VISTA Data Flow System - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

VISTA Data Flow System

Description:

Apr 04 VISTA Project Board moved pipeline PDR coincident with camera s/w FDR (Nov) ... and source catalogs and curate them should be in place before any resources were ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 15
Provided by: jimem
Category:
Tags: vista | curate | data | flow | system

less

Transcript and Presenter's Notes

Title: VISTA Data Flow System


1
VISTA Data Flow System
  • for WFCAM VISTA data2nd overview for AGOC

2
Some events since 1st AGOC visit
  • Mar 28 1st AGOC visit
  • Apr 04 VISTA Project Board moved pipeline PDR
    coincident with camera s/w FDR (Nov)
  • Apr 15/16 v1/2 VDFS Archive CDR (wfcam)
  • May 05 v1/2 VDFS Archive CDR panel report
    received
  • May 28 v1/2 VDFS Archive Software Architecture
    Design Document
  • Jun 06 VISTA Project Board
  • Jun 12/13 Workshop on Observing Strategy (wfcam)
  • Jul 04 VDFS Q2 reviewed, Q3 plan set
  • Jul 04 Jim Gray Alex Szalay visit archive
  • Aug 01 VISTA Project Board
  • Sep 17-19 VISTA Camera pre-FDR workshop
  • Oct 01 VDFS Q3 reviewed, Q4 plan set
  • Oct 02 VISTA Project Board

3
v1Archive CDR conclusions
  • VDFSv1 Science Archive CDR was held 15/16 Apr.
    The main task of the Panel was to determine
    whether the Science Archive design put forward by
    WFAU members met eight (seven!) criteria, their
    conclusions were
  • 1 The end product is acceptable Yes.
  • 2 The project as conceived is feasible The Panel
    had major concerns regarding the project schedule
    and risk assessment. Both were far too
    optimistic, and timescales could easily be scaled
    up by a factor of two.
  • 3 Detailed plans for building the complete system
    are in place A plan is in place, but important
    areas need to be better defined and planned. One
    important example is software architecture and
    software design procedures.

4
V1 Archive CDR conclusions 2
  • 4 The budget and staffing resources are
    sufficient for the project and commensurate with
    the estimated time to completion Staffing is a
    concern especially after deployment. Too little
    staff was allocated for v1 operations.
  • 5 A reasonable estimate of the risk has been
    made, and whether there are useful de-scope
    options Risk assessment needs to be planned in
    greater detail. No de-scoping options were
    presented although the Panel strongly felt that
    the hardware and software needed to produce
    satisfactory pixel data and source catalogs and
    curate them should be in place before any
    resources were allocated to the ingestion of
    external catalogs for example.
  • 6 External interfaces are well controlled Yes.
  • 7 The path from v1 to v2 is understood and
    feasible The path from v1 to v2 will be easier
    if sufficient attention is paid to proper
    software architecture and design procedures that
    will maintain portable code and clean interfaces
    between subsystems.

5
AGOC visit 28 Mar 2003 pt1/5
  • Conclusions
  • 1.     The Committee recommended the following
  • a.      Further VISTA DFS Advisory Committee
    members should be appointed who were potential
    data users who were not linked to the delivery of
    the project.
  • On further reflection it was felt there was no
    need for a formal AC as individual contacts
    served the advice functions needed by the team.
  • The question of a future role for a Users
    Committee remains open with PPARC for the future.

6
1st AGOC visit 28 Mar 2003 pt2/5
  • b.     Appropriate procedures appeared to be in
    place for the proper engagement with ESO over the
    ESO deliverable aspects of the project.
  • Apr 04 VISTA Project Board moved pipeline PDR to
    be coincident with camera s/w FDR (Nov)
  • Sep 11 ESO asked for DFS PDR after camera FDR

7
1st AGOC visit 28 Mar 2003 pt3/5
  • c.     A regular external oversight activity was
    required. At present this function fell to the
    VISTA Board. The VISTA Board appeared to be
    focusing most of its efforts on other aspects of
    the VISTA project, to the extent that the DFS
    project was not getting the level of scrutiny and
    oversight that it needed. PPARC should institute
    a more effective oversight structure for the DFS
    project.
  • PPARC wish to continue current oversight by VISTA
    Board supplemented 6 monthly this panel, at least
    until next tranche of e-science money.

8
1st AGOC visit 28 Mar 2003 pt4/5
  • d.      The unfunded future effort issue would
    need to be resolved through appropriate bids to
    the current PPARC e-science call.
  • May 31 VEGA proposal submitted
  • Jul 14/15 PPRP passes 2.3m VDFS part of VEGA
  • Sep 30 GSC letter re VDFS/VEGA
  • Oct 14 telecon Oct 28 discussion meeting
  • Jan 2004 GSC

9
1st AGOC visit 28 Mar 2003 pt5/5
  • e.     Project management procedures appeared to
    be emerging but these had only been instituted
    recently. A specific set of milestones and
    interim deliverables was still required, as was a
    process for measuring progress against them.
    Future oversight would need to ensure that these
    procedures became fully operational and
    effective.

10
Changes to External Milestones (top level)
  • WFCAM DFS
  • 04 Jan Commissioning - no data camera
    hardware problems
  • 04 Apr Operations - no data camera hardware
    problems
  • 05 Jan v2 pipeline archive
  • 05 Apr 1st year science out but wont be a
    year of it by then!
  • VISTA DFS
  • 03 July Preliminary Design Review moved by
    Board, then by ESO -- new date being negotiated
  • 03 Nov Final Design Review corresponding
    slippage
  • 05 Dec Instrument in Chile
  • 06 May Instrument and onsite DFS Commissioning
  • 06 Aug Instrument Acceptance gt Operations

11
Top Level Milestones to end 2004
12
Top Level Milestones 2005-8
13
Working of Management Process
  • Project Wide Mgt team Local Mgt? added Hambly
    Hodgkin to monthly review team
  • Deliverables detailed?
  • Work Packages ( their managers) ?
  • Sub tasks defined ( implementers)
  • Long range plan?
  • Risk analysis ? ? but not yet reviewed
  • Quarterly detailed plan deliverables?
  • Report against in future
  • Review past and make next
  • Monthly Mgt team (tele) progress meetings ?
  • Weekly/fortnightly (local) team progress
    meetings. ? Minutes actions distributed. ?

14
Deliverables - metrics
Key
100 complete 50 almost finished
10 started 0 not started
15
Changes to Management Structure
GSC
VISTA Project Scientist now based in Cambs
VISTA Board
6 monthly reports??
Two Monthly reports
VDFS Advisory Committee
PI Management Team
Weekly reports
Fortnightly reports
CASU manager
WFAU Manager
report
CASU WPMs
WFAU WPMs
manage
advice
16
VDFS Advisory Committee
  • Membership (provisional)
  • Project Leader (chair)
  • VISTA Project Office s/w WPM, UKIRT Director
  • UKIDSS VISTA Project Scientists
  • Astrogrid Project Scientist
  • Archive/pipeline implementer (from Leicester?)
  • CASU/WFAU co-Is and managers in attendance
  • Purpose
  • Provide advice to Project from customers and
    external experts
Write a Comment
User Comments (0)
About PowerShow.com