Title: ILC Operation
1ILC Operation SLAC ILC Controls meeting,
1/19/2006
- Turning on the beam
- The chronology of a trip
- Separating power and luminosity
- testing feedbacks
- Maintaining equilibrium through transients
- Positrons
2At first
- Extract the 1 pilot from the DR
- 10 us later begin the full train sequence
- Each bunch must traverse properly or the abort
system will be triggered. - sensed using the
- beam position monitors,
- beam loss monitors and
- beam intensity monitors
- true single bunch response time devices.
3Damping Ring
- Before extraction must have
- no coherent motion
- decent lifetime
- appropriate gaps
- designated pilot bunch ready to be first
- tested kicker pulse in the gap
- RF within tols
4Abort systems rtml, linac/undu, bds
- The minimal abort system consists of a spoiler /
collimator / absorber block (copper) and a
kicker. - Rise time should be fast enough to produce a
guaranteed displacement of more than the pipe
radius in an inter-bunch interval. In any given
fault, at most 450 bunches would then strike the
copper block. - Assuming the latency for detecting the fault is
500 ns, the upstream signal effective propagation
speed is 0.7 c, and the abort kicker latency time
is 1 us, the maximum kicker spacing should be
1000m.
5MPS abort dumps
- In the baseline configuration five abort systems
are needed on the electron side (four on the e
side) 2 upstream of the linac, one upstream of
the undulator and 2 in the beam delivery. - An alternative is an additional abort per
kilometer of linac. - may depend on the linac straightness.
- The required kicker deflection is 10 mm, for the
radius, and a relatively small additional amount
for margin. With a kicker volume of 20 20 mm,
about 25 MW of peak power would be required for a
50 m long kicker system
6Linac failure modes and time scales
- Quads,
- RF phase and amplitude during the pulse
- Cryo slow
- valves slow
- dipoles
- fast time scale energy drop
7Energy / Energy spread stabilization
- Nominal plan end of linac monitoring system
- Backup plan use residual beta oscillation
wavelength - May need additional BPMs (HOM?)
- Chirp bunch train a small amount
- High resolution BPMs needed
- To avoid ? mid-linac spectrometers.
- These are justified when the linac will be
operated with narrow energy bandpass (not this
linac) - expected bandpass 50, depending on
straightness? - expect undulator to be narrow - band
8Collimation
- 10KW/m max with very optimistic halo
assumptions - About 10x SLC max
- Mechanical tests, tolerances
- energy collimation likely to demand most care
- narrower than BDS optical bandwidth (0.2?)
- energy variations on the slits
- intra-train feedback
- fast local abort
9Expected energy variability
- LLRF LO
- Seen at TTF (250kHz)
- Mixing intermodulation 1300 / 52 MHz ?
- Interbunch spacing 400/1300 (16/52) us
- Should be ok.
- Check for intermodulation with digitizer clock
high harmonic relationship - slow quenches outside of feedback correction
range - the loss in gradient cannot be compensated by
single klystron vector sum feedback - often seen at TTF
10MPS average power loss
- For stability, it is important to keep as much of
the machine operating at a nominal power level. - including the source, damping ring injector and
the damping ring itself. - Segmentation is the key ? beam shut off points.
- Each of these segmentation points is capable of
handling the full beam power, i.e. both a kicker
and dump are required. - also fast abort locations
11Begin End
1 e- injector Source (gun) e- Damping ring injection (before)
2 e- damping ring Ring injection e- Ring extraction (after)
3 e- RTML Ring extraction e- Linac injection (before)
4 e- linac Linac injection Undulator (before)
5 Undulator Undulator BD e target
6 e- BDS BD start e- Main dump
7 e target e target e damping ring injection
8 e damping ring Ring injection e ring extraction
9 e RTML ring extraction e linac injection
10 e linac linac injection e BDS
11 e BDS e BDS e main dump
12Low Power operation
- intra-train b/b feedback limitations
- Pilot bunch one nominal I bunch?
- What is the minimum beam power for nominal
operation? - beam-sensor performance degradation
- LLRF/BPM systematics
- Collimation esp. energy. Does the pilot bunch go
through the slits? - Reduced repetition rate
- 0.1 Hz pulse rate
- 10 KHz bunch spacing
- Reduced RF power operation
13Example low power operationpilot 1 _at_ 1Hz
- 800W / 11.3 MW ? factor 15000 reduction
- Compelling to test lumi/background/tuning
procedures - How many bunches at what intensity / spacing are
needed for systems that MUST have intra-train
feedback? - Pilot 1 at 10 us?
- Laserwire scan will take 1 minute x y
coupling phase space 15m unless scans can be done
in parallel, at both ends of the machine, for
example. - Can electricity use be reduced?
- Marx allows controllable pulse length
- Baseline?
- Klystron thermal stabilization ? another
transient for LLRF to handle
14Equilibrium
- Where are the fields that depend on preceding
beam pulses? - There are (at least) 3 primary subsystems whose
configuration depends on average beam power - 1) damping ring alignment,
- 2) positron capture system phases,
- 3) collimation
- Klystrons (depending on power saving
strategies) - In each of these cases, beam heating is a
significant part of the total heat flow and will
necessarily have some impact. - At SLC, the beam power on target was 30KW, about
20 of this was absorbed in the positron capture
RF section. - Much can be done to reduce these effects using
more careful initial engineering, - beam power is much more than 30KW neutral beam
may mitigate this - Must consider the impact of residual temperature
changes carefully and assume they will be a
problem.
15Damping ring stored current
- How to keep the DR full under all variations
downstream upstream? - Lifetime?
- Off-axis injection (aka accumulation)?
- Abort fill cycles low repetition rate
- most ring users recommend top up for
maintaining equilibrium - Full power dumps are needed in the damping ring
(complex) and at the entrance to the linac. - to keep the DRs as warm as possible.
16Tune up and steady-state dumps
- 1) purpose for additional high power dumps
results from the desire to keep upstream systems
in equilibrium during short interruptions. - Other functions include the desire to have beam
instrumentation and related feedback /
stabilization systems in operation during the
interruptions - (soft requirements in comparison).
- The critical parameters are the degree to which
the upstream machine configuration (includes
field strength, phase, alignment etc) depend on
the average beam power in those locations. - If it is guaranteed that there is no difference
between full power operation and very low power
operation, then additional high power dumps are
not needed.
17MPS Transients
- two basic kinds of interruptions,
- 1) short (MPS or beam tuning) driven where it
would be useful if the system recovered more or
less instantly and - 2)longer interruptions involving access etc where
upstream thermal time scales are unimportant. - High power beam auxiliary beam dumps are only
needed for 1) (not 2). - The most logical place to dump the full rep
rate/n_bunch beam is before the entrance to the
linac, not after it. - recommend removing the baseline requirement for
full power dumps at the entrance to the beam
delivery. - These dumps are important but need not take full
power, only the full bunch train. A much lower
power, lower cost dump could be implemented, for
example one capable of 0.1Hz full train
operation. - expect that 0.5MW dumps will be much cheaper and
easier to deal with than full power beam dumps. - full power dump will cost 50M (DESY).
- Lower power dumps may cost 1/10 of this, based on
the SLC design.
18Full power Dumps
- The undulator positron system should also remain
operating at full power. This requires a full
power charged beam dump at that location. In
principle, if there were a problem on the
positron side, the electron beam could be
transported to the main BDS dumps. - 6) During access to the BDS area, where the
interruption is long compared to these thermal
time scales, the power in the entire machine,
except the stored beam in the DR, should be
scaled back to reasonable levels. - 7) This is the 'minimum dump' configuration.
There are 6 1/2 MW class dumps, one 15 MW (at the
e source) and 2 nominal full power 20MW dumps.
Not including dumps needed in the injector,
undamped, system. - Positron capture
19Operation with the keep-alive
- ring population
- both rings full
- full e- ring / one e
- full e / one e- (?)
- both rings one (or small)
- accumulation (aka off-axis injection) from the
keep-alive - full ring fill takes 30,000 10 bunches (100
min _at_ single bunch) - lifetime 10 minutes
20Pilot control
- Will the pilot bunch go through the energy
collimation? - Coupling vs intensity two different ways to
make a pilot bunch.
21Kicker operation
- Feedback
- stabilizing the voltage
- stabilizing the residual kick
- Feedforward
- across the extraction hairpin
- Single point failures
22Single point failures
- critical, high power, high speed devices
- damping ring kicker,
- DRRF,
- linac front end RF,
- bunch compressor RF and
- dump magnets systems
- redundancy needed.
- extraction kicker, a sequence of independent
power supplies and stripline magnets that have
minimal common mode failure mechanisms. - front end and bunch compressor RF, more than one
klystron / modulator system powering a given
cavity through a tee. - LLRF feedback must stabilize the RF in the event
that one of sources fails mid-pulse. - alternate using a sequence of modestly powered
devices controlled completely in parallel, - There are several serious common mode failures in
the timing and phase distribution system that
need specially engineered controls. - frozen unless the system is in the benign beam
tune up mode.
23Control limits
- Depending on the state of the machine, ?
- programmed (perhaps at a very low level) ramp
rate limits that keep critical components from
changing too quickly. - may have an impact on the speed of beam based
feedback. - Some devices, such as collimators should be
effectively frozen in position at the highest
beam power level. - There may be several different modes, basically
defined by beam power, that indicate different
ramp rate limits.
24The Baseline Machine (500GeV)