD MARCH 2003
9GARDENS ON SPRING CREEK - 4,000 SF 10 ACRES
GARDENS - 2.05M - SCD SEPT 2003
10GARDENS ON SPRING CREEK LONG RANGE MASTER PLAN
11NEW METER SHOP SITE - 8,500 SF 2.03M - SCD
DEC 2003
12NEW N S A C - 52,000 SF CONCEPTUAL PHASE
100,000 YR 2004 FUNDING 8 M
13NIX SITE MAINTENANCE FACILITY - 6,000 SF 2.05M
- 27.48 AC COMPLETED JUNE 2002
14NIX SITE FARM HOUSE 6,500 SF 2.4M - SCD
OCT. 2002
15SOUTHRIDGE GOLF CART STG 3,250 SF 200,000
- SCD EARLY 2003
16TRAFFIC OPS BUILDING - 9,300 SF 2.17M -
SCD NOV. 2002
17UTILS WH YD IMPRVMNT SITE EAST SIDE 3.25M
- SCD SUMMER 2003