Title: LHCC Comprehensive Review 7
1LHCC Comprehensive Review 7 20.3. 2007 ALICE
Detector Installation and Commissioning
Overview Strategy, Status, Schedule of
Detector Installation and Commissioning
2Detector Installation Scenario
Baby spaceframe, spaceframe, frontabsorber,
backframe
The TPC arrives in a transport cradle (delphi
frame) and moves into the spaceframe to a
distance of 4.5m from the IP. All inner
detectors are installed and the TPC is finally
moved over the inner detectors to the IP.
3Connection of Detectors
C
A
Miniframe
TPC and all detectors inside the TPC are read out
50 to C side and 50 to A side. C side can be
connected right after installation ? start of
commissioning A side can only be connected when
the miniframe is in place
4Overall Constraints
The ALICE central detector installation ? TPC/
ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/ SSD/
SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/ V0-A/
FMD1/ PMD/ Dipole/ Beampipe/ Shielding is a
strict sequence that MUST be followed in exactly
this way. Also the installation of TOF, TRD and
PHOS is fixed in the sequence, because for this
installation the TPC transport cradle (Delphi
Frame) must be removed and the Miniframe must not
yet be there. A major part of the sequence
was exercised in an installation test in 2005
with the real TPC and 75 of the real
installation tooling. This test was presented to
the LHCC.
5Overall Constraints
The dimuon spectrometer is independent of this
installation sequence and is working its on a
schedule with the only constraint of being
ready on 31.8. 2007. ? See presentation of the
Muon spectrometer.
6Changes from CR6 (Mar. 2006) to CR7 (Mar. 2006)
Detectors installed and Vacuum closed 31.4.
2007 (CR6) ? 31.8. 2007 (CR7) 4
months Lowering of ITS Barrel 3.10. 2006
(CR6) ? done 15.3. 2007 5.3 months Start of
V0, T0 etc. installation 9.11. 2006
(CR6) ? planned 9.4. 2007 5 months We have
absorbed the 4 month additional time from the
LHC schedule for extended commissioning (TPC)
and termination of ITS. Using last years
installation schedule sequence we are one month
late. This month is regained by performing the
installation of the last 4 forward detectors
between vacuum closure and first beam
injection. We have not compressed the schedule.
It is still based on 5 8hour working days/week,
meaning that nights and weekends are
contingency. Our delays are from waiting for
detectors and not from increased installation
time.
7Status of Detector Installation
HMPID Sep. 24th 2006 TOF1 TOF2 Oct. 6th
2006 TRD1 Oct. 10th 2006 TPC Feb. 1st
2007 (CR6 Oct 1st ? 4 moths) SSDSDD Mar.
15th 2007 Beampipe Mar. 19th 2007 Ongoing Cle
arly, having the complete ITS detector was the
prime objective that justified the additional 6
weeks delay.
8Overall Commissioning Strategy
All sub detectors perform a combined DAQ/ECS/TRG
test at CERN with the final components on the
surface. Services and electronics are installed
before the detector is installed in the
cavern. Commissioning and checking of detectors
can start right after installation and
connection.
9Status of Detector Commissioning
TOF, TRD, HMPID, ACORDE are being connected at
the moment and commissioning in the cavern will
start within weeks. For all other detectors the
service installation is in full swing in order to
be ready when the detectors are installed. Racks
are ready to receive electronics. First
electronics crates are currently being installed.
10Dec 2006 1 TRD, 2 TOF
1
2
1
2
11July 2007 1 PHOS, 3 TRD, 7 TOF
5
7
1
1
2
3
2
3
4
6
PHOS Free HMPIDTRDTOF HMPIDTOF HMPID
1
122008 3 PHOS, 7 TRD, 18 TOF
17
15
11
14
9
5
7
7
5
1
1
2
3
2
3
4
4
6
8
6
10
12
16
13
18
3
2
1
13? 2009 5 PHOS, 18 TRD, 18 TOF
17
16
11
17
14
15
9
13
11
9
5
7
7
5
1
1
2
3
2
3
4
4
8
6
8
6
12
10
10
12
16
18
14
16
13
18
3
5
2
4
1
14TPC installation
Leaving the Cleanroom
15TPC installation
Leaving SXL2 Entering SX2
16TPC installation
Descending the Shaft
17TPC installation
Transfer to Magnet Alignment of Transport Frame
with Spaceframe
18TPC installation
Pulled into the magnet
19TPC installation
Pulled into the magnet
20TPC installation
Final Position
21TPC installation
Final position, alignment with nominal beam axis
to 1mm
22TPC installation
Move 4.6m back to parking position
23TPC installation
ITS Table
Feb 5th 2007, Ready for ITS
24ITS Lowering to the Cavern
15.3. 2007
25ITS Lowering to the Cavern
15.3. 2007
26ITS Lowering to the Cavern
15.3. 2007
27ITS Lowering to the Cavern
15.3. 2007
28Beampipe Installation and Bakeout
16.3. 2007
29Beampipe Installation and Bakeout
Bakeout planned to be terminated on 5.4. 2007
(before easter) ? Continue detector installation
on 9.4.
30(No Transcript)
31V0, T0
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Detectors are ready to be installed
32FMD3
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Detector is at CERN and ready to be installed
33Pixel detector
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Detector is at CERN and close to completion
34Connection of FMD,SPD,SDD,SSD ? Very difficult
part
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Cable, fiber, cooling connections, tests of
C-side 166 22 days
35FMD2
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
36Service Chariot Connections
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Cable, fiber, cooling connections, tests of
A-side 166 22 days
37Move TPC to final Position
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Pictures from Integration Test
Connection and full commissioning of TPC C-side
38BeampipeValve FIxation
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
39PHOS/EMCAL Support/TOF/TRD
40Miniframe
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
Connection and full commissioning of ITS and TPC.
41T0-A/V0-A/FMD1/PMD
TPC/ ITS barrel/ Beampipe/ V0-C/ T0-C/ FMD3/ SPD/
SSD/ SDD/ FMD2/ TPC/ Valve/ Miniframe/ T0-A/
V0-A/ FMD1/ PMD/ Dipole/ Beampipe/ Shielding
42Shielding
43Summary
The ALICE detector installation is a strict
sequence that is well established and was
extensively tested and studied. Delay was
accumulated due to waiting for ITS
detector. ITS is in place and the sequence is
again well under way. The detectors coming next
in the sequence are ready to be
installed. Certification of detectorsDAQ/ECS/TRG
on the surface is ongoing. Apart from the
installation of the detectors the main focus is
on installation and verification of services
(cables, fibres, cooling) in order to be able to
start detector commissioning right after
installation.