Title: VISTA Data Flow System
1VISTA Data Flow System
- for WFCAM VISTA data2nd overview for AGOC
2Some events since 1st AGOC visit
- Mar 28 1st AGOC visit
- Apr 04 VISTA Project Board moved pipeline PDR
coincident with camera s/w FDR (Nov) - Apr 15/16 v1/2 VDFS Archive CDR (wfcam)
- May 05 v1/2 VDFS Archive CDR panel report
received - May 28 v1/2 VDFS Archive Software Architecture
Design Document - Jun 06 VISTA Project Board
- Jun 12/13 Workshop on Observing Strategy (wfcam)
- Jul 04 VDFS Q2 reviewed, Q3 plan set
- Jul 04 Jim Gray Alex Szalay visit archive
- Aug 01 VISTA Project Board
- Sep 17-19 VISTA Camera pre-FDR workshop
- Oct 01 VDFS Q3 reviewed, Q4 plan set
- Oct 02 VISTA Project Board
3v1Archive CDR conclusions
- VDFSv1 Science Archive CDR was held 15/16 Apr.
The main task of the Panel was to determine
whether the Science Archive design put forward by
WFAU members met eight (seven!) criteria, their
conclusions were - 1 The end product is acceptable Yes.
- 2 The project as conceived is feasible The Panel
had major concerns regarding the project schedule
and risk assessment. Both were far too
optimistic, and timescales could easily be scaled
up by a factor of two. - 3 Detailed plans for building the complete system
are in place A plan is in place, but important
areas need to be better defined and planned. One
important example is software architecture and
software design procedures.
4V1 Archive CDR conclusions 2
- 4 The budget and staffing resources are
sufficient for the project and commensurate with
the estimated time to completion Staffing is a
concern especially after deployment. Too little
staff was allocated for v1 operations. - 5 A reasonable estimate of the risk has been
made, and whether there are useful de-scope
options Risk assessment needs to be planned in
greater detail. No de-scoping options were
presented although the Panel strongly felt that
the hardware and software needed to produce
satisfactory pixel data and source catalogs and
curate them should be in place before any
resources were allocated to the ingestion of
external catalogs for example. - 6 External interfaces are well controlled Yes.
- 7 The path from v1 to v2 is understood and
feasible The path from v1 to v2 will be easier
if sufficient attention is paid to proper
software architecture and design procedures that
will maintain portable code and clean interfaces
between subsystems.
5AGOC visit 28 Mar 2003 pt1/5
- Conclusions
- 1.    The Committee recommended the following
- a.     Further VISTA DFS Advisory Committee
members should be appointed who were potential
data users who were not linked to the delivery of
the project. - On further reflection it was felt there was no
need for a formal AC as individual contacts
served the advice functions needed by the team. - The question of a future role for a Users
Committee remains open with PPARC for the future.
61st AGOC visit 28 Mar 2003 pt2/5
- b.    Appropriate procedures appeared to be in
place for the proper engagement with ESO over the
ESO deliverable aspects of the project. - Apr 04 VISTA Project Board moved pipeline PDR to
be coincident with camera s/w FDR (Nov) - Sep 11 ESO asked for DFS PDR after camera FDR
71st AGOC visit 28 Mar 2003 pt3/5
- c.    A regular external oversight activity was
required. At present this function fell to the
VISTA Board. The VISTA Board appeared to be
focusing most of its efforts on other aspects of
the VISTA project, to the extent that the DFS
project was not getting the level of scrutiny and
oversight that it needed. PPARC should institute
a more effective oversight structure for the DFS
project. - PPARC wish to continue current oversight by VISTA
Board supplemented 6 monthly this panel, at least
until next tranche of e-science money.
81st AGOC visit 28 Mar 2003 pt4/5
- d.     The unfunded future effort issue would
need to be resolved through appropriate bids to
the current PPARC e-science call. - May 31 VEGA proposal submitted
- Jul 14/15 PPRP passes 2.3m VDFS part of VEGA
- Sep 30 GSC letter re VDFS/VEGA
- Oct 14 telecon Oct 28 discussion meeting
- Jan 2004 GSC
91st AGOC visit 28 Mar 2003 pt5/5
- e.    Project management procedures appeared to
be emerging but these had only been instituted
recently. A specific set of milestones and
interim deliverables was still required, as was a
process for measuring progress against them.
Future oversight would need to ensure that these
procedures became fully operational and
effective.
10Changes to External Milestones (top level)
- WFCAM DFS
- 04 Jan Commissioning - no data camera
hardware problems - 04 Apr Operations - no data camera hardware
problems - 05 Jan v2 pipeline archive
- 05 Apr 1st year science out but wont be a
year of it by then! - VISTA DFS
- 03 July Preliminary Design Review moved by
Board, then by ESO -- new date being negotiated - 03 Nov Final Design Review corresponding
slippage - 05 Dec Instrument in Chile
- 06 May Instrument and onsite DFS Commissioning
- 06 Aug Instrument Acceptance gt Operations
11Top Level Milestones to end 2004
12Top Level Milestones 2005-8
13Working of Management Process
- Project Wide Mgt team Local Mgt? added Hambly
Hodgkin to monthly review team - Deliverables detailed?
- Work Packages ( their managers) ?
- Sub tasks defined ( implementers)
- Long range plan?
- Risk analysis ? ? but not yet reviewed
- Quarterly detailed plan deliverables?
- Report against in future
- Review past and make next
- Monthly Mgt team (tele) progress meetings ?
- Weekly/fortnightly (local) team progress
meetings. ? Minutes actions distributed. ?
14Deliverables - metrics
Key
100 complete 50 almost finished
10 started 0 not started
15Changes to Management Structure
GSC
VISTA Project Scientist now based in Cambs
VISTA Board
6 monthly reports??
Two Monthly reports
VDFS Advisory Committee
PI Management Team
Weekly reports
Fortnightly reports
CASU manager
WFAU Manager
report
CASU WPMs
WFAU WPMs
manage
advice
16VDFS Advisory Committee
- Membership (provisional)
- Project Leader (chair)
- VISTA Project Office s/w WPM, UKIRT Director
- UKIDSS VISTA Project Scientists
- Astrogrid Project Scientist
- Archive/pipeline implementer (from Leicester?)
- CASU/WFAU co-Is and managers in attendance
- Purpose
- Provide advice to Project from customers and
external experts