Title: Dioxin Emissions in Candidate Countries
1Dioxin Emissions in Candidate Countries
Improving the knowledgeon dioxin emissions in
CCs A measurements strategyUlrich QuassIUTA
e.V., Duisburg, Germany
2Dioxin Emissions in Candidate Countries
Emission measurements within the project...
- WHY (Purpose of measurements)
- WHICH (selection of sources)
- WHAT (methodology)
- WHO (sampling teams, laboratories)
- WHEN (time schedule)
3Dioxin Emissions in Candidate Countries
WHY?
Check compliance with limit values
Evaluate and improve emission factors
P
Check potentially relevant sources
P
First results for unknown source types
P
Rise awareness
P
Capacity building in CCs
4Dioxin Emissions in Candidate Countries
WHICH?
Excluded source types
- Waste incinerators
- Diffuse non-industrial sources dom. burning,
vehicular emissions re-volatilsation of
PCDD/F fires
5Dioxin Emissions in Candidate Countries
WHICH?
Probably irrelevant sources, unless specific
indications
- Gas/oil power plants
- Coal power plants with DeSO2/DeNOx
- Blast oxygen furnaces
- Primary non-ferrous metal production
- Dry cement kilns without supplemental fuels
6Dioxin Emissions in Candidate Countries
WHICH?
Relevance Criteria
A. Stack gas concentration (ng I-TEQ/m³)
B. Annual emission (g I-TEQ/year)
7Dioxin Emissions in Candidate Countries
8Dioxin Emissions in Candidate Countries
WHICH?
Relevance Criteria (amended)
A. Stack gas concentration (ng I-TEQ/m³)
B. Annual emission (g I-TEQ/year)
C. Stack height (for low flow/ high
concentration sources)
9Dioxin Emissions in Candidate Countries
WHAT?
Waste incineration Directive
sampling time typ. 6 hours (8 h max) analysis
with HRGC/HRMS
10Dioxin Emissions in Candidate Countries
Cost minimisation by...
11Dioxin Emissions in Candidate Countries
...methodological simplification
Stack sampling2-day campaigns, max. three
2(3)-hour samples
Analysis 1st sample extract split into two
fractions
- HRGC/HRMS (exact I-TEQ- determination)
- simpler GC/MS (order of magnitude)
2nd/3rd sample
- Simple analysis or
- analysis only in case of discrepancies
12Dioxin Emissions in Candidate Countries
WHO?
A. Sampling
Needed experienced teams (proof required)
1. preference companies/institutes from CCs
2. preference co-operative activities CC/EU 15
3. preference companies/institutes from EU 15
13Dioxin Emissions in Candidate Countries
WHO?
B. Analysis
Favourable CC based institutes
Needs
- experienced laboratories (proof required)
- good co-operation with sampling team
- QC analysis by independent lab (e.g. TNO, IUTA
or other)
14Dioxin Emissions in Candidate Countries
WHEN?
Mar- July 03 proposals of sources (CC
institutions)
- Not yet measured, operators permit available
July-Aug 03 priority list/preliminary work
plan/call for tenders (TNO/IUTA/DG ENV/JRC)
15Dioxin Emissions in Candidate Countries
WHEN?
Sept 03 decision on work plan/commitments
Sept-Nov 03 First phase of measurements
Mar Sept 04 Second phase of measurements
Oct 31st, 04deadline for measurement reports