Office of Acquisition and Property Management - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Office of Acquisition and Property Management

Description:

Quick review of Value Engineering (VE) requirements and benefits ... USGS Clarence (Bill) Fulk. Contact your coordinator with questions. Department of the Interior ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 18
Provided by: usth2
Category:

less

Transcript and Presenter's Notes

Title: Office of Acquisition and Property Management


1
Integration of Value Engineering (VE)and the
Five-Year Planning Process
  • Office of Acquisition and Property Management

2
Presentation Overview
  • Quick review of Value Engineering (VE)
    requirements and benefits
  • Summarize DOIs Current VE requirements
  • List potential revisions to DOI requirements
  • Summarize integration of VE into Five-Year
    planning process

Department of the Interior December 2007
3
Background VE Requirements
  • Public Law 104-106 (1996) requires all agencies
    establish a VE program
  • OMB Circular A-131 requires VE to reduce
    nonessential procurement and program costs
  • Threshold is 1 million for projects and programs
  • DOI submits annual VE accomplishment report
    submitted to OMB by December 31 of each year
  • DOIs requirements are in Department Manual 369

Department of the Interior December 2007
4
Background - Value Engineering Presentation
Overview
  • Public Law 104-106 defines VE as
  • An analysis of the functions of a program,
    project, system, product, item of equipment,
    building, facility, service, or supply of an
    executive agency, performed by qualified agency
    or contractor personnel, directed at improving
    performance, reliability, quality, safety, and
    life cycle costs.''

Department of the Interior December 2007
5
Background - Value Engineering
  • VE applies to all projects, programs, equipment
  • Studies can be performed by in-house or
    contractor personnel
  • VE can be applied at any point in project or
    program life cycle

Department of the Interior December 2007
6
Background - Value Engineering
  • Construction projects
  • VE usually applied at conceptual and design
    stages
  • May be applied more than once on an individual
    project
  • Objective is to
  • Ensure all viable alternatives have been examined
  • Avoid cost and realize cost savings
  • Improve quality of completed project
  • Facilitate the government receiving best value

Department of the Interior December 2007
7
DOIs Current VE Requirements
  • VE program is mandatory for all bureaus and
    offices and programs, projects, and activities
  • Applies to
  • Construction, repair, rehabilitation, and
    renovation projects with estimated cost 500,000
    or greater

Department of the Interior December 2007
8
DOIs Current VE Requirements
  • VE is performed when concept and estimated cost
    is detailed enough for comparison of alternatives
  • Goal is to achieve saving equal to or greater
    than 4 percent of a bureaus aggregate annual
    construction budget

Department of the Interior December 2007
9
Objective of VE Integration
  • The two primary objectives of integrating VE and
  • the Five-Year planning process are
  • 1) Foster thorough planning and analysis to
    complete high quality construction and repair
    projects at an appropriate cost
  • 2) Use VE as a tool to limit project cost and
    schedule variance

Department of the Interior December 2007
10
Potential Revisions to DOI Requirements
  • The below revisions will be discussed by bureau
  • VE coordinators. Additional items may be added.
  • Define the project stage at which VE results are
    reported.
  • Clearly define the stage in project development
    at which VE is performed.

Department of the Interior December 2007
11
Potential Revisions to DOI Requirements
  • 3) Ensure construction Capital Planning and
    Investment Control (CPIC) guide identifies points
    in project life cycle to perform VE.
  • 4) Define application of VE to design/build
    projects.
  • 5) Consider raising the VE threshold to 1
    million from 500,000
  • - 1 million is minimum threshold per A-131

Department of the Interior December 2007
12
Potential Revisions to DOI Requirements
  • 6) Define how VE is applied to dam projects
  • 7) Acknowledge that sustainable building
    practices may justifiably increase some project
    costs to create environmental benefit
  • 8) Consider whether VE should be applied more
    rigorously to non-project work

Department of the Interior December 2007
13
Revision of Appendix Q
  • Appendix Q is the VE section of the construction
    CPIC guide
  • Core of the Appendix is Department Manual 369
    (VE)

Department of the Interior December 2007
14
Integration Process
  • Revise Department Manual Part 369 (VE)
  • Goal is for final revision June 1, 2008
  • Revise Appendix Q of the Construction CPIC Guide
  • Goal is for final revision June 1, 2008
  • Bureau VE coordinators will submit proposed
    revisions to both documents by January 22, 2008

Department of the Interior December 2007
15
Integration Process
  • Include revised VE requirements in Attachment G
    for the FY 2011- FY 2015 Five Year Plan
  • This guidance will be issued in FY 2008
  • Add a VE data field to the Project Data Sheet
    included in the FY 2011- FY 2015 Five Year Plan

Department of the Interior December 2007
16
Bureau VE Program Coordinators
  • DOI Bill Hamele
  • BIA Alan Roit
  • BLM Linda Force, Ed Giagni
  • BOR Norman Hyndman
  • FWS Marshall Wright
  • NPS Rich Turk
  • USGS Clarence (Bill) Fulk
  • Contact your coordinator with questions

Department of the Interior December 2007
17
  • Questions, Comments?

Department of the Interior December 2007
Write a Comment
User Comments (0)
About PowerShow.com