Title: Low Cost Evaluations
1Low Cost Evaluations
TRAFFIC SAFETY SYSTEMS MANAGEMENT SECTION -
Shawn A. Troy, PE North Carolina DOT - Traffic
Engineering Branch
Low Cost Pooled Fund TAC Meeting June 20, 2007
2Directional Crossover - 1
- Problem Statement
- High volume of traffic on mainline
- Vehicles attempt left turns from the side road
- Resulting in high number of crashes at the
location - Signal not considered due to signals on either
side of intersection within 600 - Countermeasure
- Installation of a Directional Crossover
- Cost 55,000
- Project completion - June 30, 2000
- 5 Years and 7 Months - Before and After Data
3Directional Crossover - 1
4Directional Crossover - 1
Looking East on Main
Looking East on Main
Picture 1
Picture 2
Looking East on Main
Looking West on Main
Picture 3
Picture 4
5Directional Crossover - 1
Before Collision Diagram
6Directional Crossover - 1
After Collision Diagram
7Directional Crossover - 1
8Directional Crossover - 1
Picture 1
Picture 2
Picture 3
Picture 4
9Directional Crossover - 1
10Directional Crossover - 2
- Problem Statement
- Congestion and high volume of traffic at the
intersection - Vehicles attempt left turns from the side road
- Resulting in high number of crashes at the
location - Countermeasure
- Installation of a Directional Crossover
- Cost 30,000
- Project completion - April 9, 1999
- 6 Years and 10 Months - Before and After Data
11Directional Crossover - 2
12Directional Crossover - 2
Looking South on US 158
Looking South on US 158
Picture 1
Picture 2
Looking South on US 158
Looking South on US 158
Picture 3
Picture 4
13Directional Crossover - 2
Looking North on US 158
Looking North on US 158
Picture 1
Picture 2
Looking North on US 158
Looking North on US 158
Picture 4
Picture 3
14Directional Crossover - 2
Before Collision Diagram
15Directional Crossover - 2
After Collision Diagram
16Directional Crossover - 2
17Directional Crossover - 2
Picture 1
Picture 2
18Directional Crossover - 2
Picture 1
Picture 2
19Directional Crossover - 2
Before Collision Diagram
20Directional Crossover - 2
After Collision Diagram
21Directional Crossover - 2
22Directional Crossover - 2
23Centerline Rumble Strips
- Problem Statement
- 11.5 mile segment of rural 2-lane roadway
- Section bordered on North and South by 4-lane
divided roadway segments - North is a 65 mph full control access segment
- South is a 55 mph partial control access segment
- Construction began in December 4, 2004 to convert
2-lane segment to 4-lane divided roadway to match
North and South segments - During first 6 months of construction - 4 Fatal
Head-On Crashes occurred
24Centerline Rumble Strips
Picture 1
Picture 2
25Centerline Rumble Strips
- Fatal Crash History
- January 1999 through June 2005
26Centerline Rumble Strips
- Countermeasure
- Installation of Centerline Rumble Strips for the
remainder of the construction project - Centerline rumble strips were installed in 5 days
between July 19-28, 2005 - Total cost for the installation of milled rumble
strips, traffic control and motorcyclist signing
was 34,388
27Centerline Rumble Strips
Picture 1
Picture 2
Picture 3
Picture 4
28Centerline Rumble Strips
Picture 2
Picture 1
Picture 3
Picture 4
29Centerline Rumble Strips
Picture 2
Picture 1
Picture 3
Picture 4
30Centerline Rumble Strips
31Safety Evaluations
- Safety Evaluation Group
- 2004 15 projects 15
- 2005 95 projects (10 to be complete) 105
- 2006 102 projects (5 to be complete) 107
- 2007 41 projects (145 to be complete) 186
- Above are projects completed through 2002 - 102
projects will be assigned from the 2003
completions - 190 Spot Safety project evaluations are on the
web that were completed through December 31,
2006 - http//www.ncdot.org/doh/preconstruct/traffic/Safe
ty/ses/projects/completed.html
32AASHTO TIG-CMB
- Key Topic Areas
- Contact Information
- Background and Problem Identification
- Roadway Design Issues
- Maintenance Issues
- Benefits and Evaluation
- System Threats
- Barrier Design
33Contact Information
Shawn A. Troy, PE (919) 773-2897 stroy_at_dot.stat
e.nc.us
Traffic Safety Unit Website http//www.ncdot.or
g/doh/preconstruct/traffic/TSU/default.html