TURNAROUND PLANNING - PowerPoint PPT Presentation

1 / 61
About This Presentation
Title:

TURNAROUND PLANNING

Description:

'THE FOUR HOUR HOUSE. DISCUSSION/TEAM BUILDING. SAFETY. JOE SELF, HUNTSMAN. MAY 8, 2003 ... Detailed field logistics (Where to put trailers, laydown areas, etc. ... – PowerPoint PPT presentation

Number of Views:532
Avg rating:3.0/5.0
Slides: 62
Provided by: joed8
Category:

less

Transcript and Presenter's Notes

Title: TURNAROUND PLANNING


1
TURNAROUND PLANNING EXECUTION FORUM
CONSTRUCTION INDUSTRIES INSTITUTE of the GOLDEN
TRIANGLE BUSINESS ROUNDTABLE MAY 8, 2003
2
AGENDA
  • INTRODUCTION
  • WALTER ALMON, DUPONT
  • ANDY BULLOCK, HUNTSMAN
  • THE FOUR HOUR HOUSE
  • DISCUSSION/TEAM BUILDING
  • SAFETY
  • JOE SELF, HUNTSMAN

3
AGENDACONTINUED
  • WORKSCOPE DEVELOPMENT
  • MIKE FORSE, PREMCOR
  • PLANNING/SCHEDULING
  • STEVE HENDERSON, ATOFINA
  • BREAK!!
  • MOBILIZATION ONBOARDING
  • ANDY BRISENDINE, ECHO MAINT.

4
AGENDACONTINUED
  • WORK EXECUTION PERMITTING ISSUES
  • BILL HARRINGTON, CONEX
  • SKILLS ASSESSMENT
  • WALTER ALMON, DUPONT
  • CLOSING STATEMENTS
  • WRAP-UP
  • NOON LUNCH!

5
PANELIST
  • MARK BRITTAIN
  • INTERNATIONAL MAINTENANCE CORPORATION
  • 722-8031 x222

6
TURNAROUND SAFETY
  • JOE SELF
  • HUNTSMAN
  • 723-3979

7
Items To Be Considered
Resources - People Planning Scheduling Safety
Contract Strategy
Information contained herein was taken from a
study conducted by the Construction Industry
Institute - 2002 Construction Project Improvement
Conference
8
Resources - People
Prior To Shutdown, When Does The Hiring Of
Workers Begin?
Recordable Incident Rate Less Than 2 Weeks
Before 0.58 Two To Six Weeks Before 0.22
9
Resources - People
Where Do Workers Come From?
Recordable Incident Rate Available Workers Not
Familiar With The Work 2.28 Transferred
Workers Familiar With The Work 0.47
10
Planning Scheduling
Was Software Used To Schedule The Project?
Recordable Incident Rate No 2.92 Yes
0.72
11
Planning Scheduling
What Unit Of Time Was Used On Project Schedule?
Recordable Incident Rate Days 1.51 Shifts
0.68 Hours 0.45
12
People,Planning Scheduling
Combined Worker Familiarity Scheduling By The
Hour
Recordable Incident Rate Not Familiar, Not
Hours 1.75 Familiar Or Scheduled By
Hours 1.08 Familiar Scheduled By
Hours 0.28
13
Planning Scheduling
Days Worked Each Week
Recordable Incident Rate 7 Days 0.96 6
Days 0.67
14
Planning Scheduling
Typical Shutdown Duration
Recordable Incident Rate 2 To 8
Weeks 1.20 Less Than 2 Weeks 0.62
15
Planning Scheduling
Combined Shutdown Duration Days Worked Each
Week
Recordable Incident Rate At Least 4 Weeks At 7
Days Per Week 1.34 Less Than 2 Weeks 6 Days
Per Week 0.38
16
Planning Scheduling
Crew Size
Recordable Incident Rate Over 12
Workers 1.62 7 Or Less 0.55
17
Safety Contract Strategy
Shutdowns, Turnarounds Outages With Safety
Incentive Contracts
Recordable Incident Rate No Contractual Safety
Incentive 1.73 Fee-Impacted Safety
Performance 0.71
18
TURNAROUND SCOPE OF WORK DEVELOPMENT
  • MIKE FORSE
  • PREMCOR
  • 985-1685

19
  • WORK SCOPE DEVELOPMENT IS ONE OF THE KEY ELEMENTS
    IN THE TURNAROUND PROCESS
  • Cost
  • Duration
  • Execution/Contracting strategy
  • Future Unit availability
  • Turnaround frequency

20
  • WORK SCOPE DEVELOPMENT IS
  • THE PROCESS
  • Identifying mechanical jobs
  • Process items
  • Project work

21
  • REASONS TO EXCLUDE WORK ITEMS
  • More effective and efficient to perform work
    outside of the turnaround
  • Additional supervision and overhead cost

22
  • REQUIREMENTS OF A JOB REQUEST
  • Have at least one sponsor
  • Screened and challenged
  • Support the business objective
  • Approved by the unit turnaround team

23
  • PRIMARY SOURCES OF WORK
  • Previous turnaround summary reports
  • Work order backlogs
  • Inspection Engineering
  • Operations
  • Regulatory inspections
  • Process improvement projects
  • Unit shutdown and startup preparation

24
  • MILESTONE CHART FOR SCOPE DEVELOPMENT
  • Identify sources of information
  • Date needed and why
  • Establish and communicate a freeze date

25
  • ADDITIONAL WORK PROCEDURES
  • Job cost / Manpower impact
  • Job duration/Impact on schedule
  • Job category-
  • Management approval

26
  • MAJOR SCOPE CHANGES
  • INCREASE COST
  • Increase planning cost
  • Engineering cost
  • Material cost
  • Manpower cost

27
  • THE WORK SCOPE HAS THE LARGEST IMPACT ON
    TURNAROUND
  • Cost
  • Unit down time
  • Loss profit opportunity

28
  • MAJOR KEYS FOR A SUCCESSFUL TURNAROUND
  • Good scope development
  • Good extra work process
  • Buy-in from all departments

29
TURNAROUND PLANNING AND SCHEDULING
  • STEVE HENDERSON
  • ATOFINA
  • 963-6888

30
Turnaround Planning and Scheduling
  • Long Range Planning
  • Short Term Planning
  • Planning and Scheduling during the Turnaround.
  • Post Turnaround

31
Long Range Planning
  • Coordination with upstream and downstream
  • Raw Materials Purchasing and Disposition
  • Product Sales and Disposition
  • Industry economics
  • Set Turnaround Budget (Based on historical and
    known work)
  • Integrate Capital Projects
  • Develop Key Performance Indicators
  • Contracting Strategies
  • Develop Work Scope Criteria and Responsibilities

32
Short Term Planning
  • Risk rank Turnaround jobs
  • Detailed work scopes and estimates
  • Determine the length of the outage
  • Detailed schedule including
  • Operations turnover of equipment
  • Pre/Post Turnaround
  • Turnaround Execution
  • Detailed field logistics (Where to put trailers,
    laydown areas, etc.)
  • Organization structure for Turnaround execution

33
Planning and Scheduling during the Turnaround
  • Planning
  • Track and forecast cost
  • Provide field support for job scope, contract
    issues and extras
  • Scheduling
  • Track Critical Path
  • Track status of equipment
  • Project completion date

34
Post Turnaround Planning
  • Modify tracking steps based on actual
    information
  • Review methodology used to determine if the work
    could have been done more efficiently
  • Check logistics plans and other peripheral
    components for needed modifications
  • Hold critique meeting with all areas involved to
    determine areas for improvement

35
TURNAROUND MOBILIZATION ONBOARDING
  • ANDY BRISENDINE
  • ECHO MAINTENANCE
  • 724-1512

36
Turnaround Mobilization
  • Client
  • Award Contract
  • Contractor
  • Several Weeks In Advance

37
Safety
  • Clients Safety Procedure
  • Contractor To Have Enough Time To Know And
    Understand

38
Permitting Procedures
  • Clients Operations
  • Contractor To Interface With Operations

39
Scope
  • Client To Have Definitive Scope
  • Contractors Supervision To Be Onboard In Advance

40
ISTC
  • Clients Scan System
  • Contractor To Be Able To Apply For Scan Cards In
    Advance

41
Background Check
  • Clients Position
  • Contractors Position

42
Pre-Turnaround
  • Client
  • Contractor To Perform All Of The Work

43
Job Site
  • Client To Establish
  • Contractors View

44
TURNAROUND WORK EXECUTION PERMITTING ISSUES
BILL HARRINGTONCONEX866-9888 X102
45
EFFECTIVE STAFFING
1. Setting Contractor Milestones 2. Setting
Inspection Milestones 3. Critical Path
Management Productivity
46
PRE-TURNAROUND PREPARATION
1. Team to Learn Scope Early 2.
Verification of Onsite Materials 3.
Identification of Potential Conflicts 4.
Review of Rigging Plans and Safety Procedures
47
PERMITTING
Assuring Compliance
1. Supervision to Review Written Policy 2.
Pre-Turnaround Permit Meeting with
Supervision 3. Pre-Job Walkthrough (
Foreman Permit Issuer) 4. Mutual
Understanding
48
SKILLS ASSESSMENT
WALTER ALMONDUPONT727-9129
49
SKILL ASSESSMENTSBORN OF NECESSITY
  • BEFORE OSHA 29 CFR 1910.119
  • MANY INCIDENTS ALONG GULF COAST
  • - PHILLIPS, ARCO, ARCADIA, CONOCO, CITGO

50
OSHA REGULATIONSBORN OF NECESSITY
  • PER OSHA 29 CFR 1910.119(h)(3)(i)
  • CONTRACTOR EMPLOYER RESPONSIBILITIES
  • THE CONTRACT EMPLOYER SHALL ASSURE THAT EACH
    CONTRACT EMPLOYEE IS TRAINED IN THE WORK
    PRACTICES NECESSARY TO SAFELY PERFORM HIS/HER
    JOB.

51
OSHA REGULATIONSBORN OF NECESSITYCONTINUED
  • PER OSHA 29 CFR 1910.119(h)(2)(v)
  • EMPLOYER RESPONSIBILITIES
  • THE EMPLOYER SHALL PERIODICALLY EVALUATE THE
    PERFORMANCE OF CONTRACT EMPLOYERS IN FULFILLING
    THEIR OBLIGATIONS AS SPECIFIED IN PARAGRAPH (h)
    (3) OF THIS SECTION.

52
OBJECTIVE
  • ENSURE THAT CRAFTSPERSONS ARE SKILLED IN THIS
    REGION
  • MEET PROCESS SAFETY MANAGEMENT
  • PER OSHA 1910.119

53
OBJECTIVE- CONTINUED
  • SYSTEM NEEDS TO BE COMMON
  • OWNERS
  • CONTRACTORS
  • CRAFTSPERSONS

54
COMMON METHOD FOR CRAFT SKILL ASSESSMENT
  • IMPLEMENT A STANDARD SKILL ASSESSMENT PROGRAM
  • USE NATIONAL CENTER FOR CONSTRUCTION EDUCATION
    RESEARCH (NCCER) ASSESSMENTS

55
COMMON METHOD FOR CRAFT SKILL ASSESSMENTCONTINUED
  • RECIPROCITY
  • CONTRACTORS
  • DIFFERENT GEOGRAPHICAL REGIONS

56
KEY SUCCESS FACTORS
  • GTBR/CII PLAN AGREED TO BY
  • CONTRACTORS
  • PLANT MANAGERS OF OWNERS
  • AUGUST 2002
  • MANDATE USE OF NCCER SKILL ASSESSMENTS

57
COMMON REQUIREMENTS - DOCUMENTATION!!
  • UNION
  • DEPT OF LABOR PROGRAMS
  • MERIT SHOP
  • NCCER
  • SPECIALTY
  • COMPANY OR INDUSTRY PROGRAMS

58
IMPLEMENTATION TIMELINE - 2003
  • 1Q03 - IMPLEMENT
  • CONTRACTORS
  • OWNERS
  • ALL CORE CRAFTSPEOPLE SKILL ASSESSED - 1 APRIL
    2003
  • WRITTEN
  • HANDS-ON BY CONTRACTOR
  • DOCUMENTED

59
IMPLEMENTATION TIMELINE - 2004
  • BY JANUARY 2004
  • ALL CRAFTSMAN SKILL ASSESSED
  • WRITTEN
  • HANDS-ON BY CONTRACTOR
  • DOCUMENTED

60
SUMMARY
  • Q A SUMMARY
  • EMAILED LATER
  • CRITIQUE FORM
  • FILL OUT
  • ADDITIONAL COMMENTS
  • RETURN BEFORE LEAVING!

61
PHASE II
  • SAFETY
  • ENGINEERING CHG/SCOPE CREEP
  • CONTRACTING STRATEGIES
  • COST CONTROL
  • DOCUMENT CONTROL
  • OTHER TOPICS
  • FALL 2003
Write a Comment
User Comments (0)
About PowerShow.com