Low Cost Safety Improvements Pooled Fund Study
  • Combination Centerline and Edgeline Rumble Strips

Dr. Frank Gross, VHB
2
Overview
  • Background
  • Missouris Program
  • Status of Data Collection
  • Remaining Data Needs
  • Evaluation Considerations

3
Background
  • Singe-vehicle ROR Crashes
  • 39 percent of all fatal crashes (FARS, 1999)
  • Included in Several NCHRP 500 Series Guidebooks
  • Run Off Road, Head-on, Heavy Trucks, and
    Horizontal Curves
  • Run-Off Road Guidebook
  • 3 Experimental Strategies
  • Edge line profile marking
  • Edge line rumble strips
  • Modified shoulder rumble strips
  • (narrow or no paved shoulder)
  • Ranked 1st in Phase I
  • Low cost and short implementation timeframe (lt 1
    year)

4
Background
  • Head-on Guidebook
  • Install centerline rumble strips
  • Tried strategy
  • Ranked 3rd in Phase II
  • Low cost
  • Short implementation timeframe (lt 1 year)
  • Heavy Trucks and Horizontal Curve Guides
  • Shoulder and centerline rumble strips
  • Low to moderate costs
  • Short to medium implementation timeframe (1-2
    years)
  • Heavy-vehicle drivers and horizontal curves

5
Background
  • Dual Application
  • Combination of centerline and edge line rumble
    strips
  • Not included in NCHRP 500 Series
  • Identified by Technical Advisory Committee
  • NCHRP 17-32 Survey Results
  • Approximately 200 miles
  • 9 States
  • AZ, ID, KY, MO, OR, TX, UT, WA, WY

6
Missouri DOT Program
  • Missouri DOT Better Roads Brighter Future
  • Improve 85 percent of major route system in 5
    years
  • Part of Program Install Dual Rumble Strips
  • Two predominant roadway types
  • 4-lane divided expressways
  • 2-lane roadways.
  • Includes both rumble strips and stripes
  • Mostly stripes
  • Stripes are placed on the edge line
  • Posted speed limits 55-65 mph

7
Missouri DOT Program
  • Proposed Strategy Sites for FY 2007-2011
  • 1170 miles (170 sites for 2007)
  • 543 miles (75 sites for 2008)
  • 2351 miles (329 sites for 2009-2011)
  • Additional Improvements
  • Surface improvements (overlay)
  • Shoulder improvements (upgrade to 4 where
    possible)
  • Others (sign upgrades where necessary)

8
Status of Data Collection
  • Missouri
  • Planned installations
  • Those for SFY 2007 have begun
  • MO DOT provided roadway/traffic data
  • 2002 2005
  • MO DOT provided crash database
  • 1997 2005

9
Remaining Data Needs
  • MO Reference Sites
  • Sites planned for treatment in later years
  • Additional States
  • Proactive evaluation
  • States planning to install combination rumble
    strips

10
Evaluation of Dual Application
  • Crash Based Evaluation in MO
  • Proactive before/after evaluation
  • Evaluate sample of installations
  • Disaggregate analysis
  • Roadway type
  • Night and weather conditions

11
Evaluation Considerations
  • Disaggregate analysis
  • Functional class
  • Night and weather conditions
  • Including other states in evaluation
  • 4 States are Technical Advisory Committee Members