Low Cost Evaluations - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Low Cost Evaluations

Description:

Low Cost Evaluations – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 34
Provided by: trafficen
Category:
Tags: cost | evaluations | low

less

Transcript and Presenter's Notes

Title: Low Cost Evaluations


1
Low Cost Evaluations
TRAFFIC SAFETY SYSTEMS MANAGEMENT SECTION -
Shawn A. Troy, PE North Carolina DOT - Traffic
Engineering Branch
Low Cost Pooled Fund TAC Meeting June 20, 2007
2
Directional Crossover - 1
  • Problem Statement
  • High volume of traffic on mainline
  • Vehicles attempt left turns from the side road
  • Resulting in high number of crashes at the
    location
  • Signal not considered due to signals on either
    side of intersection within 600
  • Countermeasure
  • Installation of a Directional Crossover
  • Cost 55,000
  • Project completion - June 30, 2000
  • 5 Years and 7 Months - Before and After Data

3
Directional Crossover - 1
4
Directional Crossover - 1
Looking East on Main
Looking East on Main
Picture 1
Picture 2
Looking East on Main
Looking West on Main
Picture 3
Picture 4
5
Directional Crossover - 1
Before Collision Diagram
6
Directional Crossover - 1
After Collision Diagram
7
Directional Crossover - 1
  • Results

8
Directional Crossover - 1
Picture 1
Picture 2
Picture 3
Picture 4
9
Directional Crossover - 1
10
Directional Crossover - 2
  • Problem Statement
  • Congestion and high volume of traffic at the
    intersection
  • Vehicles attempt left turns from the side road
  • Resulting in high number of crashes at the
    location
  • Countermeasure
  • Installation of a Directional Crossover
  • Cost 30,000
  • Project completion - April 9, 1999
  • 6 Years and 10 Months - Before and After Data

11
Directional Crossover - 2
12
Directional Crossover - 2
Looking South on US 158
Looking South on US 158
Picture 1
Picture 2
Looking South on US 158
Looking South on US 158
Picture 3
Picture 4
13
Directional Crossover - 2
Looking North on US 158
Looking North on US 158
Picture 1
Picture 2
Looking North on US 158
Looking North on US 158
Picture 4
Picture 3
14
Directional Crossover - 2
Before Collision Diagram
15
Directional Crossover - 2
After Collision Diagram
16
Directional Crossover - 2
  • Results

17
Directional Crossover - 2
Picture 1
Picture 2
18
Directional Crossover - 2
Picture 1
Picture 2
19
Directional Crossover - 2
Before Collision Diagram
20
Directional Crossover - 2
After Collision Diagram
21
Directional Crossover - 2
  • Results

22
Directional Crossover - 2
23
Centerline Rumble Strips
  • Problem Statement
  • 11.5 mile segment of rural 2-lane roadway
  • Section bordered on North and South by 4-lane
    divided roadway segments
  • North is a 65 mph full control access segment
  • South is a 55 mph partial control access segment
  • Construction began in December 4, 2004 to convert
    2-lane segment to 4-lane divided roadway to match
    North and South segments
  • During first 6 months of construction - 4 Fatal
    Head-On Crashes occurred

24
Centerline Rumble Strips
Picture 1
Picture 2
25
Centerline Rumble Strips
  • Fatal Crash History
  • January 1999 through June 2005

26
Centerline Rumble Strips
  • Countermeasure
  • Installation of Centerline Rumble Strips for the
    remainder of the construction project
  • Centerline rumble strips were installed in 5 days
    between July 19-28, 2005
  • Total cost for the installation of milled rumble
    strips, traffic control and motorcyclist signing
    was 34,388

27
Centerline Rumble Strips
Picture 1
Picture 2
Picture 3
Picture 4
28
Centerline Rumble Strips
Picture 2
Picture 1
Picture 3
Picture 4
29
Centerline Rumble Strips
Picture 2
Picture 1
Picture 3
Picture 4
30
Centerline Rumble Strips
  • Results

31
Safety Evaluations
  • Safety Evaluation Group
  • 2004 15 projects 15
  • 2005 95 projects (10 to be complete) 105
  • 2006 102 projects (5 to be complete) 107
  • 2007 41 projects (145 to be complete) 186
  • Above are projects completed through 2002 - 102
    projects will be assigned from the 2003
    completions
  • 190 Spot Safety project evaluations are on the
    web that were completed through December 31,
    2006
  • http//www.ncdot.org/doh/preconstruct/traffic/Safe
    ty/ses/projects/completed.html

32
AASHTO TIG-CMB
  • Key Topic Areas
  • Contact Information
  • Background and Problem Identification
  • Roadway Design Issues
  • Maintenance Issues
  • Benefits and Evaluation
  • System Threats
  • Barrier Design

33
Contact Information
Shawn A. Troy, PE (919) 773-2897 stroy_at_dot.stat
e.nc.us
Traffic Safety Unit Website http//www.ncdot.or
g/doh/preconstruct/traffic/TSU/default.html
Write a Comment
User Comments (0)
About PowerShow.com