Title: 2' Phase: PLAN THE PROJECT
12. Phase PLAN THE PROJECT
- What? ? How?
- Work Breakdown Structure
- Estimation of resources
- Definition of dependencies between project
activities - Development of PERT diagram
- Assignment of responsibilities
2Work Breakdown Structure (WBS)
- Project - Hierarchical system (tree)
- Goal
- Objectives
- Workpackages
- ...
- Tasks
- Decomposition upside- down
3(No Transcript)
4Task
- S.M.A.R.T. Criterion
- Specific
- Measurable (costs, work, time)
- Assignable (responsibility)
- Realistic
- Time-related
5TASK DESCRIPTION
- Task ID, title, description
- Input (outcomes of other tasks)
- Title, type, description of a deliverable
- Start and end time
- Effort (e.g. in person-months)
- Costs
- Responsibility
6Example Conference planning
1. Conference programme 1.1 Define programme of
conference 1.2 Obtain speakers 1.3 Prepare
conference materials 1.3.1 Obtain presentations
from speakers 1.3.2 Prepare and print conference
materials
7Example Conference planning (2)
2. Set the conference site date 2.1 Set the
conference date 2.2 Select commit conference
site 2.3 Confirm arrangements
8Example Conference planning (3)
3. Develop marketing plan 3.1 Develop and print
conference brochure 3.2 Obtain Label Sets for
Direct mailing 3.3 Mail brochures 3.4 Receive
acknowledge registrations
9Duration of a Task
- Task duration Effort / No of persons
- Random character
- Average time of activity duration
- TA (O 4.M P) / 6
- O - optimistic completion time
- P - pesimistic
- M most likely completion time
10COSTS CATEGORIES
- Personnel costs
- Equipment
- Travel and subsistence
- Consumables
- Other direct costs
- Subcontracting
- Indirect Costs (overheads)
11SEQUENCING THE PROJECT ACTIVITIES
- Logical / time dependencies
- Types of dependencies
- Finish ? Start (Immediate predecessor)
- Finish ? Finish
- Start ? Start
- Start ? Finish
12Example Conference planning
Activity
Title
Imm. Pred.
A (2.1)
Date
-
B (1.1)
Programme
-
C (2.2)
Site
A
D (1.2)
Speakers
B
E (3.1)
Conf.broch.
C, D
C, D
F (3.2)
Database
13Example Conference planning (2)
Activity
Place
Imm.Pred.
G (3.3)
Mailing
E, F
H (1.3.1)
Obtain
D
I (3.4)
Process
G
J (2.3)
Finish
H, I
K (1.3.2)
Print
J
14 PERT DIAGRAM(Project Evaluation Review
Technique)
- NODE
- ID - activity identifier
- ES - earliest possible start
- EF - earliest possible finish
- LS - latest possible start
- LF - latest possible finish
- AD - activity duration
- TS - time slack
15NODE PERT
16Example Conference Planning
A
E
C
I
G
start
end
K
J
F
B
D
H
17USE OF PERT
- Locating the Critical Path (CP)
- Earliest possible time of finishing the project
- Determination of paralelly executable tasks
- View from bird perspective
18CRITICAL PATH
Critical path The longest path in PERT Delay of
activity delay on critical path ? prolongation of
the project duration
19CALCULATION OF THE CRITICAL PATH
ESk max EFi , i ? all imm. predecessors of the
node k EFk ESk ADk LFk min LSi , i ?
all nodes for which the node k is a
predecessor LSk LFk - ADk Activities on CP
have zero Time slack
20Example Conference Planning
4
4
0
2
2
7
11
20
A
2
C
5
E
9
4
6
6
11
11
20
20
22
22
28
G
I
2
6
4
20
22
22
28
11
16
29
31
28
29
end
F
K
J
5
2
1
start
15
20
29
31
28
29
13
11
15
5
11
0
5
H
D
B
4
6
5
24
28
5
11
0
5
21 APPLICATION OF PERT
- Planning activity scheduling, assigment team
members to tasks - Implementation realocation of resources
- Control Comparision of plan and current status
quo
22Project Proposal
- Problem definition, Aim of the project, approach
taken, expected benefits - Detailed description of project activities
(Workplan) - dates, resources, deliverables, ... - Budget, management structure, ...
- ? Depends on the type of the project
23PURPOSE OF THE PROJECT PROPOSAL
- Detailed project description (Request for Grant)
- Dynamic tool for project manager for decision
making - Reference document for project control
- Becoming familiar with the project
24TEAM ASSIGNMENT 2
- Develop a Project Proposal for the ACRU
Continuind Education Project addressing the
following items - WBS with brief description of each activity
- PERT diagram
- Budget
252nd Phase PROJECT PLAN Summary
- Work break down structure (Tasks - S.M.A.R.T.)
- Estimation of time and costs (duration, effort,
costs) - Sequencing of activities
- PERT diagram
- Determination of the critical path
- Project Proposal