Title: ProDFM Lecture
1Title
A Worksheet Tool for DFM and Cost Analysis in the
NPD Process
www.cloversoft.net
2DFM Introduction
- Design for Manufacturability (DFM) may be
described as a method for evaluating product
designs so as to identify likely manufacturing
cost drivers, and then leading to solutions for
the mitigation of these cost drivers. - DFM emphasizes cross functional integration and
early evaluation of downstream manufacturing
issues. DFM analysis must therefore be
integrated into the New Product Development (NPD)
process. Further the DFM metrics must be linked
to one or more NPD stage-gates. - The use of DFM techniques early in the design
cycle results in shorter design delays, easy
production transitions, and higher product
quality.
3Integrating DFM in the NPD Process
- An effective NPD/DFM analysis requires that the
following three sequential events occur in an
efficient manner - 1. Capture and deploy all new design and
production related data to the NPD team - 2. Evaluate, quantify and document the
manufacturability of the proposed design - 3. Integrate the manufacturability evaluation
into cost estimating. - Pro-DFM is a worksheet based tool that
facilitates the accomplishment of these three
events. - Pro-DFM provides accurate production cost
estimates with little analytical effort. It is
based on a parametric cost model which focuses on
the primary drivers of cost.
4Key Metrics Generated
- The goal of Pro-DFM is to provide the NPD team
with an accurate estimate of the unit production
cost, and then facilitate the reduction of this
cost. Using Pro-DFM you will generate the
following key metrics. These will be used by the
NPD team to evaluate and monitor DFM initiatives. - Estimated Unit Production (EUP) Cost - The EUP
Cost is what Pro-DFM estimates it will cost to
make the new product. It starts with the Direct
Part Cost (as provided by vendor quotes or plant
estimating) and then progressively scales this
cost for inventory and considers all DFM Eval
factors plus any supply chain costs. - (ii) Inventory Penalty Cost - Projects the
likely additional costs for maintaining the
needed parts inventory. An Inventory Eval Factor
( 0 to 1 range) is first derived on the basis of
weeks of supply and number of part variants. In
the extreme case where the factor is 1, the part
cost is doubled.
5Key Metrics Generated
(iii) DFM Part Evaluation Penalty - Projects the
likely additional costs in the processing of this
part. A DFM Part Eval Factor (0-1 range) is
derived on the basis of NPD team responses to a
set of scaled response queries. These queries are
divided into three criteria Procurement, Part
Handling, and Part Geometry. (iv) DFM Assembly
Evaluation Penalty - Projects the likely
additional costs in the execution of this
assembly step. A DFM Process Eval Factor (0-1
range) is first. The evaluation queries are
divided into seven criteria Process Difficulty,
Equipment Needs, Tooling Needs, Process Setup,
Handling, Inventory and Quality Control. (v) DFM
Part Reduction Opportunity Projects the likely
percent reduction in direct part costs by
eliminating parts. Is based on the likelihood
that individual parts can be eliminated. Where
the opportunity is close to zero then the NPD
team need not focus on part reduction.
6Pro-DFM A Simple Analysis
- A key problem with traditional DFM analysis is
that it tends to be cumbersome and requires an
extensive effort from an experienced user group. - This makes the cost and effort difficult to
justify, for most NPD projects. As a result in
many cases DFM analysis is only being done by
large company design groups. - Pro-DFM solves this problem by proposing a simple
and time-tested approach to DFM analysis. This
simplicity is achieved by using the following two
strategies - - A Multi Factor Scaled Response Model
- - A MS-Excel Based Worksheet
7A Multi Factor Scaled Response Model
- Pro-DFM analyses three different factors (i)
parts, (ii) assembly processes, and (iii)
inventory. Each of these is independently
analyzed using multiple criteria, with each
criterion being further divided into
sub-criteria. - The evaluation metrics are presented in the form
of simple queries, with an anchored response
scale. The NPD team selects the relevant
response. - This approach bypasses the traditional DFM use of
a rigid knowledge base, and automatically adapts
Pro-DFM for each company.
8DFM Part Evaluation
DFM Part Eval Factor (DPi) Projects the likely
additional costs in the processing of this part.
9DFM Part Evaluation
- Each sub-criterion is evaluated on a 0 (none) to
10 (max penalty) score using an anchored scale. - Use your judgment to select the score that best
represents the specific situation. If there is
insufficient data to evaluate then select 0. - Empirical evidence suggests that DFM issues could
effect part cost by as much 50 -
- DPi indicates the cost penalty assigned to the
part. If a part is expected to cost 1.50 and DPi
0.50, then Pro-DFM projects that a more accurate
cost estimate is 1.50 (10.50) 2.25.
Criterion Part Handling Sub-Criterion Part Feed
Automation Response Scale Part feeding into
assembly machines will be (0-2) Automatic on
existing equipment (2-5) Automatic needs new
equipment (4-8) Manual assisted feeding (5-10)
100 Manual feeding
DPi 0.5 Sk Wk Xik/90 Where i1,..,N
Parts in the assembly k1,..,9 Part eval
sub-criteria. Wk Sub-criteria weight (0 to
1) Xik Part DFM evaluation scores
10DFM Assembly Process Evaluation
DFM Assembly Process Eval Factor (DAj)
Projects the likely additional costs in the
execution of this assembly step
11DFM Assembly Process Evaluation
- Each sub-criterion is evaluated similar to the
part evaluation. - Empirical evidence suggests that DFM issues could
effect the assembly process cost by as much 70 - DAj indicates the cost penalty assigned to the
assembly process step. If the direct assembly
process cost is expected to cost 0.80 and DAj
0.40, then Pro-DFM projects that a more accurate
cost estimate is 0.80 (10.40) 1.12.
Criterion Setup Sub-Criterion
Commonality Response Scale Setup process that
is common to similar products(0) 100
commonality(1-3) 80 to 100 commonality(4-7) 50
to 80 commonality(8-10) lt 50 commonality
DAj 0.7 Sp Vp Yjp/190 Where j1,..,M
Steps in the assembly p1,..,19 Assembly eval
sub-criteria. Vp Sub-criteria weight (0 to
1) Yjp Assembly DFM eval scores
12Inventory Evaluation
Inventory Eval Factor (DVi) Projects the
likely additional costs for maintaining the
needed parts inventory
DVi 0.4(Bi-1)/10 0.6Si/52 Where i1,.
.,N Parts in the assembly Bi Number of part
variants (color, etc.) Si Projected weeks of
supply per order
- The inventory requirements for a part are often a
function of several design parameters. - When a part has many variants on the basis of
color, size, labels, etc., this can have a
significant impact on inventory levels. - The part type (material, production process,
etc.) will influence the order batch size and
hence the weeks of supply to be inventoried.
13Estimated Unit Production (EUP) Cost
The EUP cost derivation considers all DFM Eval
factors plus other factors as shown below. EUP
COST Direct Part Cost (i) (DPi DVi
Indirect Rate) Inbound Supply Chain Direct
Assembly Cost (j) (DAj Indirect Rate)
Outbound Supply Chain
14DFM Part Reduction Opportunity
- The assessment is based on the likelihood a part
can be eliminated and why. For each part you will
select from the list of reasons the most
applicable reason. - The likelihood evaluations are used to derive the
Part Reduction Opportunity as follows - PElimination(i) x Direct Part Cost(i) / Total
Direct Part Cost
Prob of Reason Elimination (0.0) No -
Provides Primary FR" (0.0) No - Motion
Requirements" (0.2) No - Material
Restrictions" (0.3) No - Assembly
Restrictions" (0.4) Yes - Possible to Transfer
FR" (0.5) Yes - Possible to Reduce
Count" (0.7) Yes - Easy to Transfer
FR" (0.8) Yes - FR maybe Eliminated" (1.0) Yes
- Redundant FR" (0.0) No - Unable to Evaluate"
15A MS-Excel Based Worksheet
- Pro-DFM is based on the popular MS-Excel
program and therefore requires minimal training.
MS-Excel provides a familiar interface and file
portability. - The Pro-DFM software is organized into a series
of 14 worksheets. All sheets are linked together
by our backend macro program. - Data is entered through pop-up windows, and the
worksheets are automatically updated.
Pro-DFM Worksheets FRONT 1. NPD/DFM Analysis
Cover Page 2. DFM Action Item Log REPORTS 3. NPD
/DFM Exec Summary Report 4. EUP Cost
Report 5. Analysis of Prod Cost by Plant 6. DFM
Evaluation Summary Report DATA 7. Part/Material
Data 8. DFM Part Evaluation Data 9. Assembly
Process Data 10. DFM Process Evaluation
Data 11. Assembly Process CostCalc 12. Supply
Chain Costs 13. Alternate Plant HELP 14. Defini
tions Help
16Data Requirements
- Listed here are the data required for creating a
Pro-DFM file and running the analysis. - You need not wait to have all the data to start
the analysis. - Most of the analytical components use numerical
data. Where the data is not available enter the
default (usually zero) value. - Pro-DFM also promotes data transparency in the
NPD team. Some data is recorded for this purpose
and not used in the DFM or costing analysis (e.g.
Quality Requirements). This data, though, is
found to promote a more reliable DFM evaluation. - The development time data is used to support
project planning and estimate what design changes
can be made without effecting the end date.
- PART DATA
- Product BOM including material specs
- Design drawings or schematics
- Part function and key features
- Test method specs
- Quality control specs
- Inventory supply chain data
- Development time
- ASSEMBLY PROCESS DATA
- Assembly process plan
- Tooling requirements
- Equipment requirements
- Labor and Equipment unit utilization times
- Setup times
- Quality rejection rates
- Production volumes and unit batch sizes
- Development time
17Adding Parts
Step 1 Add parts to your Pro-DFM file. A part
will typically be a BOM item retrieved from the
product specifications.
Step 2 Complete the DFM evaluation of all
added parts. You can view the anchor scales for
each sub-criterion as you enter the evaluation.
18Adding Assembly Process Steps
Step 4 Complete the DFM evaluation of all
added assembly steps.
Step 3 Add assembly process steps to your
Pro-DFM file. The steps can be retrieved from a
process plan document.
19CostCalc Utility for Assembly Process Costs
For each assembly step you can either directly
enter the hourly costs or derive it using the
inbuilt Pro-DFM CostCalc utility. LABOR
DETAILS Can add up to 4 operators. For each
operator specify the (i) Hourly Rate (ii)
Productivity - relative to benchmark production
rate and (iii) Busy Time - what of time is
dedicated to this step, if he operates 2 machines
then 50, if he works for 10 minutes in a 100
minute run then 10. EQUIPMENT DETAILS Can add
up to 3 equipment. For each equipment specify the
(i) Hourly Run Rate - cost to operate the machine
minus labor (ii) Utilization - of run time that
the machine is busy on this step, if a blender is
needed for 5 minutes in a 50 minute step then 10
and (iii) Setup Time - time to setup a batch run.
20Example Pencil Sharpener
The design of an electric pencil sharpener (shown
below) will be used to demonstrate the use of the
Pro-DFM software. There are 20 parts and 4
assembly process steps. The design is based on a
common model that is readily available in any
office supply store (e.g. Staples). This product
has an average retail price of price of 11.50.
The target EUP price should therefore be 5.75.
21EUP Cost Report
Provides summarized costing details for each part
and each assembly process step. Lets you see the
cost roll-up and cost significant parts and
assembly process steps. Provides a starting point
for direct cost reduction initiatives. The DFM
and Inventory penalties are listed. DFM
activities initiatives should initially focus on
the highest penalties.
22EUP Cost Report
23EUP Cost Report
24DFM Evaluation Summary Report
Provides aggregated details of the DFM
Evaluation. First part aggregates the part and
process evaluation responses. Displays the
average and maximum scores, plus alert frequency.
An alert is issued when the score to any response
is above your specific alert limit. Second part
is divided into DFP Part Analytics and DFM
Process Analytics. Presents data graphically and
identifies the part and process with highest DFM
scores, plus the most penalized DFM criterion.
25DFM Evaluation Summary Report
26NPD/DFM Executive Summary Report
Summarizes the results of the DFM and cost
analysis, and should be reviewed first by the NPD
team. Divided into the following sections (i)
Unit Production Cost Summary, (ii) Development
Time Summary, (iii) DFM Evaluation Summary, (iv)
Production Cost Analytics, and (v) Design
Development Time Line.
27NPD/DFM Executive Summary Report
28NPD/DFM Executive Summary Report
29Getting Started
- Following this brief introduction you are now
ready to start a Pro-DFM project. You will be
provided with the following files - 1 ProDFM-2 - This file is of the type MS-Excel
Add-in (.xla extension), and requires MS-Excel
XP or later to run. - 2. Pencil Sharpener A MS-Excel file
- 3. ProDFM User Manual A .pdf file
- Please read the User Manual to learn how each
function is performed. Print out Sheet.14 Help so
that you can quickly reference all the
definitions. - We recommend that you browse through the Pro-DFM
example provided to you (Pencil Sharpener file)
to familiarize yourself with the different
worksheets and the associated data requirements. - Create an appropriately named folder on your
computer and transfer the ProDFM-2 file to this
folder.