Title: Office of Acquisition and Property Management
1Integration of Value Engineering (VE)and the
Five-Year Planning Process
- Office of Acquisition and Property Management
2Presentation Overview
- Quick review of Value Engineering (VE)
requirements and benefits - Summarize DOIs Current VE requirements
- List potential revisions to DOI requirements
- Summarize integration of VE into Five-Year
planning process
Department of the Interior December 2007
3Background VE Requirements
- Public Law 104-106 (1996) requires all agencies
establish a VE program - OMB Circular A-131 requires VE to reduce
nonessential procurement and program costs - Threshold is 1 million for projects and programs
- DOI submits annual VE accomplishment report
submitted to OMB by December 31 of each year - DOIs requirements are in Department Manual 369
Department of the Interior December 2007
4Background - Value Engineering Presentation
Overview
- Public Law 104-106 defines VE as
-
- An analysis of the functions of a program,
project, system, product, item of equipment,
building, facility, service, or supply of an
executive agency, performed by qualified agency
or contractor personnel, directed at improving
performance, reliability, quality, safety, and
life cycle costs.''
Department of the Interior December 2007
5Background - Value Engineering
- VE applies to all projects, programs, equipment
- Studies can be performed by in-house or
contractor personnel - VE can be applied at any point in project or
program life cycle
Department of the Interior December 2007
6Background - Value Engineering
- Construction projects
- VE usually applied at conceptual and design
stages - May be applied more than once on an individual
project - Objective is to
- Ensure all viable alternatives have been examined
- Avoid cost and realize cost savings
- Improve quality of completed project
- Facilitate the government receiving best value
Department of the Interior December 2007
7DOIs Current VE Requirements
- VE program is mandatory for all bureaus and
offices and programs, projects, and activities - Applies to
- Construction, repair, rehabilitation, and
renovation projects with estimated cost 500,000
or greater
Department of the Interior December 2007
8DOIs Current VE Requirements
- VE is performed when concept and estimated cost
is detailed enough for comparison of alternatives - Goal is to achieve saving equal to or greater
than 4 percent of a bureaus aggregate annual
construction budget
Department of the Interior December 2007
9Objective of VE Integration
- The two primary objectives of integrating VE and
- the Five-Year planning process are
- 1) Foster thorough planning and analysis to
complete high quality construction and repair
projects at an appropriate cost - 2) Use VE as a tool to limit project cost and
schedule variance
Department of the Interior December 2007
10Potential Revisions to DOI Requirements
- The below revisions will be discussed by bureau
- VE coordinators. Additional items may be added.
- Define the project stage at which VE results are
reported. - Clearly define the stage in project development
at which VE is performed.
Department of the Interior December 2007
11Potential Revisions to DOI Requirements
- 3) Ensure construction Capital Planning and
Investment Control (CPIC) guide identifies points
in project life cycle to perform VE. - 4) Define application of VE to design/build
projects. - 5) Consider raising the VE threshold to 1
million from 500,000 - - 1 million is minimum threshold per A-131
Department of the Interior December 2007
12Potential Revisions to DOI Requirements
- 6) Define how VE is applied to dam projects
- 7) Acknowledge that sustainable building
practices may justifiably increase some project
costs to create environmental benefit - 8) Consider whether VE should be applied more
rigorously to non-project work
Department of the Interior December 2007
13Revision of Appendix Q
- Appendix Q is the VE section of the construction
CPIC guide - Core of the Appendix is Department Manual 369
(VE)
Department of the Interior December 2007
14Integration Process
- Revise Department Manual Part 369 (VE)
- Goal is for final revision June 1, 2008
- Revise Appendix Q of the Construction CPIC Guide
- Goal is for final revision June 1, 2008
- Bureau VE coordinators will submit proposed
revisions to both documents by January 22, 2008
Department of the Interior December 2007
15Integration Process
- Include revised VE requirements in Attachment G
for the FY 2011- FY 2015 Five Year Plan - This guidance will be issued in FY 2008
- Add a VE data field to the Project Data Sheet
included in the FY 2011- FY 2015 Five Year Plan
Department of the Interior December 2007
16Bureau VE Program Coordinators
- DOI Bill Hamele
- BIA Alan Roit
- BLM Linda Force, Ed Giagni
- BOR Norman Hyndman
- FWS Marshall Wright
- NPS Rich Turk
- USGS Clarence (Bill) Fulk
- Contact your coordinator with questions
Department of the Interior December 2007
17Department of the Interior December 2007