Title: ME31B: CHAPTER SEVEN
1ME31B CHAPTER SEVEN
- DESIGN OF EXTERNAL FACILITIES ONE
2INTRODUCTION
- This chapter deals with structures which are only
indirectly related to buildings, but which are of
great importance to the farmer. - These include roads, culverts, bridges and water
distribution systems related to farming
activities.
37.1 INTRODUCTION TO SIMPLE
ROAD DESIGNS
- Rural access roads range from the simplest earth
roads to bituminous surfaced highways. However,
earth roads are normally the only type that can
be justified for access to farmsteads. - These roads, designated as unimproved earth
roads, are generally suitable solely for light
traffic, up to some dozen or so vehicles per day,
and they often become impassable in the wet
season. - Heavy lorries, which sometimes need to have
access to farmsteads, should only be allowed on
this type of road after an adequately long dry
spell.
4Simple Roads Contd.
- There is no need for actual structural design of
unimproved roads, but there are some principles,
which if followed, will produce a reasonably good
road for the small investment that they justify.
57.1 Road Location
- A survey to determine the best location for a
road line starts by identifying areas through
which the road must pass, for example - A gap between hills, the best location for a
river crossing, and points to be linked by the
road. - Places to be avoided include soft ground, steep
slopes, and big rocks. In large scale road
projects the terrain is viewed from aerial
photographs, but for smaller projects this is too
costly and instead an overview of the proposed
road line must be obtained fromadjacent hills.
6Road Location Contd.
- Such an overview provides valuable information on
natural drainage, but should always be
supplemented by a detailed examination on foot. - Once the points through which the road must pass
have been established, the road line is laid out
to run as directly as possible between them
7Road Gradients
- A steep gradient not only slows down traffic and
limits the load a draught animal can pull, - The recommended gradient standards for unimproved
roads differ in different countries, but
generally, for roads used mainly by motor
vehicles, the gradient should not exceed 1 in 17
in flat or rolling terrain, 1 in 13 in hilly
terrain, or 1 in 11 in mountainous terrain. - In exceptional cases it may be necessary to have
steeper gradients, but their maximum length
should then be limited.
8Road Curves
- A straight road is the shortest distance between
two points, but this may not be the most
economical line for a durable, easily constructed
road which is passable throughout the year. - Long gentle curves are preferred since there is
better visibility and less speed reduction
necessary than on a sharp corner. The minimum
radius for a horizontal curve is 15m but 30m or
more is preferable.
9Road Slopes
- Only occasionally will an unimproved road require
embankments or cuttings, but where it cannot be
avoided, the side slopes should not exceed 1 in 1
on well-drained soils. In wet soil it should not
exceed 1 in 3, i.e. one unit rise in three units
of horizontal distance. - These are maximum values and should only be used
where the depth of the cut or fill is so large
that to reduce the slope would be too expensive.
10Road Camber
- The camber is the slope of the road surface to
the sides designed to shed water into the side
drains. - A simple earth track has no camber and no side
drains. But all other roads should have a camber
of 5 to 7 from the middle of the road, thus
shedding water into both side drains. In deep
cuts (where the road is dug into a hill side) or
on sharp curves, the camber is designed to drain
water from the whole surface inwards toward the
cut or to the inside of the curve.
117.1.6 Cross Section of a Simple Earth Track
- The simplest earth track is obtained by merely
clearing vegetation and stones from the natural
soil surface. - It may run between fields within a farm, from the
main road to a farmstead or between small
villages where the traffic volume is very low. - Earth tracks are based on single lane traffic in
one pair of wheel tracks, but vegetation should
have been cleared wide enough to allow for two
small cars to meet.
12Cross-Section of a Simple Earth Track
13Cross Section of an Upgraded Earth Road
- These roads may be used to connect rural
market centres and villages where the traffic
volume is 10 to 20 vehicles per day including
some heavy lorries in the dry season. - Generally the only affordable surface material
is the soil found on the line of the road or in
its immediate surroundings. - The bearing capacity of the road depends on
the type of soil and the prevailing climatic
conditions.
14Cross Section of an Upgraded Earth Road Contd.
- The road is constructed by digging out soil from
the sides and throwing it on the road until the
cross section illustrated in Figure below is
obtained. - The 30 cm difference in level between
- the road surface and the bottom of the side
drains, combined with the camber of the road
surface, will ensure a much drier roadway with
higher carrying capacity than the simple earth
track.
15(No Transcript)
16(No Transcript)
17Methods For Improving Earth Roads
- Gravelling Reduces the risk of mud forming
- Paving with pit run or with pitch
- Grassing to improve their strengths
- Constructing side drains
- These improvements are common on earth roads in
Trinidad including Nariva Swamp
187.1.8 Road Construction
- When the land has been surveyed and the most
feasible road line has been found, the centre
line of the road is set out with pegs inserted at
15 to 20m intervals and tall enough to be clearly
visible. - Additional pegs may be installed to mark the
width of the roadway, side drains and the area to
be cleared. - Stumping and Clearing
- To construct a simple earth road, trees and rocks
must be cleared from the road line and well back
from the road so that sun and wind can dry the
road surface.
19Road Construction Contd.
- If the objective is to construct a high-level
earth road, the work will continue with the
construction of side drains. - Construction of Side Drains
- Using wooden pegs and string as a guideline, the
edge of the road should be established 1.8 to
2.0m from the center line. - On roads with no cross-fall, side drains are dug
out of either side to a depth of 150 mm and half
the width of the roadway. - All soil thus dug out is thrown on to the road
and spread to form an even road surface with
correct camber.
207.1.8 Road Maintenance
-
- The most important maintenance job on any type of
earth road is to ensure that all drains work
properly and that additional drains are installed
wherever it becomes necessary. - Secondly, rutted wheel tracks should be filled in
with soil from outside the road bed. - If the road surface becomes badly deteriorated
it will be necessary to resurface the road by
adding more soil from the side drains.
217.1 Culverts
- Where the road crosses a natural water way, a
culvert or bridge should be built. -
- Culverts are best suited for streams with steep
banks, since their construction requires some
difference in height between the level of the
road surface and the bed of the stream.
22Culverts Contd.
- Culvert construction consists of the following
- 1 The actual culvert (one or more pipes), which
carries the water under the road. - 2 The embankment, which carries the road across
the water course. - 3 Wing walls, which protect the embankment from
flood water and direct the flow into the culvert. - 4 The apron at the discharge end, which prevents
erosion of the stream bed.
23(No Transcript)
24Culverts Contd.
- The normal water flow is carried by the culvert,
but large flows of storm water are allowed to
flow over the top of the embankment. - Concrete pipes, 400 to 900 mm in diameter, are
often used for culverts. - The diameter and number of pipes is determined by
the expected water flow. - Alternatively corrugated steel pipes or masonry
work in burnt bricks, concrete blocks or stone
may form the culvert.
25Culverts Concluded
- Where concrete pipes have been used for a
culvert, the embankment must provide for a soil
cover above the pipe to a depth at least equal to
the diameter of the pipe in order to sufficiently
protect the pipes from the load of heavy
vehicles. - The beams in the ceiling of a square shaped
culvert with masonry walls may be designed to
carry the load of vehicles, thus reducing the
need to spread the load in the embankment by a
soil cover.
267.1 Simple Bridges
- The ideal site for a bridge is where the river is
narrow and the banks are solid. - The bridge should be designed to interfere as
little as possible with the natural flow of
water. - The highest level, which the river is known to
have reached, is determined and the bridge
designed to give at least 0.5m clearance above
that level.
27(No Transcript)
28Components of Simple Bridges
- 1. Abutments, the structures provided to
strengthen the stream banks and adequately
support the shore end of the road-bearing beams. - They can be constructed of concrete, masonry work
(stone, brick, concrete blocks) or timber. The
lower part of the abutments will normally require
wing walls to protect them from the action of the
stream. - Intermediate supports installed where the stream
is too wide to be bridged in a single span.
Timber trestles, masonry piers and reinforced
concrete columns are the most common types of
support.
29Components of Simple Bridges Contd.
- 2. Road-bearing beams that carry the weight of
the roadway and traffic between abutments and
any intermediate supports. Simple bridges have
road-bearing beams consisting of round or sawn
timber or universal steel beams spaced about 600
mm center-to-center across the roadway. - For example, a bridge 3.0m wide requires 6 beams
and a bridge 3.6m wide, 7 beams etc. - The beams are usually designed as simple beams
supported at the ends.
30Components of Simple Bridges Contd.
- 3. Decking or flooring, which make up the road
surface on the bridge. - Where poles or other rough materials have been
used for decking a smoother surface can be
obtained by putting planks along the bridge for
the wheel tracks. - The decking should be strong enough to spread the
load from one wheel over at least two
road-bearing beams. Wooden decking should never
be covered with soil, since that will increase
decay and disguise any weakness in the bridge.
31Components of Simple Bridges Concluded
- 4. Curbs made from poles or pieces of timber
should be secured to the edges of the decking.
Curbs will reduce the risk of vehicles slipping
over the edge and will also, if positioned over
the outer road-bearing beams and well secured to
them, contribute to the strength of the bridge. - 5. Rails along the edges of the bridge for
safety.
32Concluding Remarks About Simple Bridges
- The bridge must be designed to carry the weight
of the members of the bridge (dead load) and the
weight of any traffic moving across it (moving
load). - In order to simplify calculations, the moving
load is often converted to an equivalent live
load by multiplying it by 2. - When a heavy lorry moves across the bridge, the
bridge will carry concentrated loads from the
wheels with spacing equal to the wheelbase and
tread-width.
33Concluding Remarks About Simple Bridges Contd.
- In a bridge of short span the largest bending
moment in the road-bearing beams will occur when
the back wheels which carry the greatest weight
are at the centre of the span and will be
determined by half the weight on one wheel, since
the decking is designed to distribute the load to
at least two beams. - In a bridge of longer span where both front and
rear wheels may be on the span at the same time,
the maximum bending moment will occur when the
centre of the wheel base is a short distance from
the centre of the span.
34Concluding Remarks About Simple Bridges
- In addition to bending, shear may have to be
considered in short spans, and deflection for
long spans. - Where bridges are constructed with rough
materials under unfavourable conditions, a
larger factor of safety should be used.
357.1 DESIGN OF WATER DISTRIBUTION SYSTEMS
- 7.4.1 Demand and Consumption of Water
- Consumption is the amount of water used in
reality e.g. in domestic needs. It rises to
demand according to water supply improvements. - Demand is the amount of water that would be used
by consumers if available, under specific
conditions of price, quality and others.
36Uses of Water
- Water is normally used for domestic, tourist,
fire-fighting, industrial, agricultural (mainly
irrigation) and hydro-electricity. - Typical domestic water use in the Caribbean is
given in Table 7.1 below.
37(No Transcript)
38Agricultural Water Use
- The agricultural consumption is mainly the crop
water requirements, usually higher than human
needs. In the Caribbean region, this ranges from
1 to 1.5 m (gross) per crop per season. This
amounts to about 10 to 15 million litres per crop
per season. - Another form of agricultural consumption is
livestock requirement, which can be about 64
litres per hr per day for cattle.
39Water Contd.
- Design should be based not on present water
demand but on future demand estimation which is
normally obtained by extrapolation.
40(No Transcript)
41(No Transcript)
427.4.2 Storage and Distribution of Water
- Service Reservoirs Storage in water supply
network - 7.4.3.1 Purposes for Storage
- (i) To balance supply and demand
- (ii) Protection against breakdown
- (iii) To provide a static head for gravity
running - (iv) Water treatment.
43Siting and Capacity of Reservoir
- 7.4.3.2 Siting of Reservoir It should be sited
as close as possible to point of use within
constraints of available relief. This is to
reduce the pipe cost due to the higher discharge
from storage to points of use. - 7.4.3.3 Capacity of Reservoir Inflows should be
kept fairly even. Outflows can be peaked.
Storage is used to balance uniform inflow and
non-uniform outflows. If inflow is greater than
outflow, then water is getting into storage and
if outflows is greater than inflows, water is
coming out of storage.
44(No Transcript)
45(No Transcript)
467.4.3.4 Pipes
- There are three categories of pipes
- (i)MainsTrunk - not tapped and Distribution
Mains supply water. They have relatively large
diameter and are used for conveyance and
distribution. Materials used include cast iron,
spun iron, asbestos, cement, or steel. - (ii) Service Pipes Individual supply lines to
farms, houses and hospitals or standpipes.
Materials used include copper, steel, plastics
(PVC or polyethylene). - (iii) Plumbing Pipe work within the building
477.4.3.4 Pressure Classes of Pipes
- There are three important pressures associated
with pipes. - (i) Work Test 2 to 3 times the working
pressure. It is the pressure used to test
manufactured pipes. - (ii) Maximum Field Test One and half times the
working pressure. The specified design pressure
should be tested in the field. - (iii) Maximum Working Pressure Maximum pressure
derived in the field. There are three classes of
maximum working pressures e.g. polyethylene Class
B- 6 bars, Class C - 9 bars and Class D 12
bars.
487.4.3.4 Pipeline Design
- The selection of pipes is an economic tradeoff
between large diameter which will give high
capital cost and low friction losses and low
pumping costs (if there is pumping) OR small
diameter, which will involve low capital cost,
more head losses and more pumping cost. - Energy cost is a function of head losses while
pipe cost is a function of diameter.
49Allowable Head Losses
- (i) Allow 1 m (for big pipes) to 10 m (small
pipes) head loss per 1000 m of mainline - (ii) Using velocity as criteria as head loss
effects is related to velocity. - Normal practice in water supply for irrigation is
to keep velocity within 0.6 to 1.5 m/s. Above
that, there can be water hammer or high rates
of corrosion. Water hammer is transient high
pressure waves due to rapid valve closure. Below
0.6 m/s, there may be silting or sediment
deposition. - Pipe diameter can be chosen using head losses and
velocity using charts or equations.
507.4.3.4 Pipe Layout Types of Distribution
Systems
- (i) Individual Pipes Connects two points in the
distribution system say from a reservoir to the
point of use.
51Example 1 A reservoir (Figure 7.7) is situated
65 m vertically above some farm buildings. The
length of pipe required to lead water from the
reservoir is 750 m and the pressure required at
the buildings is 30 m head. Rate of flow
required is 2 m3/h (2000 litre/hr).
52Solution
- If the head available due to the height of the
reservoir is 65 m, and the pressure head needed
at the buildings is 30 m, the head available for
overcoming friction is 65 30 35 m being the
difference in head between the ends of the pipe.
- The equivalent length of the pipe is
- Actual length (750 m) 10 (75 m)
- 825 m
- Plus (say) 1 tap 2 stop taps 135 m
- Total 1060 m
53Solution Concluded
- The hydraulic gradient is Pressure difference/
equivalent length 35/1060 1/30 - Since the maximum head is 65 m, a Class C (9 bar
or 90 m) pipe is required, and referring to Chart
provided, it can be seen that a 32 mm nominal
(internal) diameter Class C low density polythene
pipe would satisfy these requirements. - Velocity is about 0.8 m/s which is acceptable
(within 0.6 and 1.5 m/s).
54Chart
55(ii) Branching System
- The advantages are relatively few joints and the
system is easy to build and design. - The disadvantages are that sediments may
accumulate at dead ends of the pipe. Secondly,
it there is pipe bursts, a total cut off for zone
beyond failure results. - This means that in case of bursts, the system
will be cut off. - Also there is limitations in adding to the system
beyond a certain point. - Because of these disadvantages, branch system is
used in small community projects.
56(No Transcript)
57Solution Computation Table
Pipe Sect. Flow (m3/h) Length (m) Pipe Dia mm Head Loss (m/100 m Flow Vel m/s Head Loss (m) Elev. of hydr. Grade (m) Ground level elev (m) Press Head (m) Rem.
AB 2.9 700 32 3.3 0.85 23 A 260 B 237 189 46 O.K
BC 0.5 825 19 1.6 0.5 13 B 237 C 224 219 5 Just O.K
58Explanation of Table
- The average of the maximum and minimum pressure
required at A is 41 m. - If you subtract the minimum pressure needed at B
(5 m) from 41 m, you get 36 m. - Since the length of the pipe is 700 m, the
hydraulic head loss is 36/700 0.051 5/100
1/20. - With the discharge of 2.9 m3/h and head loss of
1/20, the next higher diameter of pipe is 32 mm
from the chart.
59Chart
60Explanation of Table Contd.
- With now 32 mm diameter pipe chosen in column 4
of the Table, and the same flow rate, the actual
head loss is now 1/30 from the chart which is 3.3
m/100m as shown in column 5. - The flow velocity is about 0.85 m/s which is
acceptable. - The head loss is now (3.3 x 700)/100 23 m. At
A, the elevation of the hydraulic grade line is
now 41m ground elevation (219 m) 260 m.
61Explanation of Table Contd.
- For B, it is 260 minus the head loss (23 m) which
is 237 m. - The ground elevation at B is 189, so the pressure
head of water is 237 189 48 m which is
adequate. - For Pipe BC, the design flow is 0.5 m3/h. The
hydraulic grade line at B is still 237 m and the
elevation at C is 219 m. - The hydraulic grade line required at C is 219 m
plus 5 m head of water, making a total of 224 m.
62Explanation of Table Concluded.
- The hydraulic gradient from B to C is then (237
224)/825 0.016 which is 1.6/100 1/60. - With hydraulic gradient 1/60 and the flow rate
of 0.5 m3/s, the diameter of pipe from the Chart
is exactly 19 mm. - The velocity is 0.5 m/s which is barely
acceptable. - The head loss is 0.016 x 825 m 13 m.
- The hydraulic grade line at C is therefore 237 m
13 m, which is 224 m. This will give the
pressure head of 5 m required at C.
63(iii)Grid Pattern/Looped Network
- Interconnected pipes water reaches a point from
a number of directions. - The advantages are that there will be no
stagnation i.e. no dead ends and during repairs
(pipe burst), there will be no need for complete
cutoff. - Only some parts of the system will be cut off.
There are also more even pressures throughout the
system. - The disadvantages are that the designs are more
complicated and there are more pipes and more
fittings.
64Pipe Network Analysis Using the Hardy Cross
method.
- The Hardy Cross system is used for water flow
analysis in a more complex system
than the dead end system. - There are two principles In any closed loop
65(No Transcript)
66(No Transcript)
67Procedure For Analysis
- 1. Assign assumed flows to each pipe segment in
network such that at each junction
- 2. Calculate hf for each pipe using for example
Hazen Williams equation - hf 10.67 CH -1.85 D- 4.87 Q1.85 L
- Where hf is head loss (m), CH is roughness
coefficient of pipe material D is diameter of
pipe (m), Q is water flow rate (m3/s) and L is
length of pipe (m).
68(No Transcript)
69Procedure Concluded
- For any pipe that occurs twice, do the
- correction for the two loops.
-
-
-
- BC occurs twice.
- 8. Repeat from step 2 until desired accuracy is
obtained.
B
E
A
D
F
C
70Example
71Solution
- ABDE is one loop as shown above and BCD is the
second loop. - Note that the clockwise water flows are positive
while the anti-clockwise ones are negative. - Positive and negative flows give rise to positive
and negative head losses respectively
72(No Transcript)
73(No Transcript)
74(No Transcript)
75(No Transcript)
76(No Transcript)
77Final Water Flows